City of New Orleans v. Federal Energy Regulatory Commission

67 F.3d 947, 314 U.S. App. D.C. 253
CourtCourt of Appeals for the D.C. Circuit
DecidedOctober 20, 1995
DocketNos. 94-1340, 94-1345
StatusPublished
Cited by2 cases

This text of 67 F.3d 947 (City of New Orleans v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of New Orleans v. Federal Energy Regulatory Commission, 67 F.3d 947, 314 U.S. App. D.C. 253 (D.C. Cir. 1995).

Opinion

WALD, Circuit Judge:

This case involves a decision by the Federal Energy Regulatory Commission (“FERC” or “the Commission”) to allow the spin-off of two electricity generating plants by Entergy, a holding company which owns four subsidiary utility companies. The City of New Orleans (“CNO”), claiming that New Orleans ratepayers will suffer harm from FERC’s decision, and Entergy, the holding company, both challenge the Commission’s Order for addressing the “prudence” of the spin-off only as to its current effect on rates up until such time as the utility system will need to purchase new capacity. Both petitioners, while disagreeing on the final result of a prudence analysis, agree that FERC must consider now the reasonableness of the ultimate effect the addition of replacement capacity will have on rates. We hold that FERC’s decision to defer any prudence determination affecting rates based on replacement capacity until such time as that occurs is a reasonable one and deserves our deference.

I. Background

A. The Entergy System

Entergy Corporation, a holding company, owns four utility operating companies and a generating company which together form the integrated Entergy System (“System”). The four companies — New Orleans Public Service, Inc. (“NOPSI”), Louisiana Power & Light (“LP & L”), Mississippi Power & Light (“MP & L”), and Arkansas Power & Light (“AP & L”) — provide electric services to consumers in Louisiana, Mississippi and Arkansas, in accordance with a series of contracts known as the Entergy System Agreement (“System Agreement”). The System Agreement, which governs the planning, construction, and operation of the generating and transmitting facilities, is subject to FERC oversight.

Pursuant to the System Agreement, imbalances associated with the costs of plants assigned to individual operating companies are shared, to an extent, by the other operating companies. For example, Service Schedule MSS-1 in the System Agreement provides for companies which own a share of the total system generating capacity that is less than their share of total system demand (“short” companies) to make equalization payments to the companies which own a share of capacity greater than their share of system demand (“long” companies).

Another service schedule (MSS-3) provides for the coordinated dispatch and pur[949]*949chase of economy energy. Under a method known as economic dispatch, System generating plants provide the operating companies with the lowest-cost energy available. Subject to certain technological constraints, the lowest-cost resources are run first, without regard to ownership (except that the operating company with responsibility for a plant has first call on the energy generated by that particular facility). The energy generated in excess of an operating company’s consumption is allocated to the other operating companies.

B. The Spin-Off

In 1990, AP & L, one of Entergy’s utility companies, sold a substantial interest in two generating plants to Entergy Power, Inc. (“EPI”), a newly-created subsidiary of Entergy. AP & L had more generating capacity than required to meet its immediate needs, and no other company in the Entergy System wished to purchase the excess capacity. Thus, in order to avoid generating more energy than could be used by the System, Entergy sought permission from FERC, the Securities and Exchange Commission (“SEC”), and the Arkansas Public Service Commission (“APSC”), which governs rate regulation in Arkansas, to spin-off AP & L’s two excess generating plants and transfer them to the new subsidiary for eventual sale to unaffiliated purchasers.

Although the two generators were producing excess capacity in the 1980s and early 1990s, and thus burdening the System, there is evidence to suggest that the System eventually will need that extra power. If and when that time comes, presumably in the next century, the System will have to purchase additional capacity to replace the power originally generated by the two spun-off facilities. These costs, central to the instant dispute, are referred to as “replacement capacity costs.”

The APSC and the SEC approved the sale, and the transfer to EPI took place in August, 1990. However, in 1992, this court remanded the matter to the SEC for reconsideration in City of New Orleans v. SEC, 969 F.2d 1163 (D.C.Cir.1992). The SEC has not yet issued any new determination on the validity of the spin-off.

II. Procedural History

A. The SEC Proceeding

The Public Utility Holding Company Act of 1936, 15 U.S.C. § 79a et seq. (1988 & Supp. V 1993) (“PUHCA”), requires that, before approving an acquisition, the SEC must determine that the transaction “will serve the public interest by tending towards the economical and efficient development of an integrated public-utility system.” City of New Orleans v. SEC, 969 F.2d at 1166 (citing 15 U.S.C. § 79j(c)(2)).

The SEC originally determined that the Entergy spin-off satisfied PUHCA’s statutory requirements and the Commission granted Entergy approval. On appeal, however, this court ruled that in making the spin-off determination, the SEC had not taken into account “the System’s increased costs that will result from having to replace the spin-off plants in the future ... [or] ... the fact that System costs will increase because alternative sources of energy available to the System are more expensive than the type used by the spin-off plants.” Id. at 1167. Because of that omission, we remanded the case for further development of the administrative record. See id. at 1169.

B. FERC Proceedings

1. The Commission’s Hearing Order

The City of New Orleans filed a complaint with FERC, seeking relief from alleged adverse rate consequences from the transfer of capacity to EPI. In response, FERC set for hearing “the narrow question of whether overall billings will increase under the Enter-gy System Agreement as a result of the transfer of AP & L’s ownership interests in the two units and, if so, whether those higher charges reflect prudently incurred costs which may be reasonably passed through the Entergy System Agreement’s formula rates.” City of New Orleans v. Entergy Corp., 54 [950]*950F.E.R.C. ¶ 61,298, at 61,865, reh’g denied, 55 F.E.R.C. ¶ 61,221 (1991).1

In the same Hearing Order, however, FERC noted that the effect on ratepayers of any eventual replacement costs would depend on several highly speculative factors. Thus, the Commission concluded that it would be premature to decide the prudence question finally until the actual need for replacement capacity arose, and dismissed without prejudice the portion of CNO’s complaint requesting investigation into the costs associated with adding future capacity. See id. at 61,865-66.

2. The Commission’s Rehearing Order

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Verizon California Inc. v. Peevey
413 F.3d 1069 (Ninth Circuit, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
67 F.3d 947, 314 U.S. App. D.C. 253, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-new-orleans-v-federal-energy-regulatory-commission-cadc-1995.