357 So.2d 1251 (1978)

CLAIBORNE ELECTRIC COOPERATIVE, INC., Plaintiff-Appellant-Appellee,
v.
Felix Gordon GARRETT et al., Defendants-Appellants-Appellees.
CLAIBORNE ELECTRIC COOPERATIVE, INC., Plaintiff-Appellant-Appellee,
v.
Mrs. Alicegene McKENZIE et al., Defendants-Appellants-Appellees.

Nos. 13515 and 13516.

Court of Appeal of Louisiana, Second Circuit.

March 27, 1978.
Rehearing Denied May 10, 1978.
Writ Refused June 30, 1978.

*1253 Shaw & Shaw, Homer by James R. Hatch, Jonesboro, for plaintiff-appellant-appellee.

Sanders & Castete, Ltd. by Martin S. Sanders, Jr., Winnfield, for defendants-appellants-appellees.

Before BOLIN, PRICE and HALL, JJ.

En Banc. Rehearing Denied May 10, 1978.

BOLIN, Judge.

To meet the increased demand for electric power in the Lake Claiborne area, plaintiff planned a ten-mile-long 69 KV transmission and distribution line of single pole construction from an already existing to a proposed electric substation. Alleging inability to obtain rights of way across defendant landowners' property by conventional agreement, plaintiff instituted these expropriation proceedings pursuant to Louisiana Revised Statutes 19:2(7).[1]

* * * * * *

*1254 The trial court consolidated for trial suits against two groups of landowners, but rendered separate judgments in each case. Plaintiff and the defendants in each suit have appealed or answered the appeals from judgments which granted plaintiff servitudes and awarded defendant landowners compensation for the takings, severance damages, attorney and expert witness fees. We amend the judgments by reducing the amount awarded for severance damages in No. 13,515, and by reducing expert witness fees and increasing attorney fees in both cases; otherwise, we affirm.

The multiple issues relative to procedural and substantive matters will be discussed separately.

MOTIONS TO DISMISS

The trial court signed judgments in both cases on July 19, 1977. Plaintiff appealed the judgments the same day, and perfected its appeals by posting devolutive bonds of $500 on July 22. On July 26, defendant landowners filed motions for new trials. New trials were granted and the July judgments were ordered held in abeyance pending decisions; judgments identical to the July 19 judgments, with the exception of increased attorney fees in both cases, were signed on November 8. Plaintiff and defendants timely perfected appeals from the November judgments. Also, after the records were lodged in this court, defendants timely answered plaintiff's appeals from the July judgments.

Defendants moved to dismiss the original appeals of plaintiff as premature, since those appeals were taken from judgments subsequently ordered held in abeyance. We find no merit in this contention, which would penalize plaintiff for promptly perfecting its appeals.

After argument before this court the Garrett defendants (No. 13,515) filed a second motion to dismiss plaintiff's appeal, contending Claiborne Electric had already cleared a right of way across their property and "otherwise effected a complete taking." Since this motion to dismiss was not timely filed, it will not be considered. Louisiana Code of Civil Procedure Article 2161.

NEW TRIAL PROCEDURE

Plaintiff assigns as error the granting of new trials in these expropriation proceedings, contending this procedure is not available under the explicit terms of La.R.S. 19:13, as amended by Acts 1974, Ex.Sess., No. 11:

. . . The whole of the judgment, however, shall be subject to the decision of the appellate court on review under a devolutive appeal, and the delays for taking such appeal shall commence upon the signing of the judgment determining compensation. (Emphasis added)

Plaintiff argues forcefully that the sixty-day period for perfecting a devolutive appeal begins to run on the date judgment is signed in an expropriation proceeding governed by Part I of Title 19, not after the expiration of delays for new trial as provided by La.C.C.P. Art. 2087; that this variance was intended to expedite these expropriation proceedings, which are summary in nature. See La.C.C.P. Art. 2081; Columbia Gulf Transmission Co. v. C. J. Grayson, Inc., 232 So.2d 150 (La.App.2d Cir., 1970).

Assuming arguendo the new trial procedure is inappropriate, plaintiff and defendants in both suits are nevertheless before this court; plaintiff perfected appeals from the July judgments and defendants timely answered those appeals in this court. The answers present the questions of the inadequacy of both compensation and attorney fees awarded by the trial court, which is also the relief defendants sought by appealing the later judgments. We therefore choose to set aside the second judgments; *1255 we amend and affirm the judgments of July 19, 1977.

