City of High Point v. Duke Power Co.

120 F.2d 866, 1941 U.S. App. LEXIS 3575
CourtCourt of Appeals for the Fourth Circuit
DecidedJune 10, 1941
DocketNo. 4759
StatusPublished
Cited by3 cases

This text of 120 F.2d 866 (City of High Point v. Duke Power Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of High Point v. Duke Power Co., 120 F.2d 866, 1941 U.S. App. LEXIS 3575 (4th Cir. 1941).

Opinion

PARKER, Circuit Judge.

These are cross appeals in an action instituted by the City of High Point, North Carolina, as plaintiff, against the Duke Power Company, as defendant, to recover over-payments alleged to have been made for electric current furnished by defendant to plaintiff between March 1, 1935 and April 23, 1938. Defendant filed counterclaim to recover for current furnished by it to plaintiff following the last named date. The case was heard before the judge without a jury. He denied recovery to plaintiff and gave judgment for defendant on its counterclaim in the sum of 8127,435.94 with interest from April 24, 1939 for electric current furnished plaintiff between April 23, 1938 and April 24, 1939, together with the sum of $5,671.01 for miscellaneous power, not in dispute. Plaintiff complains on this appeal of the denial of its claim of over-payment and of the allowance of interest on the amount allowed defendant on its counterclaim. Defendant complains because recovery was not allowed on its counterclaim on the basis of a higher rate [868]*868schedule. The facts relevant to the questions presented are as follows:

The power company and its predecessors in interest had been furnishing electric current to the city for a number of years prior to 1935. It was engaged also in furnishing electric current to manufacturers and others in High Point and vicinity for power purposes. In 1932 it entered into contracts with the city under which the city agreed not to resell power purchased “to any consumer for any one motor in excess of five horsepower capacity.” Immediately 'prior to March 1, 1935, power was being furnished the city pursuant to such contracts under a schedule designated by the power company as schedule 8A.1 These contracts were terminated by the city as of March 1, 1935 and notice was given the power company that the city intended to purchase current on a “month to month basis upon such terms as may be mutually agreed upon”. No terms were agreed upon, but the power company continued to furnish current and the city continued to make monthly payment for same at the rates prescribed by schedule 8A until April 23, 1938. After that date the power company continued to furnish current but the city made no further payments.

Prior to March 1, 1935, the power company filed with the North Carolina Utilities Commission its rate schedule No. 10 as an additional schedule to others on file with the commission. It differed from other schedules in that it contained a demand feature in addition to an energy charge. For customers with a constant demand it offered opportunity for savings; but for customers with an uneven demand schedule 8A was more favorable. The city authorities decided that for two of its contracts schedule 10 was the more favorable and asked that contracts for furnishing current under that schedule be executed by the power company. The company tendered such contracts but included therein the clause against resale of current which had been carried in prior contracts. The city refused to execute the contracts with these provisions and the power company refused to execute same without them. The power company contended that it could not be required to sell power to be resold by the purchaser in competition with its power business and was entitled to provide against such competitive resale in its contracts. The city contended that this position was not open to the power company because it was operating under a franchise which provided that the grantee should not sell electric current in opposition to the city. No settlement of this controversy was reached; but, as stated above, the power company continued to supply current to the city and bill the city for same monthly on the basis of the rates contained in schedule 8A, and the city, until April 23, 1938, continued to make payment for the current so furnished on the basis of these billings.

No protest was made by the city when making the payments under schedule 8A. Suit for recovery of the overpayments was instituted August 19, 1937; but payments under schedule 8A were continued thereafter until April 23, 1938. There was no protest at the time such payments were made and there was no agreement or even notice that they were made subject to the outcome of the suit.

Both schedule 8A and schedule 10 provided that electric current would be supplied at the rates therein specified only in cases where annual contracts were executed by the customer, and no such contracts were executed by the city subsequent to March 1, 1935. At a number of points at which current was received by the city it was advantageous to it to apply the rates prescribed by schedule 8Á; and no controversy is presented as to the current delivered at these points. While no contract was executed for delivery of current under schedule 10 at the other two points, it was delivered and accepted at these points for the twelve months’ period from April 23, 1938, to April 24, 1939, in no different manner from that which would have been followed if a contract under schedule 10 had been executed. It appears, also, that such contract would have been executed but for the insistence of the power company that the provision limiting the right of resale of current be included therein. The power company was selling current to a number of other municipalities in North Carolina during this period at the rates prescribed by schedule 10 under contracts containing no [869]*869restrictive provision as to resale; and no resales are shown to have been made by the city during the period which would have been violative oí' the provision, had a contract containing such provision been executed.

The findings of the court below embraced the foregoing mailers and a number of others which, in the view that we take of the case, we need not consider. The judge held that the charges for current delivered between March 1, 1935, and April 23, 1938, were not unlawful or discriminatory and that since payments for same were voluntarily made by the city with knowledge of all the facts, no part thereof could be recovered. With respect to the current delivered between April 23, 1938, and April 24, 1939, he held that, as no contract existed prescribing the rates to be charged therefor, the rates prescribed by schedule 10 should he applied as the reasonable value of the current, and entered judgment for defendant accordingly, with interest from April 24, 1939.

We need not consider whether the power company was within its rights in insisting upon the incorporation in the contract of the clause restricting the resale of current, or whether the provisions of the franchise forbade it to sell current for power purposes in competition with the city. All arguments addressed to these questions become moot in view of the fact that no contract of any sort was executed and consequently no rights arising out of any such contracts are here involved. On one branch of the case, the question is whether rates in excess of legal rates were collected by the power company from the city under such circumstances as would warrant the recovery of the overcharge; on the other branch, the question is what is the reasonable rate to apply for current for which no payment has been made.

On the first question, we cannot say that the city was entitled as a matter of law to the rates specified in schedule 10; for the rates of schedule 8A as well as the rates of schedule 10 were legal rates.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Sac City v. Bentsen
329 N.W.2d 675 (Court of Appeals of Iowa, 1982)
American Yearbook Company v. Askew
339 F. Supp. 719 (M.D. Florida, 1972)
Thompson v. Baltimore & OR Co.
59 F. Supp. 21 (E.D. Missouri, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
120 F.2d 866, 1941 U.S. App. LEXIS 3575, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-high-point-v-duke-power-co-ca4-1941.