Cleaver Brooks Company, Inc. v. B&K Mechanical Contractors, LLC, doing business as Grunwald Mechanical Contractors & Engineers; Amerisure Mutual Insurance Company

District Court, D. Nebraska·Decided August 5, 2026·No. 4:23-cv-03243·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEBRASKA

CLEAVER BROOKS COMPANY, INC.,

Plaintiff and counterclaim defendant,

vs. 4:23-CV-3243 B&K MECHANICAL CONTRACTORS, LLC, doing business as Grunwald Mechanical MEMORANDUM AND ORDER Contractors & Engineers,

Defendant and counterclaimant,

and

AMERISURE MUTUAL INSURANCE COMPANY,

Defendant.

This is a breach of contract case involving two contractors: Grunwald Mechanical Contractors & Engineers, and the Cleaver Brooks Company. The parties contracted on a government project, but fell out over Grunwald's failure to make partial payments that Cleaver Brooks thought Grunwald was required to make. Each party accuses the other of breaching their agreement, and the parties have very different views on what that agreement entailed. The Court concludes that while Cleaver Brooks is not entirely right about the scope of the parties' agreement, it is right enough to establish that Grunwald breached that agreement. But while Cleaver Brooks has proved liability, it hasn't proven the amount of its damages as a matter of law. Accordingly, the Court will partially grant Cleaver Brooks' motion for summary judgment on its breach of contract claim.

I. BACKGROUND Cleaver Brooks is a Texas corporation that manufactures boiler room products. Filing 64 at 1.1 Grunwald is an Omaha contractor. Filing 64 at 1-2. In 2021, the Department of Veterans Affairs contracted with Spees- Hernandez JV 2, LLC for the installation of three boilers at the Omaha VA Medical Center. Filing 73 at 27; filing 72-1 at 8-51. Their contract required Spees-Hernandez to complete its work 425 days after the VA gave Spees- Hernandez notice to proceed, and allowed the VA to withhold damages from the contract price for a failure to complete the project on time. Filing 72 at 28. Spees-Hernandez, as the general contractor, subcontracted with Grunwald for installation of a new boiler system. Filing 73 at 28. In October 2021, Cleaver Brooks submitted a proposal ("the Proposal") to Grunwald for production of a D-Style Boiler for the project. Filing 64 at 2; filing 67-3; filing 73 at 29. The Proposal is one of the three documents central to the parties' dispute. The Proposal included "milestone payments" providing for specified percentages of the total price to be paid upon commencement or completion of certain stages of the project. See filing 64 at 2-3; filing 67-3 at 31. The Proposal

1 Pursuant to NECivR 56.1, a party moving for summary judgment must include in its brief a statement of material facts about which the movant contends there is no dispute, and the party opposing summary judgment must include in its brief a concise response to that statement of facts, noting any disagreement. Properly referenced material facts in the movant's statement are considered admitted unless controverted in the opposing party's response. NECivR 56.1(b)(1)(B). also included a percentage-based schedule for liquidated damages if the project was canceled. Filing 64 at 3; filing 67-3 at 31. Several months later, Grunwald decided to proceed with Cleaver Brooks and the parties began exchanging emails about the terms of their agreement. Filing 64 at 4. After receiving a draft purchase order from Grunwald, Cleaver Brooks' project manager replied that there were "a few things missing on the PO that we'd normally like to see": • Reference to our proposal • Desired delivery date (even if estimate) • Milestone payment schedule • Mutually agreed-upon legal T&C's Filing 64 at 4; filing 73 at 29-30. Grunwald's project manager replied as follows: • Reference to our proposal o We will reference this in our subcontract • Desired delivery date (even if estimate) o The preliminary schedule our GC had put together had the new boilers being delivered on 11/11/2022. This schedule is being worked out with the VA but that is the date we should work toward as of today. • Milestone payment schedule o We can work on a payment schedule. Are there milestones you typically use? • Mutually agreed-upon legal T&C's o We will issue these in our subcontract. Filing 64 at 4-5; filing 67-5 at 2-3; filing 73 at 30. A few minutes later, Cleaver Brooks' project manager replied, "Regarding milestone payments, our proposal contains a typical schedule on pg. 30. We are flexible and can work with you on these if needed. Our goal is to try and keep things cash-neutral for both parties." Filing 73 at 30; filing 67-5 at 1. Grunwald sent Cleaver Brooks a draft agreement. Filing 73 at 30. After receiving it, Cleaver Brooks' project manager described it to Cleaver Brooks' director of sales in internal correspondence:

