City of Baldwin v. Woodard & Curran, Inc.

730 S.E.2d 486, 316 Ga. App. 768, 2012 Fulton County D. Rep. 2363, 2012 Ga. App. LEXIS 652
CourtCourt of Appeals of Georgia
DecidedJuly 11, 2012
DocketA12A0620
StatusPublished
Cited by10 cases

This text of 730 S.E.2d 486 (City of Baldwin v. Woodard & Curran, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Baldwin v. Woodard & Curran, Inc., 730 S.E.2d 486, 316 Ga. App. 768, 2012 Fulton County D. Rep. 2363, 2012 Ga. App. LEXIS 652 (Ga. Ct. App. 2012).

Opinion

Andrews, Judge.

The City of Baldwin, Georgia (City) appeals after a jury awarded Woodard & Curran, Inc. (W&C) $203,000 on its claim for money owed under a contract to provide services for the City’s wastewater treatment plant. Because there was sufficient evidence to support the award, we affirm.

The record shows that W&C sued for breach of a contract under which it was to be paid for engineering and design services for the City’s water system (May contract). W&C claimed that it provided supporting engineering documents for the City’s application for government stimulus funds to improve the City’s wastewater treatment plant under the May contract and also under a proposal submitted on June 15, 2009 (June proposal). The June proposal was signed by the mayor under “authorization to proceed,” and provided that W&C would be paid a sum “not to exceed $210,000.00.” In the alternative, the complaint asked for damages of $203,870.44 as the value of the services provided to the City.

The City’s position was that it paid the $5,000 owed under the May contract and that was the total amount due. The City stated in its Answer that the mayor’s signing of the June proposal was an ultra vires act and was not binding on the City because it was not approved by a quorum of the city council. The City also stated that the June 2009 proposal was to secure funding and W&C failed to secure the funding; therefore, the City was unable to proceed with the project.

The case went to trial, and the evidence at trial, viewed in the light most favorable to the jury’s verdict,1 was that W&C began operating the City’s wastewater treatment plant in January 2008. In [769]*769conjunction with an application for funding to help improve the plant, W&C agreed to

provide the supporting engineering documents ... in order to convert this project from “fundable” to “funded” for a Lump Sum fee of $5,000. ... Under separate covers we will be preparing a scope, budget and schedule for the actual design work for the Headwords [sic] and associated improvements (including the Design Development Report for the overall plant) and also will submit a grant application to Rural Development to fund the development of a capital master plan for the water and wastewater systems. Additional engineering fees will only be contracted once funding has been committed.

Brent Bridges, a senior vice president with W&C testified that the $5,000, as stated in the proposal, was to be paid for the documents to support the funding application for stimulus money. The second part of the proposal agreed to in the May contract was not covered by the $5,000 and involved supplying the design engineering necessary to apply for funding.

The senior project manager at W&C testified that pursuant to the second part of the May contract, there was a meeting with the mayor and two city council members and they authorized the second project of the May contract and authorized payment of $210,000 for that work.

At this meeting with the mayor and council members, W&C was told to proceed with the work necessary to continue the application process. This work included hiring surveyors, hiring geo-technical core drillers, getting bids for the work, and completing the design plans.

After the mayor signed the authorization to proceed, and as the work progressed, the project engineer was asked to attend a city council meeting and update the mayor and city council on the work that W&C was doing. The engineer stated that he attended the meeting and described the work that was being done and the status of the permits, applications, designs, specifications and reports. He testified that the City owed W&C approximately $203,000 for this work.

The mayor who signed the June proposal testified that it was his understanding that the full amount contracted for was the $5,000 and any additional engineering fees would be contracted for once the funding was committed. The mayor said that he signed the proposal for the additional work but did not date it because he could not [770]*770obligate the City by himself and it would have to be voted on by the council and reviewed by the city attorney.

The mayor testified as to the benefit to the City if improvements were made to the wastewater treatment plant, stating that improvements to the headworks would have averted the possibility of substantial fines from the EPD. The mayor acknowledged that he knew W&C was doing engineering work for the City in order to obtain the stimulus money, and agreed that there was no question that W&C was going to continue doing work for the City toward applying for the stimulus money. The mayor said that he knew that deadlines existed and knew that the project must be “shovel-ready by November 1[, 2009] .”2

The mayor acknowledged that there was a council meeting attended by W&C representatives in September at which the mayor and council were told that W&C was going to have to do “engineering” for the project. The mayor said that he knew at that time that “there was a good deal more to be done.” In addition, a tape was played for the jury of this September meeting of the city council at which W&C told the council about the work that had been completed and the work that still needed to be done in order to file the application for funds.

The jury returned a verdict in favor of W&C in the amount of $203,000. The City now appeals.

Where a jury returns a verdict and it has the approval of the trial judge, the same must be affirmed on appeal if there is any evidence to support it as the jurors are the sole and exclusive judges of the weight and credit given the evidence____The appellate court must construe the evidence with every inference and presumption in favor of upholding the verdict, and after judgment, the evidence must be construed to uphold the verdict even where the evidence is in conflict. As long as there is some evidence to support the verdict, the denial of defendant’s motions for new trial and [j.n.o.v.] will not be disturbed.

(Punctuation omitted.) Lofty v. Fuller, 223 Ga. App. 95, 97 (477 SE2d 30) (1996).

1. The City contends that the trial court erred in allowing the claim for quantum meruit to go to the jury. First, we note that the verdict form does not show whether the award was made on the [771]*771breach of contract claim or whether it was made on the basis of the quantum meruit claim. The City did not request special findings and did not object to the verdict form. This Court will not speculate as to the findings of fact supporting the verdict. All Risk Ins. Agency v. Southern Bell Tel. &c. Co., 182 Ga. App. 190, 192 (355 SE2d 465) (1987).

Further, we reject the City’s argument that H. G. Brown Family, L.R v. City of Villa Rica, 278 Ga. 819 (607 SE2d 883) (2005), precludes claims of quantum meruit and unjust enrichment where an alleged contract between the municipality and a contractor is ultra vires and void. Although the trial court held that the June proposal was not a valid contract because it was not approved by a quorum of the city council, the City overlooks the fact that there was evidence submitted to the jury that the work was done in accordance with the May contract, which was a valid contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Renee Group, Inc. v. City of Atlanta
Court of Appeals of Georgia, 2021
City of Baldwin, Georgia v. Woodard & Curran
Court of Appeals of Georgia, 2013
City of Baldwin v. Woodard & Curran, Inc.
748 S.E.2d 141 (Court of Appeals of Georgia, 2013)
Velma Veasley v. Monitronics International, Inc.
Court of Appeals of Georgia, 2013
Monitronics International, Inc. v. Veasley
746 S.E.2d 793 (Court of Appeals of Georgia, 2013)
City of Baldwin v. Woodard & Curran, Inc.
743 S.E.2d 381 (Supreme Court of Georgia, 2013)
Theodore Rowe v. Law Offices of Ben C. Brodhead
Court of Appeals of Georgia, 2012
Rowe v. Law Offices of Ben C. Brodhead, P.C.
735 S.E.2d 39 (Court of Appeals of Georgia, 2012)
David Koch v. Fred Baruchman & Associates
Court of Appeals of Georgia, 2012
Koch v. Fred Baruchman & Associates, P.C.
733 S.E.2d 781 (Court of Appeals of Georgia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
730 S.E.2d 486, 316 Ga. App. 768, 2012 Fulton County D. Rep. 2363, 2012 Ga. App. LEXIS 652, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-baldwin-v-woodard-curran-inc-gactapp-2012.