City of Klamath Falls v. Environmental Quality Commission

870 P.2d 825, 318 Or. 532, 38 ERC (BNA) 1709, 1994 Ore. LEXIS 21
CourtOregon Supreme Court
DecidedApril 7, 1994
DocketCA A72620; SC S40270
StatusPublished
Cited by18 cases

This text of 870 P.2d 825 (City of Klamath Falls v. Environmental Quality Commission) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Klamath Falls v. Environmental Quality Commission, 870 P.2d 825, 318 Or. 532, 38 ERC (BNA) 1709, 1994 Ore. LEXIS 21 (Or. 1994).

Opinion

*535 FADELEY, J.

This proceeding arises from an Environmental Quality Commission (EQC) contested case order denying certification to the City of Klamath Falls’ proposed Salt Cave hydroelectric project. The EQC denied certification on the basis of a regulation that limits development-caused changes in the temperature of river water. On judicial review, the Court of Appeals affirmed, and we allowed review of that decision. At issue is whether the EQC’s interpretation and application of OAR 340-41-965(2)(b)(A), 1 a regulation or standard prohibiting water temperature changes caused by development, is in error. For the reasons that follow, we affirm.

FACTS

In July 1986, the City submitted an application to the Federal Energy Regulatory Commission (FERC) for a license for a hydroelectric project to be located on the Upper Klamath River. The application proposed the building of a dam and a reservoir. Section 401 of the Federal Clean Water Act, 33 USC § 1341, requires the state to “certify” the project as a prerequisite to federal licensing. In August 1987, the Department of Environmental Quality (DEQ) declined to *536 certify the project. The City then reapplied for certification. Acting on the second application for certification, DEQ certified the project in July of 1988, but did so subject to 13 conditions related to that proposal. As will appear more fully later in this opinion, the City has altered the nature of its request before DEQ so that, strictly speaking, a new dam and reservoir, as such, are no longer involved in the project. State certification before federal licensing is still required, however.

In July 1990, FERC issued an Environmental Impact Statement (EIS) for the project that the City seeks to have certified by the state agency. The EIS concluded that an alternative proposal for hydroelectric generation was environmentally preferred. That alternative proposal would not require the construction of a dam or a reservoir, which each previous version of the project had envisioned. Instead, a concrete wall and diversion pool would be constructed to intercept and divert river water at the point of its discharge from the tailrace of an existing hydroelectric facility, the J.C. Boyle project. The diverted river water would then be channeled via a conduit and tunnel, running along the river canyon, to a new powerhouse 10 miles down stream. The water would go through a forebay, penstock, and generating turbine there and then be returned to the river. The FERC’s EIS recommended that FERC license this “No-Dam” alternative.

On June 5, 1990, the City applied to DEQ to certify the alternative proposal involving diversion of the water from the river. In a letter dated February 7, 1991, the Director of DEQ denied certification on the grounds that the alternative plan “would not comply with the water quality standard for temperature [OAR 340-41-965(2)(b)] during the winter months,” nor “with the narrative standard for Fungi and other growths [OAR 340-41-965(2)(h)],” and “would violate the anti-degradation standard to the’ detriment of designated beneficial uses [OAR 340-41-026(1), 340-41-962, 340-41-965(1)].” (Brackets in original.) Pursuant to OAR 340-48-035, the City requested a contested case hearing before the EQC to contest the Director’s denial. 2

*537 During the contested case, DEQ withdrew the portion of the Director’s determination that found that the proposed project would violate the fungi standard, OAR 340-41-965(2)(h). On October 21, 1991, EQC concluded, contrary to the earlier ruling of DEQ Director, that the project “would not violate the Anti-Degradation standard, as set forth in OAR 340-41-026(1), 340-41-962, and 340-41-965(1), because water quality changes caused by the project would not adversely affect a designated beneficial use on the Klamath River.” However, EQC also concluded, as had the DEQ Director, that the project “would violate the Temperature standard, as set forth in OAR 340-41-962(2)(b)(A) [sic], because the project would increase water temperatures by more than 0.5°F when receiving waters are 57.5°F or less.” Accordingly, EQC affirmed the Director’s decision to deny certification. 3

The City petitioned to the Court of Appeals for judicial review. The City made three assignments of error. One alleged that “EQC erred by denying certification for the Project based on EQC’s holding that the temperature standard is ‘absolute as a matter of law.’ ” 4 The Court of Appeals, *538 with one judge dissenting, affirmed the order on all assignments of error. City of Klamath Falls v. Environ. Quality Comm., 119 Or App 375, 851 P2d 602 (1993). The City then petitioned this court for review. We allowed the City’s petition, but limited our review to the claim of error related to the water temperature standard issue.

ANALYSIS

ORS 183.482(8)(a) authorizes the Court of Appeals and this court to review an agency order in a contested case for erroneous applications or interpretations of law. ORS 183.482(8)(a) provides:

“The court may affirm, reverse or remand the order. If the court finds that the agency has erroneously interpreted a provision of law and that a correct interpretation compels a particular action, it shall:
“(A) Set aside or modify the order; or
“(B) Remand the case to the agency for further action under a correct interpretation of the provision of law.”

Here, we are asked to review an agency’s application of its own regulation to the City’s proposed hydroelectric project. In the instant case, EQC found that, “[t]he Salt Caves project would at times result in an increase in the Klamath River’s water temperature of greater than 0.5°F when existing water temperatures are 57.5°F or less.” 5 EQC then concluded as a matter of law that “[t]he Salt Caves project would violate the Temperature standard as set forth in OAR 340-41-962(2)(b)(A) [sic],” even though EQC also found as fact that, “[o]n balance, the impacts of the Salt *539 Caves project’s water quality changes on trout would not be adverse to the trout or the fishery.” 6

The City contends that the EQC erred as a matter of law when it denied the City certification based on the temperature standard regulation. The City asserts three arguments in support of that claim. All three concern the EQC’s interpretation of its temperature standard regulation to be mandatorily applicable to the City’s project.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stella v. Dept. of Human Services
344 Or. App. 38 (Court of Appeals of Oregon, 2025)
Marteeny v. Brown
517 P.3d 343 (Court of Appeals of Oregon, 2022)
City of Portland v. Building Codes Div.
496 P.3d 1108 (Court of Appeals of Oregon, 2021)
SIF Energy, LLC v. State ex rel. Department of Energy
365 P.3d 664 (Court of Appeals of Oregon, 2015)
Crystal Communications, Inc. v. Department of Revenue
297 P.3d 1256 (Oregon Supreme Court, 2013)
Joyce v. Public Employees Retirement Board
147 P.3d 379 (Court of Appeals of Oregon, 2006)
Pebb v. Ohsu
132 P.3d 1061 (Court of Appeals of Oregon, 2006)
Stanley v. Driver & Motor Vehicle Services Branch
89 P.3d 1186 (Court of Appeals of Oregon, 2004)
Haskins v. Palmateer
63 P.3d 31 (Court of Appeals of Oregon, 2003)
Gaynor v. Board of Parole & Post-Prison Supervision
996 P.2d 1020 (Court of Appeals of Oregon, 2000)
Beaver Creek Cooperative Telephone Co. v. Public Utility Commission
986 P.2d 592 (Court of Appeals of Oregon, 1999)
Evans v. Attorney General
939 P.2d 111 (Court of Appeals of Oregon, 1997)
Lee v. Oregon Racing Commission
920 P.2d 554 (Court of Appeals of Oregon, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
870 P.2d 825, 318 Or. 532, 38 ERC (BNA) 1709, 1994 Ore. LEXIS 21, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-klamath-falls-v-environmental-quality-commission-or-1994.