PREMATURITY

Defendants timely excepted to Claiborne Electric's initiation of judicial proceedings as premature, based on plaintiff's alleged failure to adequately negotiate in good faith with the landowners. The McKenzie defendants (No. 13,516) complain of failure to negotiate about price; the Garretts (No. 13,315), about both price and the location of the right of way. The trial court found adequate negotiation and overruled the exceptions.

The record shows plaintiff's agents contacted defendants' representatives, explained the route proposed by plaintiff's engineer, and offered $300 an acre for the right of way. Plaintiff was able to purchase rights of way over the other tracts along the proposed route for $300 an acre. Plaintiff's attorney contacted both the Garrett and McKenzie representatives and discussed location. Although plaintiff did not yield from its proposed route, the testimony reveals an alternate route was considered before being rejected by the expropriating authority as not feasible.

We hold there was a good faith attempt to acquire the rights of way by conventional agreement; plaintiff was not required to increase its original offer, nor change its proposed route at defendants' request. Dixie Pipeline Company v. Barry, 227 So.2d 1 (La.App.3d Cir., 1969). The trial court was correct in overruling the exception of prematurity.

NECESSITY OF THE GARRETT TAKING

In No. 13,515, the defendants argue the requirement of Article I, Section 4 of the 1974 Louisiana Constitution, i. e., that private utilities only expropriate for a public and necessary purpose,[2] places the burden on the expropriating authority to prove the particular route chosen was necessary; that, since plaintiff failed to prove it was necessary to traverse defendants' property rather than locate the transmission line elsewhere, its suit should have been dismissed.

Although the 1974 Constitution did add the word "necessary," the context of Article I, Section 4 indicates this refers to the necessity of the purpose for the expropriation, not the necessity for a specific location of the servitude. Since plaintiff has alleged and shown the need for increased electrical power in the Lake Claiborne area, defendants' contention lacks merit.

CONVENIENCE OF THE LANDOWNERS

Defendants in both cases complain plaintiff did not consider the landowners' convenience in mapping out its proposed route for the transmission line. La.R.S. 19:2(7). We agree that safety and convenience are primary considerations, but find the utility's route location was within its sound discretion, not planned in bad faith, arbitrarily or unreasonably. Louisiana Power & Light Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Exxonmobil Pipeline Co. v. Union Pacific Railroad
15 So. 3d 246 (Louisiana Court of Appeal, 2009)
Illinois Central Railroad v. Mayeux
301 F.3d 359 (Fifth Circuit, 2002)
CALCASIEU-CAMERON HOSP. SERV. v. Fontenot
628 So. 2d 75 (Louisiana Court of Appeal, 1993)
Trans Louisiana Gas Co. v. Heard
629 So. 2d 500 (Louisiana Court of Appeal, 1993)
San Diego Gas & Electric Co. v. Daley
205 Cal. App. 3d 1334 (California Court of Appeal, 1988)
State, Department of Transportation & Development v. Saxon
500 So. 2d 379 (Supreme Court of Louisiana, 1987)
VALLEY ELEC. MEMBERSHIP CORP., INC. v. Wallace
465 So. 2d 986 (Louisiana Court of Appeal, 1985)
Missouri Pacific RR Co. v. Nicholson
460 So. 2d 615 (Louisiana Court of Appeal, 1984)
Pointe Coupee Elec. Mem. Corp. v. Mounger
447 So. 2d 1104 (Louisiana Court of Appeal, 1984)
Willsey v. Kansas City Power & Light Co.
631 P.2d 268 (Court of Appeals of Kansas, 1981)
City of Baton Rouge v. Tullier
401 So. 2d 422 (Louisiana Court of Appeal, 1981)
City of Shreveport v. Pupillo
390 So. 2d 941 (Louisiana Court of Appeal, 1980)
Sirone v. South Central Bell Telephone Co.
392 So. 2d 192 (Louisiana Court of Appeal, 1980)
Southwestern Electric Power Co. v. Talley
377 So. 2d 364 (Louisiana Court of Appeal, 1979)
Claiborne Electric Cooperative, Inc. v. Garrett
359 So. 2d 1306 (Supreme Court of Louisiana, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
357 So. 2d 1251, Counsel Stack Legal Research, https://law.counselstack.com/opinion/claiborne-elec-co-op-inc-v-garrett-lactapp-1978.