City of South Bend v. Dollahan

918 N.E.2d 343, 2009 Ind. App. LEXIS 2595, 2009 WL 4824728
CourtIndiana Court of Appeals
DecidedDecember 15, 2009
Docket46A03-0901-CV-17
StatusPublished
Cited by19 cases

This text of 918 N.E.2d 343 (City of South Bend v. Dollahan) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of South Bend v. Dollahan, 918 N.E.2d 343, 2009 Ind. App. LEXIS 2595, 2009 WL 4824728 (Ind. Ct. App. 2009).

Opinions

OPINION

DARDEN, Judge.

STATEMENT OF THE CASE

The City of South Bend ("City") appeals the trial court's judgment, following a bench trial, holding it liable for injuries suffered by Charles Dollahan ("Dollahan") and ordering it to pay $300,104.00 in damages.

We affirm.

ISSUE

Whether the trial court's finding that City was liable for Dollahan's loss was clearly erroneous.

FACTS

In 2000, Dollahan was employed as a brick restorer by Larson-Danielson Construction ("Larson-Danifelson"). Larson, Danielson was hired to repair and clean the brick facade of the Wells Fargo bank building, located on Jefferson Boulevard in downtown South Bend. There is a city sidewalk immediately in front of the bank. During the preparation phase, project manager Daniel Speckhard determined that a "boom lift" would be required to raise Dollahan to the necessary height for the job, approximately twenty-five to thirty feet above the ground. A boom lift consists of a hydraulic arm and a cage that is mounted on a four-wheel drive platform base from which an operator can be raised or lifted to a desired height from the ground to perform maintenance or work. The boom lift can be operated from either the base platform or the cage controls.

Anyone seeking to temporarily occupy City's property must obtain a special permit in order to do so. Pursuant to South Bend Municipal Code Article 5, section 6-11(a) the City's engineer is responsible for issuing such permits. Speckhard contacted City's engineering department and informed officials of the masonry project and thought it would require the use of a boom lift that could be placed on the street or sidewalk near the building. The parties agreed that the boom lift could be placed on the sidewalk, as depicted in the sketch contained in the record. (City's Exhibit A, App. 90). Subsequently, City's engineer[347]*347ing department granted Speckhard a temporary occupancy permit authorizing Larson-Danielson to temporarily occupy the sidewalk with its boom lift. At no time did City's engineering officials inform Speck-hard of any structural problems with the sidewalk.

Approximately three days before the masonry project was to begin, Dollahan visited the worksite. During the visit, he observed that the sidewalk was not in the best condition and that much of the caulk between the sidewalk joints was cracked and/or missing. He was concerned about placing the boom lift on the sidewalk, given its condition and the weight of the boom lift. He was not in fear for his personal safety, but thought that the boom lift might crack the sidewalk and he could be held personally responsible for the damage. Given the condition of the sidewalk, Dollahan thought the boom lift would like-Ty be placed on the public street.

On August 21, 2000, Dollahan arrived at the worksite to find an eighty-foot boom lift on the sidewalk. He reviewed the permit and learned that City had approved the placement of the boom lift on the sidewalk. He then tested the load-bearing eapacity of the sidewalk by operating the boom lift from the base platform controls and increased the pressure on the sidewalk by "hydraulically telescoping the cage platform into the air" (Judgment p. 4). When the sidewalk withstood the stress test, Dollahan decided to proceed. He stood on the platform, entered the cage, and using the cage controls, lifted himself approximately twenty-five or thirty feet into the air. Moments later, the sidewalk cracked suddenly and the boom lift sank into a four-foot fissure beneath the sidewalk. As a result of the sidewalk collapse, Dollahan suffered injuries to his neck and upper back and required extensive medical treatment and multiple surgeries. His medical expenses amounted to $74,634.99, including the cost of disk removal and spinal fusion surgeries. He was unable to return to work and lost wages in the amount of $136,998.05 from August, 2000 to January, 2003.

An ensuing investigation revealed that the subgrade or base material underneath the sidewalk had been washed away by a "recurring leak in an irrigation system in a park area next to the bank[,] and that the washout underneath the sidewalk extended down the block." (Judgment p. 5). The investigation also revealed that some time in the past steel reinforcement I-beams had been inserted into the sidewallk-an unusual reinforcement measure in sidewalk construction indicating prior problems with the sidewalk. (Judgment p. 5; May Depo. p. 32).

