CJM Financial, Inc. v. Leebcor Services, LLC

CourtDistrict Court, E.D. Virginia
DecidedApril 5, 2021
Docket4:20-cv-00035
StatusUnknown

This text of CJM Financial, Inc. v. Leebcor Services, LLC (CJM Financial, Inc. v. Leebcor Services, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CJM Financial, Inc. v. Leebcor Services, LLC, (E.D. Va. 2021).

Opinion

riLev

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF VIRGINIA Norfolk Division CLERK, Us.DeTRICT COUR’ CJM FINANCIAL, INC., Plaintiff and Counterclaim Defendant v. CIVIL ACTION NO. 4:20-cv-35 LEEBCOR SERVICES, LLC, And ASHFORD LEEBCOR ENTERPRISES, LLC, Defendants and Counterclaim Plaintiffs, MEMORANDUM OPINION AND ORDER Before the Court are Plaintiff's Motions to Dismiss Defendants’ Amended Counterclaims under Federal Rule of Civil Procedure 12(b)(6). ECF Nos. 47, 49. The Court finds that a hearing is not necessary. The Court will concurrently address both Motions to Dismiss, originally filed as separate Motions for the sake of judicial economy. Having reviewed the parties’ filings, both matters are ripe for judicial determination. I. FACTUAL AND PROCEDURAL HISTORY The following facts taken from Leebcor Services, LLC’s (“Leebcor’’) and Ashford Leebcor Enterprises, LLC’s (“ALE”) (collectively “Defendants’”). Amended Counterclaims, ECF Nos. 39, 40, are considered true and cast in the light most favorable to Defendants. Adams v. Bain, 697 F.2d 1213, 1219 (4th Cir. 1982). On or about July 2018, the United States Army Corps of Engineer (“USACE”) awarded Leebcor a contract to construct a flight simulator and fuselage facility at Hurlburt Field (the “Hurlburt Field Project”). ECF No. 40 at 9. Leebcor then sought bids from subcontractors, who

were required to comply with the terms of the Hurlburt Prime Contract. /d. at P 11. On or about January 3, 2019, Leebcor, a general contractor, entered a contract with Maston Creek Services, LLC (“Maston Creek”), a subcontractor, to assist with the Hurlburt Field Project. /d. at 17. On or about January 3, 2019, Maston and Leebcor executed that Subcontract Agreement in the amount of Five-Hundred Twenty-Eight Thousand Seven Hundred Seventy-One Dollars and 15/100 ($528,771.15). Jd. at 717. Similarly, on or about May 25, 2018, the United States Army Corp of Engineers (“USACE”) awarded ALE a contract to construct new Guardian Angel facilities at Patrick Air Force Base, Florida (the “Guardian Angel Project”). ECF No. 39 at PP 9. Maston Creek, by its manager and sole member, Westrom, secured the bid to provide material, labor, and equipment for the concrete and ICF work consistent with the Guardian Angel Project Plans and Specifications. Id. at P 13. On or about October 26, 2018, Maston and ALE executed the Subcontract Agreement for a fixed amount of One Million Nine Hundred Fifty Thousand Dollars ($1,950,000.00) in which Maston would provide the services related to the Guardian Angel Project. /d. at P 17. In January of 2019, Maston began work on the Guardian Angels Project. ECF No. 39 at { 18. In March of 2019, Maston began work on the Hurlburt Field Project. ECF No. 40 at □ 18. Maston and Westrom communicated with CJM Financial, Inc. (“CJM”) about “entering into a long-term factoring agreement whereby Maston would assign its right to collect its accounts receivable under the Hurlburt Field [and Guardian Angel Project] Subcontract[s] to CJM in exchange for immediate funding.” ECF No. 39 at 4 19; ECF No. 40 at J 19. Before CJM agreed to enter into the long-term factoring agreement, “CJM conducted due diligence to determine state of Maston[’s] financials and its prior contractual performance.” ECF No. 39 at J 20; ECF No. 40 at 20.

In April 2019, Maston entered into a long-term factoring agreement with CJM “whereby Maston would assign its rights to collect its accounts receivable to CJM in exchange for immediate funding on an invoice-by-invoice basis.” ECF No. 39 at | 21; ECF No. 40 at 4 21. The factoring agreement was for both the Hurlburt Field and Guardian Angel Projects. Leebcor and ALE both state that “[b]y virtue of that assignment, CJM’s right to payment from Leebcor was contingent on Maston Creek’s performance in accordance with the terms of the” Hurlburt Field and Guardian Angels Project Subcontracts. ECF No. 39 at 423; ECF No. 40 at { 23. On April 29, 2019, Maston submitted its first pay application to ALE for Guardian Angels Project which ALE paid upon receipt of the funds from the Government. ECF No. 39 at 23. On June 30, 2019, Maston submitted its second pay application to ALE for $247,767.50 for additional labor, material, and equipment that Maston allegedly provided between May 1, 2019 and June 30, 2019 for the Guardian Angels Project. /d. at § 25. Based on the Guardian Angels Subcontract, “Maston Creek was required to obtain partial waivers and release of liens for all of the labor, materials, and equipment that was included on the Second Pay Application.” Jd. at J 26. Since Maston and Westrom “had represented that they had obtained partial waivers and release of liens by submitting the Second Pay Application, ALE included the amount of the Second Pay Application in ALE’s next pay application to the Government.” /d. at 27. ALE alleges that it believes that “CJM knew or should have known that reimbursement from ALE for any funds advanced to Maston Creek was contingent on Maston Creek’s compliance with the terms of the Guardian Angel Subcontract, yet CJM failed to ensure that Maston Creek performed pursuant to the terms of the Guardian Angel Subcontract.” /d. at 28. However, while ALE waited for payment from the Government, ALE was notified of non-payment from Maston’s material suppliers. /d. at 29. ALE also alleges that it believes that “Westrom, through Maston, misdirected payments made

