City of Alvin and Texas-New Mexico Power Company v. Public Utility Commission

CourtCourt of Appeals of Texas
DecidedAugust 25, 1993
Docket03-92-00459-CV
StatusPublished

This text of City of Alvin and Texas-New Mexico Power Company v. Public Utility Commission (City of Alvin and Texas-New Mexico Power Company v. Public Utility Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Alvin and Texas-New Mexico Power Company v. Public Utility Commission, (Tex. Ct. App. 1993).

Opinion

alvin
IN THE COURT OF APPEALS, THIRD DISTRICT OF TEXAS,


AT AUSTIN




NO. 3-92-459-CV


CITY OF ALVIN, ET AL., & TEXAS-NEW MEXICO POWER COMPANY,


APPELLANTS



vs.


PUBLIC UTILITY COMMISSION OF TEXAS,


APPELLEE





FROM THE DISTRICT COURT OF TRAVIS COUNTY, 53RD JUDICIAL DISTRICT


NO. 91-7744, HONORABLE W. JEANNE MEURER, JUDGE PRESIDING




Texas-New Mexico Power Company ("TNP") filed a statement of intent to change rates with the Public Utility Commission of Texas (the "Commission"). See Public Utility Regulatory Act ("PURA"), Tex. Rev. Civ. Stat. Ann. art. 1446c, § 43 (West Supp. 1993). TNP requested a rate increase to recover the costs associated with its generating facility known as TNP One Unit 1. At that time TNP had also begun construction of a second facility, known as TNP One Unit 2. The Commission issued its final order in Docket 9491, which granted in part TNP's requested rate increase. The Commission found that TNP's decision to construct Unit 1 was prudent but denied recovery of some costs associated with its construction. The Commission also found that TNP's decision to construct Unit 2 was imprudent.



TNP and certain cities ("the Cities") (1) sought judicial review of the order in district court under section 19 of the Administrative Procedure and Texas Register Act ("APTRA"), Tex. Rev. Civ. Stat. Ann. art. 6252-13a (West Supp. 1993). The district court affirmed the Commission's order in the main, but it reversed portions of the order disallowing certain costs TNP incurred on Unit 1 and remanded the docket to the Commission for further proceedings regarding these costs. The Cities and TNP appeal the district court's judgment insofar as it affirms the Commission's order. The Commission and the Cities appeal the district court's reversal of portions of the Commission's order. Overall, TNP brings thirteen points of error, the Cities bring four points, and the Commission brings one point.



AUTHORITY TO CONSIDER UNIT 2'S PRUDENCE

TNP's second point of error asserts that the Commission was without statutory authority to decide whether TNP had proven the prudence of its decision to construct Unit 2 because TNP did not request rate-base treatment or decisional-prudence findings as to Unit 2. The parties dispute whether TNP in fact made such a request.

The Commission first asserts that TNP initially pleaded this issue in its petition to change rates filed with the Commission. Paragraphs X and XI of the petition sought only recovery of the costs associated with Unit 1. The Commission, however, notes that paragraph V incorporated all the testimony and data that TNP filed along with its petition. The Commission then refers to several instances where this testimony and data discussed Unit 2's prudence. TNP argues that the Commission is pointing unfairly to isolated references in an expansive collection of documents and contends that any evidence introduced about the prudence of constructing Unit 2 concerned common costs of Units 1 and 2. Although the Commission disputes this contention, the record indicates that TNP introduced evidence about Unit 2 to bolster its proof of the prudence of Unit 1 costs. The two units were part of a plan that originally envisioned the construction of four similar units by TNP; therefore, TNP was particularly interested in convincing the Commission that the first of these plants, Unit 1, was constructed prudently.

TNP points out that, although it gave no notice to the public that the prudence of the decision to begin Unit 2's construction would be an issue in this proceeding, the Commission concluded that TNP's notice adequately satisfied the requirements in section 43 of PURA and the Commission's own rule, 16 Tex. Admin. Code § 21.22 (1988). TNP further notes that, had the Commission considered the Unit 2 prudence issue, section 13(b)(4) of APTRA required it to provide TNP notice of such consideration ("Notice must include . . . a short and plain statement of the matters asserted."). The Commission did not provide TNP such notice. (2)

Viewing the record as a whole, we find that TNP's initial petition did not ask the Commission to decide whether the decision to construct Unit 2 was prudent. However, the Commission also contends that this issue was tried by consent when TNP failed to request in its rate-filing package that the Commission should not make findings on Unit 2 or to object specifically object when the issue was raised during cross-examination of witnesses at the agency hearing. The Cities further cite portions of TNP's filed package, its post-hearing brief, and its objections to the examiners' report supporting the prudence of the decision to construct Unit 2.