After this morning's call with VA contractors, we now have the flowdown subcontract T&C's (attached, along with last week's signed PO). Notes: • Our proposal is now referenced in subcontract • They've agreed on-site date is a moving target based on our schedule (basically, they will build to our schedule) • They are open to milestone payments, although they are not reflected in this document • We need to review the rest of the legal language. Filing 73 at 31; filing 72-3 at 3. The director of sales replied noting that the draft referenced terms and conditions "on the reverse side" that he wanted to see, because "[t]he flowdowns don't seem to capture all the normal T&C language." Filing 73 at 31; filing 72-3 at 3. So, the Cleaver Brooks project manager asked Grunwald to either provide a copy of the referenced terms and conditions or state that they didn't apply. Filing 73 at 31; filing 67-6 at 3. Grunwald clarified that the "terms and conditions" referenced didn't apply to this purchase order. Filing 73 at 31; filing 67-6 at 3. Cleaver Brooks' project manager privately told his sales director that he liked that answer, and suggested that perhaps "the 'normal' terms missing in the subcontract are covered by T&C's in our proposal, which is referenced in subcontract?" Filing 73 at 32; filing 72-3 at 4. The sales director replied, asking, "Think we could get him to add something like 'including applicable commercial terms' to our proposal reference?" Filing 73 at 32; filing 72-3 at 4. So, Cleaver Brooks' project manager responded to Grunwald, noting that the draft didn't include "things that are specific to boiler equipment, like maintaining water quality for warranty, etc." Filing 67-6 at 2; filing 67-6 at 2. He suggested adding "including applicable commercial terms" to the draft's reference to the Proposal, so that it would describe the project as "Department of Veteran Affairs 4101 Woolworth Ave, Omaha NE 68105 ; Correct Mechanical Deficiencies Project 636-19-301 Purchase of D-Style Boiler 07310929-Proposal -Rev-0 Dated October 4, 2021 including applicable commercial terms." Filing 64 at 5; filing 67-2 at 2; filing 73 at 32. Grunwald replied, "Yes, that should be fine." Filing 64 at 6; see filing 73 at 32. Later the same day—June 2, 2023—Cleaver Brooks' project manager contacted Grunwald asking about milestone payments: I forgot to ask if you would accept our milestone payments below? Your subcontract included language about submitting for progress payments, which isn't really applicable to an OEM equipment supply contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Cleaver Brooks Company, Inc. v. B&K Mechanical Contractors, LLC, doing business as Grunwald Mechanical Contractors & Engineers; Amerisure Mutual Insurance Company, (D. Neb. 2026).

Cleaver Brooks Company, Inc. v. B&K Mechanical Contractors, LLC, doing business as Grunwald Mechanical Contractors & Engineers; Amerisure Mutual Insurance Company (Cleaver Brooks Company, Inc. v. B&K Mechanical Contractors, LLC, doing business as Grunwald Mechanical Contractors & Engineers; Amerisure Mutual Insurance Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Torgerson v. City of Rochester
643 F.3d 1031 (Eighth Circuit, 2011)
Quinn v. St. Louis County
653 F.3d 745 (Eighth Circuit, 2011)
Barber v. C1 Truck Driver Training, LLC
656 F.3d 782 (Eighth Circuit, 2011)
Satcher v. UNIVERSITY OF ARK. AT PINE BLUFF BD.
558 F.3d 731 (Eighth Circuit, 2009)
Leo A. Daly Co. v. Omaha-Douglas Public Building Commission
324 N.W.2d 252 (Nebraska Supreme Court, 1982)
Cleasby v. Leo A. Daly Co.
376 N.W.2d 312 (Nebraska Supreme Court, 1985)
Traudt v. Nebraska Public Power District
251 N.W.2d 148 (Nebraska Supreme Court, 1977)
Rowe v. Allely
507 N.W.2d 293 (Nebraska Supreme Court, 1993)
Acklie v. Greater Omaha Packing Co.
306 Neb. 108 (Nebraska Supreme Court, 2020)
Brock v. Lueth
4 N.W.2d 285 (Nebraska Supreme Court, 1942)