City of Rapid City v. Big Sky

2018 SD 45
CourtSouth Dakota Supreme Court
DecidedJune 13, 2018
StatusPublished

This text of 2018 SD 45 (City of Rapid City v. Big Sky) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Rapid City v. Big Sky, 2018 SD 45 (S.D. 2018).

Opinion

#28205, #28227-a-DG 2018 S.D. 45

IN THE SUPREME COURT OF THE STATE OF SOUTH DAKOTA

**** CITY OF RAPID CITY, a Municipal Corporation, Plaintiff and Appellant,

v.

BIG SKY, LLC and DOYLE ESTES, Individually, Defendants and Appellees.

****

APPEAL FROM THE CIRCUIT COURT OF THE SEVENTH JUDICIAL CIRCUIT PENNINGTON COUNTY, SOUTH DAKOTA

THE HONORABLE WARREN G. JOHNSON Retired Judge

JOHN K. NOONEY ROBERT J. GALBRAITH of Nooney & Solay LLP Rapid City, South Dakota Attorneys for plaintiff and appellant.

DONALD A. PORTER JESS M. PEKARSKI CHRISTOPHER A. CHRISTIANSON of Costello, Porter, Hill, Heisterkamp, Bushnell & Carpenter LLP Rapid City, South Dakota Attorneys for defendants and appellees.

ARGUED JANUARY 9, 2018 OPINION FILED 06/13/18 #28205, #28227

GILBERTSON, Chief Justice

[¶1.] The City of Rapid City filed an action against real-estate developers

Big Sky LLC and Doyle Estes (collectively, “Developers”), seeking to recover the

prospective cost of repairing roads in the Big Sky development outside Rapid City.

A jury returned a general verdict in favor of the Developers. The City appeals the

general verdict, arguing the circuit court erred by: (1) denying the City’s motion for

summary judgment on the issue of liability; (2) excluding evidence of the

Developers’ litigation and settlement with their subcontractors; (3) granting Estes’s

motion for judgment as a matter of law; (4) instructing the jury on period-of-

limitation, waiver, and estoppel defenses; and (5) refusing to instruct the jury on

nuisance. We affirm.

Facts and Procedural History

[¶2.] This case involves the development of real property known as the Big

Sky subdivision, which is located within the extraterritorial jurisdiction of Rapid

City. The Developers acquired real property in this area and applied to the City for

approval of 15 subdivision plats. Under the City’s municipal code, a plat will not be

approved unless the subdivider completes the construction of certain public

improvements or offers a bond guaranteeing such construction. The Developers

either completed the improvements or provided bonds for each of the 15 plats, and

the City approved these plats between 1998 and 2005.

[¶3.] Following approval of the plats, the City identified several deficiencies

in the public improvements installed by the Developers’ contractor and

subcontractors. In particular, some of the subdivision’s streets had settled

significantly since their construction. The City indicated it would not assume -1- #28205, #28227

ownership of the public improvements until the deficiencies were corrected. The

Developers did not correct the identified deficiencies, and the City did not conduct

subsequent inspections. The bonds posted by the Developers expired without the

City attempting to collect on them. Eventually, litigation ensued.

[¶4.] The procedural history of this case is complex and involves several

parties. In May 2003, Big Sky filed a complaint against J. Scull Construction

Service Inc., the subcontractor that worked on Phases 1 through 3 of the

subdivision. And in March 2007, Big Sky filed a complaint against R.C.S.

Construction Inc., the subcontractor that worked on Phase 4. Big Sky alleged that

Scull and R.C.S. breached their contracts with Big Sky by failing to properly

compact the soil underlying the streets in Phases 1 through 4. Big Sky and Scull

settled shortly after Big Sky filed its complaint against R.C.S.

[¶5.] In January 2008, the City filed a separate complaint against the

Developers, seeking specific performance and an injunction requiring the

Developers to complete the repairs. The circuit court granted summary judgment to

the Developers on the City’s complaint, reasoning that the expiration of the bonds

absolved the Developers of their obligation to complete the public improvements.