from CJM and ALE to Maston Creek by paying those funds to material suppliers for which those funds were not intended and/or to satisfy his personal financial obligations.” /d. at ]30. As a result, ALE withheld payments to Maston under the Second Pay Application because Maston failed to perform under the Guardian Angel Subcontract. /d. at 735. Thus, CJM, who had advanced Matson the funds for the Second Pay Application also did not receive payment from ALE. On August 26, 2019, ALE sent Maston a notice to cure but Maston responded that it had no intention of curing its breach of contract. /d. at 4] 42-43. On September 2, 2019, ALE terminated the Guardian Angels Subcontract with Maston. /d. at 4 44. Similarly, on June 4, 2019, Maston submitted its first pay application to Leebcor for $191,155.00 for labor, material, and equipment Maston provided between March 1, 2019 and May 31, 2019 for the Hurlburt Project. ECF No. 40 at | 24. Maston was required to obtain partial waivers and release of liens for all labor, materials, and equipment provided on its pay applications submitted to Leebcor. /d. at { 26. On June 5, 2019, CJM paid Maston a portion of the Hurlburt Pay Application. /d. at § 28. Meanwhile Leebcor waited for payment from the Government on its payment application, it received notice that Maston Creek had not paid its material supplies for the Hurlburt Field Project. /d. at { 30. Leebcor allages that Westrom, through Maston, “misdirected payments made from Leebcor to Maston for intended purposes and/or to satisfy his personal financial obligations.” /d. at 4 31. As a result, Leebcor withheld payments to Maston under the Hurlburt Pay Application. /d. at § 36. On August 26, 2019, Leebcor sent Maston a notice to cure but Maston responded that it had no intention of curing its breach of contract. Id. at 43-44. On September 9, 2019, Leebcor terminated that Hurlburt Field Subcontract with Maston. /d. at After the Court partially granted and denied CJM’s Motion to Dismiss, CJM filed an Amended Complaint, on August 28, 2020, seeking $411,958.65 against Leebcor and ALE. See

ECF Nos. 21, 22. CJM alleges Derivative Breach of Contract GAP Subcontract (Count I) and Breach of Contract (Count II) against ALE. /ad. Moreover, CJM alleges Derivative Breach of Hurlburt Subcontract (Count IV) and Breach of Contract (Count V) against Leebcor. Jd.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Klaxon Co. v. Stentor Electric Manufacturing Co.
313 U.S. 487 (Supreme Court, 1941)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Umstattd v. Centex Homes, G.P.
650 S.E.2d 527 (Supreme Court of Virginia, 2007)
Williams v. Dominion Technology Partners, L.L.C.
576 S.E.2d 752 (Supreme Court of Virginia, 2003)
Commercial Business Systems, Inc. v. Halifax Corp.
484 S.E.2d 892 (Supreme Court of Virginia, 1997)
Paul Business Systems, Inc. v. Canon U.S.A., Inc.
397 S.E.2d 804 (Supreme Court of Virginia, 1990)
Commercial Business Systems, Inc. v. BellSouth Services, Inc.
453 S.E.2d 261 (Supreme Court of Virginia, 1995)
Montagna v. Holiday Inns, Inc.
269 S.E.2d 838 (Supreme Court of Virginia, 1980)
The Hipage Co., Inc. v. Access2Go, Inc.
589 F. Supp. 2d 602 (E.D. Virginia, 2008)
Michigan Mutual Insurance v. Smoot
128 F. Supp. 2d 917 (E.D. Virginia, 2000)
Firestone v. Wiley
485 F. Supp. 2d 694 (E.D. Virginia, 2007)
Bay Tobacco, LLC v. Bell Quality Tobacco Products, LLC
261 F. Supp. 2d 483 (E.D. Virginia, 2003)
Gasperini v. Center for Humanities, Inc.
518 U.S. 415 (Supreme Court, 1996)
Tapia v. U.S. Bank, N.A.
718 F. Supp. 2d 689 (E.D. Virginia, 2010)
Navar, Inc. v. Federal Business Council
784 S.E.2d 296 (Supreme Court of Virginia, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
CJM Financial, Inc. v. Leebcor Services, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cjm-financial-inc-v-leebcor-services-llc-vaed-2021.