City of College Park, Georgia v. Sekisui Spr Americas, LLC

CourtCourt of Appeals of Georgia
DecidedMarch 20, 2015
DocketA14A1690
StatusPublished

This text of City of College Park, Georgia v. Sekisui Spr Americas, LLC (City of College Park, Georgia v. Sekisui Spr Americas, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of College Park, Georgia v. Sekisui Spr Americas, LLC, (Ga. Ct. App. 2015).

Opinion

WHOLE COURT

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. http://www.gaappeals.us/rules/

March 20, 2015

In the Court of Appeals of Georgia A14A1690. CITY OF COLLEGE PARK v. SEKISUI SPR AMERICAS, LLC.

MILLER, Judge.

Sekisui SPR Americas, LLC, a subcontractor that worked on a sewer project

for the City of College Park (“the City”), sued the City when the general contractor

failed to pay Sekisui for work performed, alleging that the City was liable because it

had failed to ensure the contractor obtained a payment bond in violation of OCGA §

36-91-90. In addition to raising a cause of action under OCGA § 36-91-90 et seq.,

Sekisui also raised claims of quantum merit, unjust enrichment, implied obligation

to pay, and sought attorney fees. The parties filed cross-motions for summary

judgment, and the trial court granted Sekisui’s motion and denied the City’s motion.

The City appeals, contending that the trial court erred in denying its motion to dismiss the case for failure to comply with the ante litem notice requirements for suits against

municipalities. The City also contends that the trial court erred in granting summary

judgment to Sekisui because the undisputed evidence showed that Sekisui was not

entitled to relief for a violation of OCGA § 36-91-90, Sekisui was precluded from

pursuing other forms of relief, and questions of fact remained as to damages.1 Since

Sekisui does not have a viable claim against the City, we reverse.

“Summary judgment is appropriate when the moving party demonstrates that

no genuine issues of material fact remain and that the facts, construed favorably to

the nonmoving party, demand judgment as a matter of law. On appeal, we review the

trial court’s grant of summary judgment de novo.” (Footnote omitted.) Vaillant v. City

of Atlanta, 267 Ga. App. 294 (599 SE2d 261) (2004).

So viewed, the evidence shows that during the summer of 2005, the City began

discussing the need for public works construction on sewer lines in the city, including

1 The City attached several exhibits to its brief that caused the brief to substantially exceed the applicable page limit. See Court of Appeals Rule 24 (f). Sekisui moved to strike the excess pages, and the City responded by moving for permission to exceed the page limit. Since these exhibits appear in the record transmitted by the trial court, Sekisui would suffer no prejudice by consideration of the excess pages. See Court of Appeals Rule 24 (g) (we will not consider documents attached to an appellate brief that are not part of the certified appellate record). Consequently, we grant the City’s motion to exceed the applicable page limit and deny Sekisui’s motion to strike.

2 the repair of the main sewer line on Embassy Drive that had apparently collapsed and

needed emergency repair. Southern Products submitted a quote to install a sewer

bypass near the creek adjacent to the intersection of Riverdale Road and Embassy

Drive. On August 5, 2005, the City approved the quote and directed Southern

Products to begin as soon as possible.

On August 8, Southern Products sent a letter requesting that the City use its

existing Clayton County Water Authority Annual Contract (the “CCWA Contract”)

in order to replace approximately 1,049 linear feet of the ten-inch sewer pipe near

Embassy Drive (the “Embassy Drive Project”). Southern Products estimated that this

project would cost $204,481.50. In the August 8 letter, Southern Products offered to

absorb some of the costs associated with maintaining the bypass system during any

delay with the start of the sewer line replacement.

The City sought permission from Clayton County to use the CCWA Contract

to complete the Embassy Drive Project. Clayton County authorized the City to use the

CCWA Contract to establish the terms, unit pricing, and conditions of work in

reaching an agreement with Southern Products, but notified the City that the CCWA

Contract would not be extended to cover the Embassy Drive Project.

3 Thereafter, the City contracted with Southern Products to complete the

Embassy Drive Project, notifying Southern Products that it was to proceed pursuant

to the terms of the CCWA Contract. The CCWA Contract pertinently provided that

a “Payment and Performance bond will be required only in the event that a job is

assigned to the contractor that is an amount greater than $100,000.00.” Southern

Products did not obtain a payment bond for the Embassy Drive Project.

Southern Products hired Sekisui as a subcontractor to provide all labor,

equipment, and materials, as well as general and project administration services, for

the Embassy Drive Project. See City of College Park v. Georgia Interlocal Risk

Managment Agency, 313 Ga. App. 239, 239-240 (721 SE2d 97) (2011) (“GIRMA”).

Sekisui began working on the project in September 2005, and at the end of the month,

Sekisui submitted its first invoice to Southern Products, who paid it after receiving

payment from the City. Id. at 240. Based on circumstances at the site, the scope of

work increased and the cost of the project exceeded the initial estimate. In October

and December 2005, Sekisui submitted two additional invoices totaling over

$314,000. The City paid Southern Products in full for Sekisui’s work on the Embassy

Drive Project, but Southern Products did not pay Sekisui’s last two invoices. See id.

4 When its attempts to recover on the unpaid invoices were unsuccessful, Sekisui

filed suit against Southern Products, which subsequently ceased operations and

became insolvent. Sekisui also filed the instant suit against the City, and the trial

court granted summary judgment to Sekisui on all counts, with the exception of

attorney fees, which the trial court reserved upon conclusion of this appeal.

1. On appeal, the City contends that the trial court erred in denying its motion

to dismiss Sekisui’s complaint on the ground that Sekisui failed to give proper ante

litem notice under OCGA § 36-33-5. We disagree.

As part of the Georgia Local Government Public Works Construction Law,

OCGA § 36-91-1 et seq., a payment bond or other security in lieu of the bond is

required for all public works construction contracts with an estimated contract

amount greater than $100,000. OCGA § 36-91-90. “If a payment bond or security

deposit is not taken in the manner and form required in this article, the corporation

or body for which work is done under the contract shall be liable to all subcontractors

. . . furnishing labor, skill, tools, machinery, or materials to the contractor . . . for any

loss resulting to them from such failure.” OCGA § 36-91-91.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hussey, Gay & Bell v. Georgia Ports Authority
420 S.E.2d 50 (Court of Appeals of Georgia, 1992)
Sims v. City of Alpharetta
428 S.E.2d 94 (Court of Appeals of Georgia, 1993)
Neely v. City of Riverdale
681 S.E.2d 677 (Court of Appeals of Georgia, 2009)
Jacks v. City of Atlanta
644 S.E.2d 150 (Court of Appeals of Georgia, 2007)
Callahan v. Hall
691 S.E.2d 918 (Court of Appeals of Georgia, 2010)
Vaillant v. City of Atlanta
599 S.E.2d 261 (Court of Appeals of Georgia, 2004)
J. Kinson Cook, Inc. v. Weaver
556 S.E.2d 831 (Court of Appeals of Georgia, 2001)
McArthur Electric, Inc. v. Cobb County School District
642 S.E.2d 830 (Supreme Court of Georgia, 2007)
CITY OF STATESBORO v. Dabbs
715 S.E.2d 73 (Supreme Court of Georgia, 2011)
City of College Park v. Georgia Interlocal Risk Management Agency
721 S.E.2d 97 (Court of Appeals of Georgia, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
City of College Park, Georgia v. Sekisui Spr Americas, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-college-park-georgia-v-sekisui-spr-americas-llc-gactapp-2015.