City of Cleveland v. Cleveland Electric Illuminating Co.

538 F. Supp. 1344
District Court, N.D. Ohio·Decided October 16, 1981·No. Civ. A. C75-560·Published·Cited by 2 cases

Opinion

KRUPANSKY, District Judge.

Presently before the Court is the oral motion of the defendant The Cleveland Electric Illuminating Company (CEI) seeking, pursuant to Rule 50(a), Fed.R.Civ.P., a determination that insufficient evidence has been adduced to support the plaintiff City of Cleveland’s contention that the defendant proximately caused the loss of generating capacity attributable to the demise of the City’s 85 mw generating unit. The Court permitted oral argument on this particular issue during the course of proceedings conducted on September 11,1981. See Transcript at pp. 16,390-99; 16,453-58; 16,-469-71. Thereafter, on September 14,1981, the Court, following a comprehensive review of the record, extended to the City a further opportunity to direct the Court’s attention to that evidence of record which bears upon the question of whether the defendant may be properly held accountable for the failure of the 85 mw generating unit. See Transcript at pp. 16,501-04. The plaintiff has, by memorandum of September 15, 1981, responded to the Court’s foregoing request.

The instant record discloses that the plaintiff’s damage claim is premised in substantial part on the fact the City of Cleveland’s Division of Light and Power (commonly referred to as “Muny Light” or “MELP”) no longer possesses generating capacity and is, as such, a “distribution only” system. See e.g. PTX 3041. It is the position of the City that the defendant’s anticompetitive conduct has occasioned, in the words of the plaintiff’s expert economic witness, Dr. Harold H. Wein, “the virtual elimination of MELP as a generating system.” Transcript at p. 16,035.

In advancing its Rule 50(a) motion, however, CEI argues with considerable force that the evidence adduced during the plaintiff’s case-in-chief fails to adequately support the City’s contention that the defendant’s conduct proximately caused the loss of generating capacity attributable to the demise of the 85 mw unit. It should be noted, however, that the motion at bar does not, as the Court understands it, challenge the City’s damage claim insofar as it is predicated upon that loss of generating capacity associated with the three (3) 25 mw gas turbine generating units. See Transcript at pp. 16,394-95; 16,399. That is to say, it would appear to the Court that the instant motion is addressed solely to the question of whether there exists sufficient factual support in the record for the conclusion that the defendant’s allegedly anti-competitive conduct was a substantial factor in bringing about the loss of generating capacity sustained by Muny Light upon the discontinuance of the 85 mw unit.

The City’s attempt to hold the defendant answerable in damages for the loss of generating capacity associated with the 85 mw unit is essentially predicated upon CEI’s failure to provide Muny Light with a permanent synchronous interconnection which the plaintiff maintains, and the evidence suggests, could have been operational as of January, 1973. Transcript at p. 15,566. The City asserts that the defendant’s refusal to interconnect effectively precluded Muny Light from obtaining, during the period January, 1973 to July, 1974, 1 the “back up” power necessary to permit MELP to plan and perform maintenance on the 85 mw unit. It is the position of the plaintiff that the inability of Muny Light to maintain the large unit in a proper state of repair during the January, 1973-July, 1974 period precipitated, at least in substantial part, MELP’s ensuing abandonment of the 85 mw unit.

A review of the record discloses that there is some evidence that the defendant’s *1346 refusal to interconnect adversely affected Muny Light’s ability to maintain and repair the 85 mw unit during the aforesaid period. 2 Warren Hinchee, for example, Muny Light’s Commissioner for the period March, 1971 to October, 1973, testified that while MELP was in fact unable to “adequately maintain the 85-megawatt generator” during the year 1973, the securing of maintenance power over the permanent interconnection would have enabled Muny Light “to plan and execute maintenance” on the large unit and, moreover, operate the unit “in accordance with good utility practice”. Transcript at pp. 11,464; 11,462-63; 11,465. Irv Daniels, Muny Light’s Superintendent of Generation from 1973 until his retirement on April 1, 1976, similarly testified, though without specifically distinguishing between the 85 mw unit and the remainder of MELP’s generating facilities, that the availability of maintenance power over the interconnection would have afforded Muny Light the opportunity to follow “a decent maintenance schedule” and thereby “save a lot of our equipment instead of driving it in the ground like we did.” Transcript at pp. 12,917-18.

The foregoing testimony, while ostensibly supportive of the plaintiff’s position herein, must be assessed in light of that evidence of record which bears upon the hereinbefore alluded to July 17, 1974 explosion, and the MELP response thereto. Such evidence consists primarily of Stipulation 132, which provides in its entirety as follows:

Muny Light’s 85 mw unit was out of service for most of the first half of 1974. On July 17, 1974 this unit suffered an explosion. Both explosion-related repairs and non-explosion-related repairs were done to the 85 mw unit at a cost in excess of $2 million with the intention of putting the unit back into service. The City determined not to complete the repairs and the unit has not operated since.

The substance of Stipulation 132 is supplemented to a limited extent by the testimony of Daniels, who estimated that the post-explosion repairs on the constituent elements of the 85 mw unit, namely, Boiler No. 6 and Turbine No. 11, were 65 per cent complete at the time of his retirement in April, 1976. Transcript at p. 12,916. 3

It is important to note at this juncture that the City advances no claim in this litigation that the July 17th explosion was in any way attributable to the failure of the defendant to provide Muny Light with a permanent synchronous interconnection as of January, 1973. See plaintiff’s Memorandum in Response to Court’s Request for Information of September 14, 1981. Indeed, the principal architect of the City’s damage claim, William R. Mayben, conceded in his testimony of August 27, 1981 that “[tjhere was nothing in [his] mind” which would indicate that the instant explosion was causally related to “the lack of an interconnection”. Transcript at p. 15,571.

Free access — add to your briefcase to read the full text and ask questions with AI

City of Cleveland v. Cleveland Electric Illuminating Co., 538 F. Supp. 1344 (N.D. Ohio 1981).

538 F. Supp. 1344 (City of Cleveland v. Cleveland Electric Illuminating Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Byre v. City of Chamberlain
362 N.W.2d 69 (South Dakota Supreme Court, 1985)