City of College Park v. Sekisui SPR Americas, LLC

771 S.E.2d 101, 331 Ga. App. 404, 2015 Ga. App. LEXIS 177
CourtCourt of Appeals of Georgia
DecidedMarch 20, 2015
DocketA14A1690
StatusPublished
Cited by2 cases

This text of 771 S.E.2d 101 (City of College Park v. Sekisui SPR Americas, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of College Park v. Sekisui SPR Americas, LLC, 771 S.E.2d 101, 331 Ga. App. 404, 2015 Ga. App. LEXIS 177 (Ga. Ct. App. 2015).

Opinion

Miller, Judge.

Sekisui SPR Americas, LLC, a subcontractor that worked on a sewer project for the City of College Park (“the City”), sued the City when the general contractor failed to pay Sekisui for work performed, alleging that the City was liable because it had failed to ensure the [405]*405contractor obtained a payment bond in violation of OCGA § 36-91-90. In addition to raising a cause of action under OCGA § 36-91-90 et seq., Sekisui also raised claims of quantum meruit, unjust enrichment, implied obligation to pay, and sought attorney fees. The parties filed cross-motions for summary judgment, and the trial court granted Sekisui’s motion and denied the City’s motion. The City appeals, contending that the trial court erred in denying its motion to dismiss the case for failure to comply with the ante litem notice requirements for suits against municipalities. The City also contends that the trial court erred in granting summary judgment to Sekisui because the undisputed evidence showed that Sekisui was not entitled to relief for a violation of OCGA § 36-91-90, Sekisui was precluded from pursuing other forms of relief, and questions of fact remained as to damages.1 Since Sekisui does not have a viable claim against the City, we reverse.

Summary judgment is appropriate when the moving party demonstrates that no genuine issues of material fact remain and that the facts, construed favorably to the non-moving party, demand judgment as a matter of law. On appeal, we review the trial court’s grant of summary judgment de novo.

(Footnote omitted.) Vaillant v. City of Atlanta, 267 Ga. App. 294 (599 SE2d 261) (2004).

So viewed, the evidence shows that during the summer of 2005, the City began discussing the need for public works construction on sewer lines in the city, including the repair of the main sewer line on Embassy Drive that had apparently collapsed and needed emergency repair. Southern Products submitted a quote to install a sewer bypass near the creek adjacent to the intersection of Riverdale Road and Embassy Drive. On August 5, 2005, the City approved the quote and directed Southern Products to begin as soon as possible.

On August 8, Southern Products sent a letter requesting that the City use its existing Clayton County Water Authority Annual Contract (the “CCWA Contract”) in order to replace approximately 1,049 [406]*406linear feet of the ten-inch sewer pipe near Embassy Drive (the “Embassy Drive Project”). Southern Products estimated that this project would cost $204,481.50. In the August 8 letter, Southern Products offered to absorb some of the costs associated with maintaining the bypass system during any delay with the start of the sewer line replacement.

The City sought permission from Clayton County to use the CCWA Contract to complete the Embassy Drive Project. Clayton County authorized the City to use the CCWA Contract to establish the terms, unit pricing, and conditions of work in reaching an agreement with Southern Products, but notified the City that the CCWA Contract would not be extended to cover the Embassy Drive Project.

Thereafter, the City contracted with Southern Products to complete the Embassy Drive Project, notifying Southern Products that it was to proceed pursuant to the terms of the CCWA Contract. The CCWA Contract pertinently provided that a “Payment and Performance bond will be required only in the event that a job is assigned to the contractor that is an amount greater than $100,000.00.” Southern Products did not obtain a payment bond for the Embassy Drive Project.

Southern Products hired Sekisui as a subcontractor to provide all labor, equipment, and materials, as well as general and project administration services, for the Embassy Drive Project. See City of College Park v. Ga. Interlocal Risk Mgmt. Agency, 313 Ga. App. 239, 239-240 (721 SE2d 97) (2011) (“GIRMA”). Sekisui began working on the project in September 2005, and at the end of the month, Sekisui submitted its first invoice to Southern Products, who paid it after receiving payment from the City. Id. at 240. Based on circumstances at the site, the scope of work increased and the cost of the project exceeded the initial estimate. In October and December 2005, Sekisui submitted two additional invoices totaling over $314,000. The City paid Southern Products in full for Sekisui’s work on the Embassy Drive Project, but Southern Products did not pay Sekisui’s last two invoices. See id.

When its attempts to recover on the unpaid invoices were unsuccessful, Sekisui filed suit against Southern Products, which subsequently ceased operations and became insolvent. Sekisui also filed the instant suit against the City, and the trial court granted summary judgment to Sekisui on all counts, with the exception of attorney fees, which the trial court reserved upon conclusion of this appeal.

1. On appeal, the City contends that the trial court erred in denying its motion to dismiss Sekisui’s complaint on the ground that Sekisui failed to give proper ante litem notice under OCGA § 36-33-5. We disagree.

[407]*407As part of the Georgia Local Government Public Works Construction Law, OCGA § 36-91-1 et seq., a payment bond or other security in lieu of the bond is required for all public works construction contracts with an estimated contract amount greater than $100,000. OCGA § 36-91-90.

If a payment bond or security deposit is not taken in the manner and form required in this article, the corporation or body for which work is done under the contract shall be liable to all subcontractors... furnishing labor, skill, tools, machinery, or materials to the contractor . . . for any loss resulting to them from such failure. . . .

OCGA § 36-91-91.

With regard to ante litem notice, OCGA § 36-33-5 (a) pertinently provides:

No . . . corporation having a claim for money damages against any municipal corporation on account of injuries to person or property shall bring any action against the municipal corporation for such injuries, without first giving notice as provided in this Code section.

OCGA § 36-33-5 (a). The notice must be written and presented within six months of the event upon which the claim is predicated. OCGA § 36-33-5 (b).

The plain text of the statute makes clear that it applies only to tort claims regarding personal injury or property damage. See City of Statesboro v. Dabbs, 289 Ga.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

West v. City of Albany
797 S.E.2d 809 (Supreme Court of Georgia, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
771 S.E.2d 101, 331 Ga. App. 404, 2015 Ga. App. LEXIS 177, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-college-park-v-sekisui-spr-americas-llc-gactapp-2015.