City of Mesa v. Federal Energy Regulatory Commission

993 F.2d 888, 301 U.S. App. D.C. 226
CourtCourt of Appeals for the D.C. Circuit
DecidedMay 25, 1993
DocketNo. 91-1499
StatusPublished
Cited by3 cases

This text of 993 F.2d 888 (City of Mesa v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Mesa v. Federal Energy Regulatory Commission, 993 F.2d 888, 301 U.S. App. D.C. 226 (D.C. Cir. 1993).

Opinion

Opinion for the Court filed by Circuit Judge WALD.'

WALD, Circuit Judge:

This case is yet another progeny of the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) recent efforts to foster competition in the natural gas industry by “unbundling” — separating—the sale of gas from its transportation. Pipelines formerly transported gas exclusively or principally in conjunction with sales of their own product; now, pipelines transport gas whether it is their own or has been purchased from a third party. This sea change in the natural gas industry has inevitably raised new issues [228]*228concerning a pipeline’s duty to its shippers in cases of capacity constraint, ie., when because of force majeure or other circumstances the demand for transportation of gas from a pipeline’s contractual customers outstrips the capacity of the pipeline. The Cities of Mesa, Arizona, and Las Cruces, New Mexico, and the Navajo Tribal Utility Authority (collectively, the “petitioners”) raise two such questions here. First, they contend that § 401 of the Natural Gas Policy Act (“NGPA”), which requires plans for “curtailment of deliveries of natural gas” to ration the resource on the basis of end-use rather than pro rata across all customers, applies to unbundled transportation service. If they are right, the FERC erred in approving an El Paso Natural Gas Company (“El Paso”) plan that curtailed shippers pro rata during shortages caused by capacity constraint. We ultimately reject this argument, however, because § 401 itself is ambiguous as to its application to capacity constraints affecting unbundled transportation service and the FERC’s conclusion that it should not apply to those circumstances is reasonable. Second, the Petitioners claim that the FERC’s approval of El Paso’s capacity curtailment plan contravenes the consumer protection requirements of the Natural Gas Act (“NGA”) because it does not assure that “high-priority” end-users — residential customers, schools, hospitals, and others for whom even short-term cut-offs of gas may have serious consequences — will have continuous access to gas. On this point, we find that the FERC has not sufficiently explained its conclusion that El Paso’s plan fulfills NGA consumer protection requirements; accordingly, we remand that question to the Commission.

I. Background

On August 31, 1990, El Paso submitted for the Commission’s approval a proposed “Global Settlement” of a slew of outstanding regulatory proceedings in which it was involved. A cornerstone of the proposed multiparty settlement was El Paso’s agreement to unbundle its services. More specifically, El Paso offered to convert all of its customers’ “bundled” entitlements to gas supply and transportation on the pipeline into transportation 1 entitlements alone. This transformation, which the Commission had strongly encouraged all pipelines to undertake, see Order No. 436, 50 Fed.Reg. 42,408 (1985) (providing incentives for pipelines to offer unbundled services), would permit El Paso customers heretofore dependent on the pipeline for both supply and carriage of gas to choose whether to buy gas from El Paso or from a third party. Cf. Associated Gas Distributors v. FERC, 899 F.2d 1250, 1254 (D.C.Cir.1990) (noting that before unbundling, pipelines “refuse[d] to transport gas for parties other than those who bought gas directly from them”). It would also mean that the ownership of the gas flowing through its pipelines would not lie with El Paso but rather with its transportation customers, mostly local distribution companies (“LDCs”) and large utilities. Under El Paso’s old “bundled” scheme, it purchased the gas from the well-head producer, transported it through its pipelines, and then sold it to LDCs and utilities at their' “city gates.” Under the proposed Global Settlement, the LDCs and utilities would buy gas from a supplier, either El Paso or a third party, at “mainline receipt points” in gas production areas; from that point, El Paso would transport (or “provide capacity for”) the gas already bought by the LDCs and utilities.

As part of this seismic restructuring, El Paso proposed a pro rata method of “curtailing” its new unbundled transportation customers, ie., reducing the amount of gas they received in force majeure or other circumstances2 when El Paso lacked the capacity [229]*229on its pipeline simultaneously to meet all its transportation customers’ demands. Until the Global Settlement, the method of allocating scarce pipeline capacity during an emergency was not a major problem for El Paso and its customers. Nearly the entire capacity of the pipeline was devoted to meeting El Paso’s bundled sales obligations, • i.e., to transporting El Paso-owned gas to sales customers’ city gates. Thus, almost all of El Paso’s capacity was subject to the curtailment plan covering its sales of gas; if El Paso could not make good on all its sales obligations — because of either a capacity constraint or, more likely, a supply shortage — it would look to the end use of the gas in deciding which customers it would curtail. El Paso’s plan adopted the end-user pecking order mandated by NGPA § 401, 15 U.S.C. § 3391(a), for “curtailment[s] of deliveries” of natural gas: “high-priority” end-users received gas first, then “essential agricultural” end-users, and on down the statutorily mandated line. See generally Process Gas Consumers Group v. United States Department of Agriculture, 657 F.2d 459, 460 ((D.C.Cir.1981) (summarizing the curtailment priorities required by § 401). But as part of its unbundling proposal, El Paso now sought to apply different curtailment plans to its newly-distinct transportation and sales services. For supply-based curtailments affecting its sales of gas at the mainline receipt points in the production area, El Paso would still apply an end-use curtailment plan. But for capacity constraint curtailments affecting its transportation service from the mainline receipt points, it proposed to apply a pro rata scheme. Scarce capacity would go first — “off the top” — to El Paso’s smallest firm transportation customers (those served under Rate Schedule FTS-S); the remainder would be divvied up among the rest of the firm customers (served under Rate Schedule T-3) pro rata, i.e., firm transportation customers would get a percentage of the available capacity equal to the percentage of El Paso’s overall capacity they had contracted for.

The El Paso Municipal Consumer Group (the “Municipal Group”), an organization that includes the petitioners, LDCs served under the T-3 Rate Schedule, as well as smaller LDCs served under the FTS-S Rate Schedule, argued to the FERC that El Paso’s plan should be modified to require scarce capacity to be allocated to protect the high-priority end-users they served. The Commission, however, rejected their proposal and on March 20, 1991, issued an order approving the Global Settlement, including its pro rata capacity constraint curtailment provisions. Explaining its decision, the Commission said that since the Global Settlement gave the small FTS-S customers capacity “off the top” in periods of capacity constraint, the Municipal Group’s objections were either “moot or resolve[d] ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
993 F.2d 888, 301 U.S. App. D.C. 226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-mesa-v-federal-energy-regulatory-commission-cadc-1993.