Leo A. Daly Co. v. Omaha-Douglas Public Building Commission

324 N.W.2d 252, 212 Neb. 533, 1982 Neb. LEXIS 1243
CourtNebraska Supreme Court
DecidedSeptember 3, 1982
Docket44069
StatusPublished
Cited by8 cases

This text of 324 N.W.2d 252 (Leo A. Daly Co. v. Omaha-Douglas Public Building Commission) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Leo A. Daly Co. v. Omaha-Douglas Public Building Commission, 324 N.W.2d 252, 212 Neb. 533, 1982 Neb. LEXIS 1243 (Neb. 1982).

Opinions

Per Curiam.

Plaintiff, Leo A. Daly Company, appeals to this court from the judgment entered by the District [534]*534Court for Douglas County, following trial to the court sitting without a jury, in favor of the defendant, Omaha-Douglas Public Building Commission, in an action brought by the plaintiff to recover for extra services and expenses performed by the plaintiff in connection with the construction of the Omaha-Douglas County Civic Center, or, to be more specific, for services and expenses of the plaintiff in the subsequent repair or rebuilding of a slurry wall along Farnam Street which had collapsed during the course of construction of the civic center. We affirm the judgment of the District Court.

By way of background, the record reveáis that on October 9, 1968, Daly and the Omaha-Douglas County Civic Center Corporation entered into an agreement in which the civic center employed Daly to serve as an architect for the construction of the Omaha-Douglas County Civic Center, which contract was subsequently assigned to the Omaha-Douglas Public Building Commission. This contract for architectural services shall hereinafter be referred to in this opinion as the 1968 contract. As previously stated, on January 19, 1974, almost 6 years after the execution of the 1968 contract, a slurry wall along Farnam Street and adjacent to the civic center collapsed during the course of the construction. Almost immediately thereafter, to wit, on January 30, 1974, the various parties who had performed work or supplied materials for the construction of the civic center entered into an agreement to cooperate for the purpose of minimizing any delay in the construction of the building and any losses that might ultimately result therefrom. This agreement was signed by the Omaha-Douglas Public Building Commission, County of Douglas, City of Omaha, Leo A. Daly Company, Metropolitan Utilities District, P & Z Co., Inc., and Hawkins Construction Company, and will hereafter be referred to in this opinion as the seven-party agreement, or as the 1974 agreement.

[535]*535Subsequent to the execution of the seven-party agreement above referred to, the plaintiff performed corrective work on the collapsed slurry wall, and the action brought by plaintiff in the District Court was for the purpose of recovering its labor costs and outside consulting costs with reference to the replacement of that wall. Plaintiff’s action did not involve recovery on a quantum meruit theory, nor did it involve claims of unjust enrichment, those doctrines not having been pleaded.

It will be helpful at this point to examine the pleadings upon which the case was tried before the district judge. In its second amended petition, filed in the District Court for Douglas County on October 6, 1978, plaintiff alleges the execution of the October 9, 1968, agreement and its subsequent assignment to the defendant. The petition further alleges that on January 30, 1974, following the collapse of a portion of the foundation wall on January 19, 1974, the plaintiff, defendant, and others entered into the seven-party agreement, and a copy of that agreement is attached to the petition. Plaintiff specifically alleges as follows: “Plaintiff performed all of its duties under the contract of October 9, 1968 including extra services and disbursements incidental to unusual circumstances as provided in sections III (B) of Exhibit ‘A’ and as required by Exhibit eD\” (Emphasis supplied.) Exhibit D, referred to, is the seven-party agreement.

Plaintiff further alleges that the extra services were rendered and expenditures made at the request and with the approval of the defendant; that the defendant is the proper party to bring a suit to determine the liability for the collapse, but has not done so; and, further, that plaintiff submitted to defendant a statement for the extra work but that defendant has refused payment thereof.

