SIF Energy, LLC v. State ex rel. Department of Energy

365 P.3d 664, 275 Or. App. 809, 2015 Ore. App. LEXIS 1593
CourtCourt of Appeals of Oregon
DecidedDecember 30, 2015
Docket102273; A150875
StatusPublished
Cited by1 cases

This text of 365 P.3d 664 (SIF Energy, LLC v. State ex rel. Department of Energy) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SIF Energy, LLC v. State ex rel. Department of Energy, 365 P.3d 664, 275 Or. App. 809, 2015 Ore. App. LEXIS 1593 (Or. Ct. App. 2015).

Opinion

NAKAMOTO, J.

This case concerns the proper amount of tax credit that petitioner should have received for its renewable energy facility under Oregon’s business energy tax credit program. A business energy tax credit is calculated based on the “certified cost” of constructing such a facility, as determined by the Oregon Department of Energy. Petitioner built a renewable energy facility for which it was eligible for a business energy tax credit. Although petitioner’s actual construction cost was more than its estimated cost, the department used the estimated cost as the certified cost for tax credit purposes. Petitioner challenged that cost certification order in the circuit court, and it now appeals a judgment affirming the department’s order. Petitioner argues that, by statute, the department was required to certify all of petitioner’s actual, eligible costs, up to 110 percent of the estimated cost. The department has interpreted the statute differently; it contends that the statute granted the agency discretion to certify any amount of actual, eligible costs between 100 and 110 percent of petitioner’s estimated cost. We conclude that the statute required the department to certify all of petitioner’s actual, eligible costs, up to 110 percent of the estimated cost; therefore, the trial court erred in affirming the department’s cost certification order. Accordingly we reverse and remand.

I. BACKGROUND

A business energy tax credit is a credit against Oregon income taxes based on the “certified cost” of capital investments in areas such as renewable energy resources. ORS 315.354. For a taxpayer to claim the credit, the Director of the Oregon Department of Energy must issue “final certification” of a facility after the investment is completed, which establishes eligibility for the credit. Former ORS 469.215 (2009), renumbered as ORS 469B.161 (2011);1 ORS 315.354. Applying for the requisite final certification is a two-step process. First, the owner of a facility must apply for a “preliminary certificate,” by submitting a project description and [812]*812cost estimate to the department. ORS 469.205(1), (2)(b), (d). If the department approves the project, it issues a preliminary certification that approves the amount of project costs eligible for a business energy tax credit. ORS 469.210(2); OAR 330-090-0130(3)(b)(A). Second, once the project is completed, the owner of the facility must apply for the final certification, by submitting, among other things, verification from a certified public accountant (CPA) of the “actual cost” of the project. ORS 469.215(2) - (3).

Then, before the owner can receive a tax credit, the department must “certify the facility,” ORS 469.215(6); ORS 315.354, an action that includes “certification of the actual cost of the facility,” ORS 469.215(4). “However, the director may not certify an amount for tax credit purposes which is more than 10 percent in excess of the amount approved in the preliminary certificate issued for the facility.” ORS 469.215(4). This case centers on the interaction between those final certification procedures and concerns the department’s certification obligations when the actual cost of constructing a facility is more than the estimated cost.

The facts in this case are undisputed. In 2008, the department issued a preliminary certification for petitioner’s biogas facility, approving $8,879,962 in projected construction costs. Petitioner completed its facility in 2009 and submitted its application for final certification. That application contained the required CPA verification of petitioner’s actual construction costs, which were $11,098,501. Thus, petitioner’s claimed actual construction costs were $2,218,539 — or about 25 percent — more than petitioner’s estimated costs.

When petitioner submitted its 2009 application for final certification, the department’s administrative rule provided that a final certification “may be up to 10 percent more than the amount approved in the preliminary certification.” Former OAR 330-090-0130(9)(b)(A) (June 20, 2008). However, while petitioner’s application for final certification was pending, the department promulgated temporary rules deleting that provision. See former OAR 330-090-0133(1) (Nov 3, 2009) (preserving final certification process rule but eliminating cost overrun provision). The new rules were [813]*813made applicable to all pending applications and future applications, for which no final certification determination had been made. Former OAR 330-090-0105(3) (Nov 3, 2009).

The department finally certified petitioner’s facility in 2010, using petitioner’s estimated cost of $8,879,962 to calculate petitioner’s tax credit. Petitioner requested that the agency reconsider that amount, asserting that ORS 469.215(4) compelled the agency to calculate petitioner’s tax credit by using $9,767,958.20—110 percent of the petitioner’s approved estimated cost. The department denied the request, explaining that it had “discontinued the practice of issuing a tax credit for more than the pre-certified amount” when it promulgated the temporary rules in 2009.

Petitioner sought review of the department’s order in the circuit court, pursuant to ORS 183.484 (providing jurisdiction for judicial review of orders in other than contested cases), and both parties filed cross-motions for partial summary judgment. The court granted partial summary judgment for the department and denied it for petitioner, in effect affirming the department’s order and concluding that “the law and OAR in effect at the time of submission clearly * * * provided that discretion would be allowed in determining whether or not a cost overrun would be considered for the tax credit.”

II. ANALYSIS

On appeal, petitioner raises three assignments of error concerning the court’s grant of the department’s motion for summary judgment and denial of petitioner’s own motion on its petition for review in the circuit court. The dispositive legal issue, however, is whether ORS 469.215

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chu v. SAIF Corp. (In re Chu)
415 P.3d 68 (Court of Appeals of Oregon, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
365 P.3d 664, 275 Or. App. 809, 2015 Ore. App. LEXIS 1593, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sif-energy-llc-v-state-ex-rel-department-of-energy-orctapp-2015.