In April of 2002, Dollahan filed a complaint for damages in two theories, wherein he alleged that City was liable for (1) negligently issuing the temporary occupancy permit; and/or (2) its failure to warn him, a business invitee, about latent defects in the sidewalk under the theory of premises liability. On April 17, 2002, City filed its answer, but failed to assert the affirmative defense of governmental immunity. At a January 28, 2003 deposition, Dollahan called John May, a City engineer, to testify. Under direct examination, he testified that the I-beam reinforcement method found in the sidewalk was an atypical approach to sidewalk construction. He also testified that the reinforcement indicated that there "was a void before" under the sidewalk because the reinforcement measures would only be necessary if the subgrade was insufficient. (May Depo. p. 32). He further testified that although the reinforced sidewalk could "have held a lot more than pedestrian traffic," the sidewalk would invariably have collapsed were any type of heavy machinery placed upon [348]*348it. Lastly, he testified that the void was not readily apparent from a surface observation of the sidewalk, and therefore, could not have been detected before the collapse.

On February 2, 2006, City filed a motion for summary judgment wherein it raised, for the first time, the affirmative defense of governmental immunity. City also designated evidence and a memorandum in support of its motion for summary judgment. On April 3, 2006, Dollahan filed his response and a memorandum in opposition to City's motion. Dollahan also designated May's deposition testimony as proof of a material issue of fact that City was not entitled to summary judgment as a matter of law. Dollahan did not object to City's belated assertion of the defense of governmental immunity. Subsequently, the trial court conducted a hearing on City's motion for summary judgment on May 12, 2006. Dollahan did not argue at the hearing that he had been prejudiced by City's belatedly raised defense. The trial court denied City's motion for summary judgment on May 18, 2006. The parties waived trial by jury, and on October 31, 2008, the trial court conducted a bench trial City requested findings of fact and conclusions of law pursuant to Trial Rule 52. On December 8, 2008, the trial court heard final arguments. Dollahan argued, for the first time, that City had waived the defense of governmental immunity. At no time, however, did he argue that City's assertion of the defense of governmental immunity was in any way prejudicial to his case.

On December 22, 2008, the trial court issued a judgment in favor of Dollahan. The judgment included, in pertinent part, the following conclusions of law:

30. [City] failed in its Answer to assert any affirmative defenses as to statutory immunity....
31. Defendant City of South Bend owed a duty to Charles Dollahan in exercising its authority to issue a temporary occupancy permit for the placement of the 88,000 pound lift on property owned by the City of [SJouth Bend.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Howard Larky v. Camp Livingston, Inc.
Indiana Court of Appeals, 2025
HALL v. MENARD, INC.
S.D. Indiana, 2023
CENSKE v. United States
S.D. Indiana, 2022
LEWIS v. MENARD, INC.
S.D. Indiana, 2021
WHITLOCK v. MENARD, INC.
S.D. Indiana, 2020
Lucy Mundia v. Drendall law Office, P.C.
77 N.E.3d 846 (Indiana Court of Appeals, 2017)
Willie Jenkins v. Mary Jenkins
17 N.E.3d 350 (Indiana Court of Appeals, 2014)
Goodrich Quality Theaters, Inc. v. Fostcorp Heating & Cooling, Inc.
16 N.E.3d 426 (Indiana Court of Appeals, 2014)
Pichon v. American Heritage Banco, Inc.
983 N.E.2d 589 (Indiana Court of Appeals, 2013)
Sagarin v. City of Bloomington
932 N.E.2d 739 (Indiana Court of Appeals, 2010)
Smithson v. HOWARD REGIONAL HEALTH SYSTEM
933 N.E.2d 1 (Indiana Court of Appeals, 2010)
City of South Bend v. Dollahan
918 N.E.2d 343 (Indiana Court of Appeals, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
918 N.E.2d 343, 2009 Ind. App. LEXIS 2595, 2009 WL 4824728, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-south-bend-v-dollahan-indctapp-2009.