It is to be noted that the plaintiff in its petition pleads both the 1968 contract and the 1974 agree[536]*536ment and alleges that the work was performed under both contracts, thereby admitting judicially in its pleading that the work was performed under the 1974 agreement as well as under the 1968 contract.

The 1968 contract between the Commission and the architect sets out the duties of the architect and divides such duties into basic services for which an agreed fee was to be 6 percent of the construction costs, to be paid monthly as certain levels of construction were reached. This case does not involve this type of charge. However, the 1968 contract also provides for the payment of extra services of the architect “if performed due to unusual circumstances,” and provides that the extra expense shall be paid for by the nonprofit corporation as a “Multiple of Direct Personnel Expenses,” including, generally, making planning surveys and special analyses; making measured drawings of existing construction; revising previously approved drawings or specifications to accomplish changes ordered by the nonprofit corporation; consultation concerning replacement of any work damaged by fire or other cause during construction, and furnishing professional services of the type set forth in the preceding paragraph of the original contract as may be required in connection with the replacement of such work; arranging for the work to proceed should the contractor default due to delinquency or insolvency; providing for contract administration and observation of construction; preparing “as-built” drawings, showing construction changes in the work, etc.; and the cost of all reproductions of drawings, and the cost of any special consultants, etc.

In its brief on appeal plaintiff contends that it is entitled to recover its expenses because of the provisions of the 1968 contract, which it claims is applicable. Defendant, however, claims that the work in reconstructing the slurry wall was performed under the provisions of the 1974 agreement and not under [537]*537the 1968 contract, and that plaintiffs right to recover depends upon the terms and provisions of the seven-party agreement, a copy of which is attached to plaintiffs second amended petition and was also received in evidence during the trial. Because of the importance of this issue, we discuss this latter agreement in some detail.

The purpose of the seven-party agreement entered into by all the parties engaged in the construction of the civic center is well summarized in the opening paragraphs of that agreement, and we quote those paragraphs in full: “WHEREAS, the Omaha Douglas Public Building Commission, hereinafter called ‘Commission’, engaged Leo A. Daly Company, hereinafter called ‘Daly’, to design and supervise the construction of a building designated in the construction contract as The City of Omaha and Douglas County Administration Building, and now known as the Omaha Douglas Civic Center, to be located on the block bounded by 18th and 19th Streets and by Famam and Harney Streets, Omaha, Nebraska; and,

“WHEREAS, the City of Omaha, hereinafter called ‘City’, and Douglas County, hereinafter called ‘County’, each have representatives among the membership of said Commission; and,

“WHEREAS, the Commission awarded the general contract for the construction of said building to Hawkins Construction Company, hereinafter called ‘Hawkins’; and,

“WHEREAS, Hawkins entered into a subcontract with P & Z Co., Inc., for the construction of the slurry wall system surrounding the building; and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderzhon/Architects, Inc. v. 57 Oxbow II Partnership
553 N.W.2d 157 (Nebraska Supreme Court, 1996)
ACME Investment, Inc. v. Southwest Tracor, Inc.
911 F. Supp. 1261 (D. Nebraska, 1995)
STATE FARM MUT. AUTO. INS. v. Royal Ins. Co.
382 N.W.2d 2 (Nebraska Supreme Court, 1986)
Nerud v. Haybuster Manufacturing, Inc.
340 N.W.2d 369 (Nebraska Supreme Court, 1983)
Hinz v. Hinz
338 N.W.2d 442 (Nebraska Supreme Court, 1983)
Holt County Cooperative Ass'n v. Corkle's, Inc.
336 N.W.2d 312 (Nebraska Supreme Court, 1983)
Leo A. Daly Co. v. Omaha-Douglas Public Building Commission
324 N.W.2d 252 (Nebraska Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
324 N.W.2d 252, 212 Neb. 533, 1982 Neb. LEXIS 1243, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leo-a-daly-co-v-omaha-douglas-public-building-commission-neb-1982.