Clean by Lucy, Inc.

CourtArmed Services Board of Contract Appeals
DecidedMarch 1, 2016
DocketASBCA No. 58432, 58441, 58442
StatusPublished

This text of Clean by Lucy, Inc. (Clean by Lucy, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clean by Lucy, Inc., (asbca 2016).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) Clean by Lucy, Inc. ) ASBCA Nos. 58432, 58441, 58442 ) Under Contract No. W9124M-05-D-0014 )

APPEARANCE FOR THE APPELLANT: Leonard W. Childs, Jr., Esq. Childs & Associates Savannah, GA

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq. Army Chief Trial Attorney CPT Megan E. Mahaney, JA Trial Attorney 1

OPINION BY ADMINISTRATIVE JUDGE THRASHER

These appeals arise from Clean by Lucy, Inc. (CBL), performing 31 task orders {TOs) under an Indefinite-Delivery/Indefinite-Quantity (ID/IQ) contract in support of the renovation and modernization of barracks on Fort Stewart, Georgia. On 17 September 2012, CBL filed 17 appeals with the Board. Fourteen of the appeals were decided under the Board's expedited procedures (Rule 12.2) in our decision on 14 June 2013 (ASBCA No. 58331 et al.). Our decision in the expedited appeals has no precedential value. Therefore, we are not bound by that decision or our findings of fact in that decision. However, we consider it reasonable that the evidentiary record produced in arriving at that decision, including the transcript of the first hearing, under the circumstances involved with these appeals, be considered part of the evidentiary record in the instant appeals. The evidentiary record from that decision involved a hearing on 6 and 7 May 2013 that produced a two-volume hearing transcript; a Rule 4 file; and a stipulation of fact between the parties regarding authority of Mr. Terrence Johnson. The Rule 4 file in the first set of appeals, as supplemented, is the same Rule 4 as in the instant appeals. Much of evidence produced at the first hearing directly addresses issues found in these three appeals. However, the parties have withdrawn the stipulation of fact regarding Mr. Johnson's authority entered into during the first hearing. Consequently, it is not part of the record in these appeals. A hearing was held and only entitlement is at issue. The Board has jurisdiction over the dispute pursuant to the Contract Disputes Act (CDA) of 1978, 41 u.s.c. §§ 7101-7109.

1 At various times during these appeals, the government was also represented by MAJ Joseph K. Venghaus, JA, Erica S. Beardsley, Esq., MAJ James P. Leary, JA, and MAJ Ildiko Szentkiralyi, JA. FINDINGS OF FACT

1. Fort Stewart and Hunter Army Airfield, Georgia, were notified in 2005 that a large group of Army troops were scheduled to return from operations in Iraq within 90 days and would be billeted at Fort Stewart and Hunter Army Airfield. At the time, Fort Stewart and Hunter Army Airfield did not have the existing capacity to house these troops in existing barracks. Although there were several empty barracks on the bases, the barracks required substantial renovation before they would be habitable. As a result, this mission imperative generated a requirement for Fort Stewart and Hunter Army Airfield to renovate 33 existing barracks within 90 days to accommodate the returning troops. This project was generally referred to as the barracks reset project (reset project). 2

2. Rather than contracting with a single general contractor to manage the overall reset project, the government chose to manage the reset project directly by employing an acquisition strategy where the government would contract directly with individual contractors for specific segments of the renovation project, such as heating and cooling, painting, flooring, etc. (tr. 2/152-55; R4, tab 1 at 2). 3 As a result, the government assumed responsibility for scheduling the various contractors and managing any scheduling conflicts between the contractors that might arise. In this regard, the solicitation pertinent to these appeals (and subsequent contract) incorporated by reference FAR 52.236-8, OTHER CONTRACTS (APR 1984 ), which put CBL on notice that other contractors might be working within the same area of their work (R4, tab 1 at 450).

