City of St. Joseph, Missouri v. Southwestern Bell Telephone, Formerly Known as Southwestern Bell Telephone Company, L.P., Olsson Associates, Inc.

439 F.3d 468, 37 Communications Reg. (P&F) 1149, 2006 U.S. App. LEXIS 4524, 2006 WL 435598
CourtCourt of Appeals for the Eighth Circuit
DecidedFebruary 24, 2006
Docket05-1800
StatusPublished
Cited by57 cases

This text of 439 F.3d 468 (City of St. Joseph, Missouri v. Southwestern Bell Telephone, Formerly Known as Southwestern Bell Telephone Company, L.P., Olsson Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of St. Joseph, Missouri v. Southwestern Bell Telephone, Formerly Known as Southwestern Bell Telephone Company, L.P., Olsson Associates, Inc., 439 F.3d 468, 37 Communications Reg. (P&F) 1149, 2006 U.S. App. LEXIS 4524, 2006 WL 435598 (8th Cir. 2006).

Opinion

SMITH, Circuit Judge.

This case stems from a road-widening and reconstruction project on Faraón Street in St. Joseph, Missouri (“the Faraón Project”). The City of St. Joseph (“the City”) sued Southwestern Bell Telephone, L.P. (“SWBT”), claiming that the City incurred additional contractor costs because SWBT failed to move its underground telephone lines for the Faraón Project. SWBT moved for summary judgment on all claims and asked the district court 1 to strike the affidavit of Roger Sparks, the Engineer of Streets and Sew *472 ers for the City. The district court granted summary judgment to SWBT and struck Sparks’s affidavit, concluding that it was a “sham” affidavit. The City appeals, arguing that the district court erred in striking Sparks’s affidavit; determining that the City failed to establish a claim for promissory estoppel against SWBT; and determining that the City failed to establish a claim for negligent misrepresentation against SWBT. We affirm.

I. Background,

In 1999, the City announced its plans to make improvements on Faraón Street. The City hired Olsson Associates (“Ols-son”) to provide design services and construction-phase services to the City and to act as the City’s representative on the Faraón Project. On May 14, 1999, Olsson informed the affected utility companies by letter. In addition, Olsson sent plan sheets to the utilities and requested that they review the locations of their facilities and return the plan sheets to Olsson. SWBT received a copy of the letter and the request to return the plan sheet.

By June 1999, SWBT knew that it would have to move its lines and facilities for the Faraón Project. Sometime between May 1999 and November 1999, SWBT decided to replace the existing lines and install new lines throughout the entire length of the Faraón Project. However, Comeo Designs (“Comeo”), SWBT’s contractor, did no work on designing the placement of the new lines during this time period.

On November 3, 1999, Olsson sent SWBT a letter stating that the Faraón Project would commence in May or June of 2000. On November 30, 1999, the City held a utility coordination meeting to ensure that the parties involved with the Faraón Project were not delayed in their work. SWBT employee Bill Hansen, Manager of Engineering Design, attended the meeting. At that time, Hansen thought SWBT’s existing line would only minimally interfere with the Faraón Project.

On February 28, 2000, Olsson mailed SWBT a 90% final design plan for the first phase of the Faraón Project. In the accompanying letter, Olsson informed SWBT that the City would begin construction of the Faraón Project in June or July of 2000. SWBT did not object to this schedule.

On April 4, 2000, pursuant to SWBT’s work request on January 26, 2000, Comeo provided work prints to SWBT for the abandonment of the existing lines and the installation of new lines in connection with the Faraón Project. None of Comco’s plans showed a temporary relocation of existing SWBT telephone lines and facilities. To implement Comco’s prints, SWBT needed to review the drawings to ensure that they coincided with SWBT’s overall plan to relocate its existing telephone lines and facilities; obtain a price from a contractor to implement the drawings; and obtain the approval of Lloyd Baskett, Director of Engineering Construction for SWBT. However, prior to the end of May, no one at SWBT had reviewed the work prints.

In April 2000, Roger Sparks, City Engineer for Streets and Sewers and the Project Manager for the Faraón Project, became concerned that SWBT would impede road construction. The City’s April 25 meeting for prospective bidders confirmed Sparks’s concerns. At the meeting, Chip Cocoran of Olsson recorded in a section of his notes entitled “utility relocation” that “[telephone is the most significant conflict, design of relocation underway, no work yet. Two fibers and 500 pari in Phase 1.”

Subsequently, Olsson’s Kent Evans inquired of SWBT about the time frame for SWBT moving its cables. Kraig Arthur, Manager of Engineering Design for *473 SWBT, took the call from Evans because he was filling in for Hansen while he was on medical disability leave. During the phone conversation, Evans indicated to Arthur that Olsson would like to have SWBT’s work finished by the end of June 2000. Arthur said that would “probably be possible.” Arthur was aware that the City planned to start construction on the Faraón Project in July 2000. Arthur told Evans that he would discuss SWBT’s time frame with John P. Garrett, SWBT’s Construction Manager, and get back to him.

When Arthur asked Garrett whether SWBT could have its lines moved by the end of June 2000, Garrett told Arthur that SWBT could have its lines moved by that time. Arthur also reviewed SWBT’s prints to install the new telephone lines and facilities. Pursuant to Evans’s request, Arthur sent a letter to Evans on May 1, 2000, which stated: “Southwestern Bell Telephone plans to have the telephone cables moved to the South by the end of June. We will start work in the next few weeks. If you have any questions, please call (815) 271-2447” (emphasis added). Arthur did not have his letter to Evans reviewed or approved by his supervisors at SWBT before he sent it. Arthur testified that when he sent the letter, he had no reason to believe that SWBT could not move its cables by the end of June.

On May 3, 2000, the City attached Arthur’s letter, along with letters from other utilities, to an addendum to its bid documents. The City, however, failed to inform Arthur or anyone else at SWBT that it would provide Arthur’s letter to bidders on the Faraón Project. On May 9, 2000, the City selected Loch Sand and Construction Company (“Loch Sand”) as the lowest bidder. SWBT never received a copy of the contract between the City and Loch Sand.

At the beginning of May 2000, Sparks did not know what methods SWBT would use to relocate its facilities on Faraón Street. Sparks testified that the City “didn’t have a commitment from [SWBT] in any way that they [sic] would be done.” Then, on May 25, 2000, three and a half weeks after the City received Arthur’s letter, Sparks spoke with Hansen, who had returned from medical leave, about Arthur’s letter. When asked what he recalled about his conversation with Hansen, Sparks stated that what he recalled was in the e-mail he sent to Cocoran about his conversation with Hansen. In the e-mail, Sparks stated:

Talked with the telephone company today (SW Bell). The lead engineering guy, Bill Hansen, was surprised to here [sic] that we have a letter from them stating that they would be clear of the construction by July 1. He thought they might be started by then. This leaves us in a slight predicament. I never could figure out how they were going to relocate before the contractor completed the cuts and fills anyway.... I have asked Bill to get his people together for a meeting with us and perhaps the contractor to figure out how this can be done ....

When questioned about the e-mail during his deposition, Sparks stated that Hansen told him that SWBT would not have its lines and cables moved prior to June 30, 2000, and that SWBT might start with the relocation by July 1, 2000, but that SWBT would not be finished by that time.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
439 F.3d 468, 37 Communications Reg. (P&F) 1149, 2006 U.S. App. LEXIS 4524, 2006 WL 435598, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-st-joseph-missouri-v-southwestern-bell-telephone-formerly-known-ca8-2006.