Classic City Mechanical, Inc. v. Potter South East, LLC

CourtCourt of Appeals of Tennessee
DecidedOctober 14, 2016
DocketE2015-01890-COA-R3-CV
StatusPublished

This text of Classic City Mechanical, Inc. v. Potter South East, LLC (Classic City Mechanical, Inc. v. Potter South East, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Classic City Mechanical, Inc. v. Potter South East, LLC, (Tenn. Ct. App. 2016).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE June 21, 2016 Session

CLASSIC CITY MECHANICAL, INC. v. POTTER SOUTH EAST, LLC, ET AL.

Appeal from the Chancery Court for Knox County No. 1855881 John F. Weaver, Chancellor ___________________________________

No. E2015-01890-COA-R3-CV-FILED-OCTOBER 14, 2016 ___________________________________

This case involves competing claims concerning a State construction project. The trial court awarded one of the subcontractors on the project compensatory damages, plus interest, based on the prime contractor‟s failure to remit payments for work that had been performed. On appeal, the prime contractor challenges the trial court‟s finding that it committed the first material breach of its contract with the subcontractor. The prime contractor also challenges the trial court‟s finding that it did not prove its claims for damages, which were predicated on an alleged delay created by the subcontractor and the subcontractor‟s cessation of performance. Although the subcontractor maintains that the trial court‟s findings regarding material breach should be left undisturbed, it appeals the trial court‟s specific award of interest, the dismissal of its fraudulent concealment claim, and the denial of its request for attorney‟s fees. Having reviewed the record transmitted to us on appeal, we affirm in part, modify in part, and remand for further proceedings consistent with this Opinion.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed in Part, Modified in Part, and Remanded

ARNOLD B. GOLDIN, J., delivered the opinion of the Court, in which CHARLES D. SUSANO, JR., and THOMAS R. FRIERSON, II, JJ., joined.

Stephen A. Marcum, Huntsville, Tennessee, for the appellants, Potter South East, LLC and Western Surety Co.

Robert P. Noell and William F. Clayton, Knoxville, Tennessee, for the appellees, Classic City Mechanical, Inc. and The Guarantee Company of North America, USA. Melissa Brodhag, Nashville, Tennessee, for the appellee, John Schroer, Commissioner of The Tennessee Department of Transportation.1

OPINION

BACKGROUND AND PROCEDURAL HISTORY

This appeal stems from a Tennessee Department of Transportation (“TDOT”) construction project that involved, among other things, the building of a bridge and extension of a road in Knox County. By contract dated March 26, 2012, TDOT entered into an agreement with Appellant Potter South East, LLC (“Potter”), under which Potter would serve as prime contractor for the project. In conjunction with this contract, Appellant Western Surety Company (“Western Surety”) executed a payment and performance bond for the full amount of Potter‟s contract with TDOT. At the time of the contract‟s execution, the unit prices in the contract totaled $15,660,653.11. Although the contract between Potter and TDOT did not have a master schedule, the original completion deadline was listed as August 31, 2014. However, pursuant to a change order that was entered after work on the project had begun, the completion date was later changed to “on or before December 13, 2014.”

On March 28, 2012,2 Potter entered into a subcontract with Classic City Mechanical, Inc. (“Classic City”) for the installation of natural gas lines related to the TDOT project. The unit prices of the subcontract totaled $1,051,656.50, and the subcontract incorporated by reference the terms and conditions of the prime contract between Potter and TDOT. Although the subcontract obligated Classic City to “commence work promptly or upon notice from [Potter],” the subcontract otherwise listed no date for the commencement of Classic City‟s performance. The subcontract was also devoid of any specific deadlines or milestones that Classic City was contractually obligated to meet with respect to its project obligations. As with the prime contract, no master schedule was provided relative to the project. Subsequent to the signing of the subcontract, Appellee Guarantee Company of North America USA (“Guarantee Company”) executed documents binding itself as a surety for Classic City‟s obligations to Potter.

One of Classic City‟s obligations under the subcontract was to install a sixteen inch gas line in the area of Beaver Creek; the Knoxville Utilities Board (“KUB”) served as an

1 Commissioner John Schroer did not file a brief.

2 Although the subcontract is dated March 28, 2012, it appears that it was actually signed the next day on March 29, 2012.

