City of College Park v. Georgia Interlocal Risk Management Agency

721 S.E.2d 97, 313 Ga. App. 239, 2011 Fulton County D. Rep. 3217, 2011 Ga. App. LEXIS 876
CourtCourt of Appeals of Georgia
DecidedOctober 11, 2011
DocketA11A1115, A11A1116
StatusPublished
Cited by4 cases

This text of 721 S.E.2d 97 (City of College Park v. Georgia Interlocal Risk Management Agency) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of College Park v. Georgia Interlocal Risk Management Agency, 721 S.E.2d 97, 313 Ga. App. 239, 2011 Fulton County D. Rep. 3217, 2011 Ga. App. LEXIS 876 (Ga. Ct. App. 2011).

Opinion

PHIPPS, Presiding Judge.

The City of College Park was sued by a subcontractor, which complained that it had not been paid for work it performed on College Park’s property. College Park, a participant in the Georgia Interlocal Risk Management Agency (GIRMA), 1 submitted a claim to GIRMA seeking a defense and indemnity. GIRMA denied the claim. College Park filed suit against GIRMA, alleging breach of contract and seeking attorney fees. On cross-motions for summary judgment, the trial court ruled in favor of College Park with respect to the breach of contract claim; the court ruled in favor of GIRMA on the attorney fees claim.

These appeals challenge those rulings. In Case No. A11A1115, College Park contests the denial of its claim for attorney fees; in Case No. A11A1116, GIRMA maintains it was entitled to summary judgment on the breach of contract claim. Because College Park failed to show that GIRMA was contractually obligated to provide a defense and indemnity, we reverse the trial court’s judgment pertaining to the breach of contract claim and affirm the judgment with respect to the attorney fees claim.

The relevant facts are not in dispute. In 2005, College Park hired a contractor, Southern Products, Inc., to perform repairs to some of its sewer pipes. In turn, the contractor hired Sekisui SPR Americas, *240 LLC to serve as a subcontractor on the project. In September 2005, Sekisui sent its first invoice to Southern Products in the amount of $18,646.79, which Southern Products paid after it submitted its application for payment to College Park. In October and December 2005, Sekisui sent second and third invoices to Southern Products in the amounts of $82,829.24 and $231,339.15, which were not paid to it either by Southern Products or by College Park. College Park, however, paid the entire amount it owed to Southern Products for services rendered on the project.

Consequently, Sekisui filed suit against Southern Products for breach of contract. After apparently determining that Southern Products had ceased operating and was insolvent, Sekisui filed suit against College Park, seeking damages in the amount owed it ($314,168.39), but not paid due to Southern Products’ alleged breach of contract. Among the causes of action set forth in its lawsuit, 2 Sekisui alleged that College Park had failed to obtain a payment bond or other security in violation of the Georgia Local Government Public Works Construction Law. 3

College Park tendered the claim against it to GIRMA pursuant to their Member Coverage Agreement. GIRMA denied the claim, citing an exclusion clause in that Agreement.

This action ensued. College Park filed a complaint against GIRMA, alleging that GIRMA had wrongfully denied the claim it submitted, that it (College Park) had been forced to litigate the case Sekisui filed against it, and that it had incurred formidable costs. College Park set forth in its complaint three separate counts: breach of contract, declaratory judgment, and attorney fees. College Park next filed a motion for summary judgment. Therein, it sought a ruling that the claim submitted to GIRMA was covered under their Agreement; it sought a ruling as to liability on the breach of contract claim, specifically that GIRMA had breached its duty to provide a *241 defense under the Agreement; and it sought a ruling that, because of GIRMA’s conduct, GIRMA should be required to pay College Park’s attorney fees.

In its motion for summary judgment, GIRMA argued that it had not breached the Agreement because the Agreement did not provide for the coverage demanded by College Park and that College Park was therefore not entitled to attorney fees.

After a hearing on the motions, 4 the trial court entered an order granting College Park’s motion for partial summary judgment on the breach of contract claim, thus determining that the Agreement provided coverage for the claim. The trial court granted summary judgment in GIRMA’s favor on the attorney fees claim.

“[T]o prevail on a motion for summary judgment, the moving party must demonstrate that there is no genuine issue of material fact, so that the party is entitled to judgment as a matter of law.” 5 “In our de novo review of the grant of a motion for summary judgment, we must view the evidence, and all reasonable inferences drawn therefrom, in the light most favorable to the nonmovant.” 6

Because our decision in Case No. A11A1115 turns on our resolution of Case No. A11A1116, we address the latter case first.

Case No. A11A1116

1. Citing cases such as Drawdy v. Direct Gen. Ins. Co., 7 GIRMA contends that “[t]he trial court lacked subject matter jurisdiction to enter a declaratory judgment.” Pretermitting whether GIRMA waived this contention by not raising it below, we find it unavailing.

Nomenclature aside, 8 it is clear from the record that College Park did not seek merely the entry of a declaratory judgment. 9 After GIRMA denied College Park’s claim, College Park sought recourse by *242 filing a lawsuit against GIRMA asserting, inter alia, a breach of contract theory. Regarding the essential element of “breach,” 10 College Park alleged that GIRMA had a duty to provide coverage for the claim, but refused to do so. To test the merits of that breach of contract claim, the parties filed their respective summary judgment motions. 11 The trial court was authorized to decide the issues presented thereby. 12 Contrary to GIRMA’s contention, cases such as Drawdy do not provide for a conclusion that the trial court’s rulings were not authorized. 13

2. GIRMA contends that it is entitled to summary judgment on College Park’s breach of contract claim. Challenging the trial court’s rulings with respect thereto, GIRMA maintains that the Agreement excluded coverage of the claim submitted by College Park.

The Agreement provided coverage for any “Wrongful Act.” The Agreement defined “Wrongful Act,” in pertinent part, as “any actual or alleged error or misstatement, omission, act of neglect or breach of duty including misfeasance, malfeasance and non-feasance by [College Park] committed during the Coverage Agreement Period.” GIRMA has conceded before the trial court and this court that College Park’s claim fell within that particular language. Nevertheless, GIRMA maintains, it properly denied the claim because of an exclusion that coverage was not provided for any claim against College Park that was “arising out of or in any way connected with breach of contract.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

HARRISON v. McAFEE Et Al.
788 S.E.2d 872 (Court of Appeals of Georgia, 2016)
Georgia Interlocal Risk Management Agency v. City of Sandy Springs
788 S.E.2d 74 (Court of Appeals of Georgia, 2016)
City of College Park v. Sekisui SPR Americas, LLC
771 S.E.2d 101 (Court of Appeals of Georgia, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
721 S.E.2d 97, 313 Ga. App. 239, 2011 Fulton County D. Rep. 3217, 2011 Ga. App. LEXIS 876, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-college-park-v-georgia-interlocal-risk-management-agency-gactapp-2011.