3. The government issued invitations for bids to perform the various segments of the barracks reset project. Pertinent to these appeals, was a solicitation for an ID/IQ contract, to provide services for the removal and installation of floor coverings for the buildings at Fort Stewart and Hunter Army Airfield (flooring contract). The flooring contract was structured for a one-year period with four option periods and was a competitive 8(a) set aside. (R4, tab 1 at 1, 3, 78, 153, 228, 303)

4. By 2005, United Grounds Maintenance (UGM) had approximately 20 years of experience performing small government contracts at Fort Stewart and Hunter Army Airfield (ASBCA No. 58331 et al. (58331), tr. 1/107-08). However, this was UGM's first bid on an ID/IQ contract and on any contract ofthis magnitude (58331, tr. 1/78). At that time, CBL was a small business specializing in cleaning and was owned by Ms. Lucy Brown. Although CBL was already certified by the Small Business

2 This background information is undisputed and the record support is throughout the transcripts of both hearings. 3 Unless otherwise noted citation to transcripts are for the hearing in ASBCA Nos. 58432,58441,58442. 2 Administration (SBA) as a minority, woman-owned 8(a) contractor, this was its first bid on a government contract (tr. 11175). After reviewing the solicitation for the flooring contract, Mr. Jerry Burkhalter, a UGM representative, approached Ms. Brown proposing that the two businesses work together to compete for Solicitation No. W9124M-05-B-0006-0004 (tr. 1/175-76). 4 Ms. Brown agreed with the proposal and a bid was submitted by CBL (R4, tab 1 at 3).

Site Visit

5. On 13 July 2005 CBL participated with other potential bidders in a pre-bid site visit. The potential bidders were driven around Fort Stewart and Hunter Army Airfield to view various buildings (tr. 2/45, 52-54). However, the potential bidders were not told of the reset project during the site visit (tr. 2/50).

Contract Award

6. CBL bid and was awarded Contract No. W9124M-05-D-0014 on 26 July 2005. The contract required CBL to provide an indefinite quantity of various services related to the buildings at Fort Stewart and Hunter Army Airfield, including the removal of the existing floor covering and replacement with new vinyl tile. (R4, tab 1 at 3, 264)

Contract Authority to Administer CBL 's Performance under the TOs

7. The government issued a notice of award letter on 28 July 2005 that, among other things, identified the contracting officer (CO), contracting officer's representative (COR) and the contract administrator. Ms. Deborah Austin was designated the CO and the letter stated she was the only individual with authority to bind the government. (R4, tab 264) Mr. Joey Waters was appointed the COR and Mr. Terrence Johnson the contract administrator (id. at 2). Pertinent to these appeals, Mr. Johnson signed every TO and virtually every TO modification as the "CONTRACTING/ORDERING OFFICER" (R4, tabs 5-31 ). In addition, he was on the worksite with CBL virtually every day providing direction and resolving issues as part of his responsibilities in administering the TOs (tr. 21167). Mr. Johnson was also responsible for ensuring CBL submitted the proper paperwork to be paid (58331, tr. 21144-45).

4 The precise legal relationship between CBL and UGM resulting from their agreement is unclear. CBL's proposal is not in the record and the awarded contract does not mention UGM. However, CBL filed the underlying claim in these appeals as a subcontractor sponsorship claim with UGM's attached request for equitable adjustment (REA) stating it is a subcontractor to CBL (R4, tab 257 at 1-5). Likewise, CBL's notice of appeal describes UGM as "an interested subcontractor" (Bd. corr.). 3 8. Mr. Burkhalter was the project superintendent for CBL and was delegated authority to act on behalf of the company (R4, tab 2; 58331, tr. 11109). Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

States Roofing Corporation v. Winter
587 F.3d 1364 (Federal Circuit, 2009)
Bell Bci Co. v. United States
570 F.3d 1337 (Federal Circuit, 2009)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
J. G. Watts Construction Co. v. United States
161 Ct. Cl. 801 (Court of Claims, 1963)
Julius Goldman's Egg City v. United States
556 F.2d 1096 (Court of Claims, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
Clean by Lucy, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/clean-by-lucy-inc-asbca-2016.