-2- inspector over this work. On May 1, 2012, Potter emailed Trent Gibson (“Mr. Gibson”), one of Classic City‟s owners and chief financial officer, to inform him that Classic City needed to start installing the sixteen inch line on June 18, 2012. A subsequent email was sent to Mr. Gibson on June 6, 2012, reminding him that Classic City was scheduled to start work. Mr. Gibson responded to the June 6 email by noting that Classic City was “a couple of weeks behind” with its steel crew. He represented that Classic City was still working with KUB to get its welders tested and stated that Classic City was also still waiting to receive its material submittals. It is undisputed that when Classic City had signed the subcontract with Potter earlier that spring, it did not have any KUB-certified welders on its payroll.

Over the next several months, a flurry of correspondence ensued regarding Classic City‟s progress on the sixteen inch line. In an August 30, 2012 email, Potter manager Dwayne Potter (“Mr. Potter”) sent an email to Mr. Gibson accusing Classic City of causing delay to the overall TDOT project.

In pertinent part, the email stated as follows:

The proposed 16‟‟ steel gas line in the area of Beaver Creek has and continues to disrupt the master schedule of the project. . . . Potter South East is requesting your personnel to begin immediately on a six day work week, sixteen hours a day (KUB specifications governing) until work is completed on the 16‟‟ steel gas line. If this work is not completed on or before September 17th, 2012 liquidated damages in the amount of $5,350.00 per day as outlined in the sub-contract will be accessed [sic] to Classic City Mechanical Inc. to cover delays impacting the project in and around the 16‟‟ steel gas line.

At this time, please present Potter South East a plan of operation for the installation of the 16‟‟ steel gas line.

Mr. Gibson responded to Mr. Potter‟s email by noting that the project had not yet been cleared to start by KUB. In relevant part, his email stated as follows:

The project started off late in the first place due to submittal delays from TDOT and KUB. Our submittals sat on people‟s desks for 60 days or more, and then had to be resubmitted. . . . I can‟t control either of these entities. Due to those delays, one of our 2 welders quit and we are in the process of testing another one tomorrow. We are required to have 2 welders on 16‟‟ and no welder is going to sit and wait on KUB. He left and we hired another one as soon as we knew.

-3- There is absolutely no way that the steel can be done by Sept. 17th. We can only begin when KUB gives us clearance to, and when the new welder passes (hopefully we‟ll know on Tuesday). When that happens we will work as long and hard to complete the work in a timely manner.

On September 25, 2012, Mr. Potter emailed Mr. Gibson to let him know that no Classic City personnel were on the work site. Mr. Potter stated that this was “totally unacceptable” and once again accused Classic City of “holding up the progress on the entire project.” Mr. Potter indicated that if work was not started within five days, Potter would “have no other option but to seek legal action.” Mr. Gibson responded to Mr. Potter‟s September 25 email by noting that Classic City was still having difficulty in securing clearance from KUB.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Velda J. Shore v. Maple Lane Farms, LLC
411 S.W.3d 405 (Tennessee Supreme Court, 2013)
Regions Bank v. Thomas D. Thomas
422 S.W.3d 550 (Court of Appeals of Tennessee, 2013)
Madden Phillips Construction, Inc. v. GGAT Development Corp.
315 S.W.3d 800 (Court of Appeals of Tennessee, 2009)
Lee Medical, Inc. v. Paula Beecher
312 S.W.3d 515 (Tennessee Supreme Court, 2010)
Eldridge v. Eldridge
42 S.W.3d 82 (Tennessee Supreme Court, 2001)
Chrisman v. Hill Home Development, Inc.
978 S.W.2d 535 (Tennessee Supreme Court, 1998)
Shepherd v. Perkins Builders
968 S.W.2d 832 (Court of Appeals of Tennessee, 1997)
Sullivan v. Sullivan
107 S.W.3d 507 (Court of Appeals of Tennessee, 2002)
Watson v. Watson
196 S.W.3d 695 (Court of Appeals of Tennessee, 2005)
Trinity Industries, Inc. v. McKinnon Bridge Co.
77 S.W.3d 159 (Court of Appeals of Tennessee, 2001)
Wells v. Tennessee Board of Regents
9 S.W.3d 779 (Tennessee Supreme Court, 1999)
Freeman v. Citizens' Nat. Bank
70 S.W.2d 25 (Tennessee Supreme Court, 1934)
Bevins v. Livesay
221 S.W.2d 106 (Court of Appeals of Tennessee, 1949)
Simmons Et Ux. v. Evans Et Ux
206 S.W.2d 295 (Tennessee Supreme Court, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
Classic City Mechanical, Inc. v. Potter South East, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/classic-city-mechanical-inc-v-potter-south-east-llc-tennctapp-2016.