This Court reversed the grant of summary judgment and remanded in City of Rapid

City v. Estes, 2011 S.D. 75, 805 N.W.2d 714. On remand, the Developers filed a

third-party complaint against Rapid Construction LLC, the general contractor.

Rapid Construction, in turn, filed a fourth-party complaint against Dream Design

International Inc., the Developers’ engineering firm. And to bring things full circle,

Dream Design International counterclaimed against the City. The court then

-2- #28205, #28227

consolidated the Developers’ action against R.C.S. with the City’s suit against the

Developers. In April 2016, the City amended its complaint to allege nuisance as an

additional cause of action.

[¶6.] The various parties settled most of the foregoing litigation. As noted

above, Big Sky settled with Scull in 2007. Big Sky also settled its complaints

against R.C.S. and Rapid Construction. Rapid Construction settled with Dream

Design International. And finally, the Developers and the City settled in regard to

all disputed project phases other than Phases 1 through 4. So prior to trial, Scull,

R.C.S., Rapid Construction, and Dream Design International were each removed as

parties, and the issues were narrowed to the dispute between the City and the

Developers regarding Phases 1 through 4 of the subdivision. 1 Citing this Court’s

decision in Estes, the City moved for summary judgment on the issue of the

Developers’ liability for these phases. The circuit court denied the motion.

[¶7.] A jury trial was held January 23 through 27, 2017. During the trial,

the circuit court excluded evidence offered by the City regarding Big Sky’s litigation

and settlement with Scull and R.C.S. Estes filed a motion for judgment as a matter

of law, which the court granted because the City did not dispute that Big Sky was

the sole owner of the properties at issue in Phases 1 through 4. And over the City’s

objection, the court instructed the jury on the Developers’ period-of-limitation,

waiver, and estoppel defenses. The court did not instruct the jury on the City’s

1. It is unclear how Dream Design’s counterclaim against the City was resolved.

-3- #28205, #28227

nuisance theory. The jury returned a general verdict in favor of the Developers,

denying any relief to the City.

[¶8.] The City appeals, raising the following issues 2:

1. Whether the City was entitled to summary judgment on the issue of the Developers’ liability. 2. Whether the circuit court erred by excluding evidence of Big Sky’s claims against, and settlements with, Scull and R.C.S. 3. Whether the circuit court erred by granting Estes’s motion for judgment as a matter of law. 4. Whether the circuit court erred by instructing the jury on the Developers’ period-of-limitation, waiver, and estoppel defenses. 5. Whether the circuit court erred by not instructing the jury on the City’s public-nuisance claim.

Analysis and Decision

[¶9.] 1. Whether the City was entitled to summary judgment on the issue of the Developers’ liability.

[¶10.] The City first argues the circuit court erred by denying the City’s

motion for summary judgment on the issue of the Developers’ liability. In the City’s

view, the Developers’ liability was established as the law of the case in Estes. In

Estes, this Court held that the expiration of bonds given in lieu of completing public

improvements did not release the Developers from the obligation of making those

2. By notice of review, the Developers also raise a constitutional issue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kuper v. Lincoln-Union Electric Co.
1996 SD 145 (South Dakota Supreme Court, 1996)
Artz v. Meyers
1999 SD 156 (South Dakota Supreme Court, 1999)
Even v. City of Parker
1999 SD 72 (South Dakota Supreme Court, 1999)
Thomas v. Sully County
2001 SD 73 (South Dakota Supreme Court, 2001)
Johnson v. Armfield
2003 SD 134 (South Dakota Supreme Court, 2003)
City of Rapid City v. Estes
2011 S.D. 75 (South Dakota Supreme Court, 2011)
Parker v. Casa Del Rey-Rapid City, Inc.
2002 SD 29 (South Dakota Supreme Court, 2002)
City of Rapid City v. Hoogterp
179 N.W.2d 15 (South Dakota Supreme Court, 1970)
Donat v. Johnson
2015 SD 16 (South Dakota Supreme Court, 2015)
Lenards v. Deboer
2015 SD 49 (South Dakota Supreme Court, 2015)
Nicolay v. Stukel
2017 SD 45 (South Dakota Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2018 SD 45, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-rapid-city-v-big-sky-sd-2018.