As discussed above, the record shows that TNP introduced such evidence to bolster its proof of the prudence of Unit 1 costs. The examiners' report also indicates which issues TNP actually presented in this proceeding. The examiners were concerned that TNP's Board of Directors had decided initially that Unit 2 would be too costly to construct. At a later board meeting, the board members studied several documents, including a life cycle analysis and a financial analysis, and subsequently decided to proceed with construction. The examiners were dismayed by "the failure of TNP to place such critical documents into the record." The report concludes:



Because the revised financial forecasts, the final Sargent & Lundy report, the life cycle analysis performed for Unit 2, and the summaries presented to the Board of Directors were not offered by TNP and are not in the record in this proceeding, this Commission is unable independently to assess the prudence of TNP's decision to release Unit 2 for construction.



(Emphasis added). Commissioner Marta Greytok, who dissented from the Commission's order on this issue, stated that a complete record was necessary before the Commission decided whether TNP had met its burden of proof. TNP's failure to introduce critical evidence in its possession indicates that TNP never intended for the issue to be determined in this agency proceeding.

TNP's objections to the examiners' report complained that Unit 2's prudence was not an issue in the proceeding. TNP subsequently repeated this argument when it filed a motion to clarify or limit the issues involved in the proceeding. Finally, TNP offered to withdraw this issue from consideration, an option TNP retained until the Commission issued its final order. See 16 Tex. Admin. Code § 21.82(b) (1988). Examining the record as a whole, we find that the issue was not tried by consent. Accordingly, we hold that the Commission lacked the authority to decide the prudence of constructing Unit 2. We sustain TNP's second point of error. We need not reach TNP's third point, which complains that the Commission's findings on the prudence of constructing Unit 2 are not supported by substantial evidence and are arbitrary and capricious.



PRUDENCE REVIEW

In TNP's first point of error, it asserts that the Commission incorrectly conducted a review of the "prudence" of TNP's decisions to incur capital expenses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alliance for Aff. Energy v. New Orleans
578 So. 2d 949 (Louisiana Court of Appeal, 1991)
Texas-New Mexico Power Co. v. Texas Industrial Energy Consumers
806 S.W.2d 230 (Texas Supreme Court, 1991)
Trenholm v. Ratcliff
646 S.W.2d 927 (Texas Supreme Court, 1983)
Sexton v. Mount Olivet Cemetery Ass'n
720 S.W.2d 129 (Court of Appeals of Texas, 1986)
Cities of Abilene v. Public Utility Commission
854 S.W.2d 932 (Court of Appeals of Texas, 1993)
Public Utility Commission v. Houston Lighting & Power Co.
748 S.W.2d 439 (Texas Supreme Court, 1987)
City of Lubbock v. South Plains Electric Cooperative, Inc.
593 S.W.2d 138 (Court of Appeals of Texas, 1979)
City of League City v. Texas Water Commission
777 S.W.2d 802 (Court of Appeals of Texas, 1989)
Suburban Utility Corp. v. Public Utility Commission
652 S.W.2d 358 (Texas Supreme Court, 1983)
Southern Union Gas Co. v. Railroad Commission
692 S.W.2d 137 (Court of Appeals of Texas, 1985)
Central Maine Power Co. v. Public Utilities Commission
109 A.2d 512 (Supreme Judicial Court of Maine, 1954)
Public Utility Com'n of Texas v. Gte-Sw
833 S.W.2d 153 (Court of Appeals of Texas, 1992)
Consumers Water, Inc. v. Public Utility Commission
774 S.W.2d 719 (Court of Appeals of Texas, 1989)
City of El Paso v. Public Utility Commission of Texas
839 S.W.2d 895 (Court of Appeals of Texas, 1992)
Pedernales Electric Cooperative, Inc. v. Public Utility Commission
809 S.W.2d 332 (Court of Appeals of Texas, 1991)
Southern Union Gas Co. v. Railroad Com'n of Texas
701 S.W.2d 277 (Court of Appeals of Texas, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
City of Alvin and Texas-New Mexico Power Company v. Public Utility Commission, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-alvin-and-texas-new-mexico-power-company-v-texapp-1993.