Citizens of the State of Florida v. Art Graham, etc.

213 So. 3d 703, 42 Fla. L. Weekly Supp. 312, 2017 WL 1021849, 2017 Fla. LEXIS 585
CourtSupreme Court of Florida
DecidedMarch 16, 2017
DocketSC16-141
StatusPublished
Cited by3 cases

This text of 213 So. 3d 703 (Citizens of the State of Florida v. Art Graham, etc.) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Citizens of the State of Florida v. Art Graham, etc., 213 So. 3d 703, 42 Fla. L. Weekly Supp. 312, 2017 WL 1021849, 2017 Fla. LEXIS 585 (Fla. 2017).

Opinions

LEWIS, J.

This case is before the Court on appeal from a decision of the Florida Public Service Commission relating to the rates or service of a public utility providing electric service. We have jurisdiction. See art. V, § 3(b)(2), Fla. Const.

FACTUAL AND PROCEDURAL BACKGROUND

Florida Public Utilities Company (FPUC) is an investor-owned electric utility located in Fernandina Beach, Florida. FPUC does not generate its own electricity, but instead relies solely on wholesale purchase power agreements with other electric utilities.

Our discussion begins on August 29, 2014, when FPUC entered into a settlement agreement with the Office of Public Counsel (OPC) in resolution of its then pending petition for an increase in base rates." In re Application for Rate Increase by Fla. Pub. Utils. Co. (Settlement Agreement Order), Order No. PSC-14-0517-SEI, at 1, 2014 WL 4960917 (Fla. P.S.C. Sept. 29, 2014), Section I of the settlement agreement prohibits FPUC from increasing its base rates thereafter until at least December 31, 2016.1 Further coloring that [706]*706prohibition, Section VI of the settlement agreement, entitled “Other Cost Recovery,” specifically delineated what costs FPUC might seek recovery of through other mechanisms, such as the Commission’s fuel clause proceedings:

Nothing in this agreement shall preclude the Company from requesting the Commission to approve the recovery of costs that are:
(a) of a type which traditionally and historically would be, have been, or are presently recovered through cost recovery clauses or surcharges, or (b) incremental costs not currently recovered in base rates which the Legislature or Commission determines are clause recoverable subsequent to the approval of this settlement. Except as provided in this Agreement, it is the intent of the Parties in this Paragraph VI that FPUC not be allowed to recover through cost recovery clauses increases in the magnitude of costs, incurred after implementation of the new base rates, of types or categories (including but not limited to, for example, investment in and maintenance of transmission assets) that have been traditionally and historically recovered through FPUC’s base rates.

In re Application for Rate Increase by Fla. Pub. Utils. Co., Docket No. 140025-EI, Document No. 04856-14 (Aug. 29, 2014) (emphasis added). On September 29, 2014, this settlement agreement was unanimously approved by the Commission. See generally Settlement Agreement Order, No. PSC-14-0517-S-EI, at 1, 2014 WL 4960917 (“Having reviewed the Settlement and the pleadings, and heard argument of counsel, we find that the Settlement is in the best interests of FPUC’s ratepayers and hereby approve it.”). Further, the Commission’s Order incorporated by reference the entire settlement agreement and thereby adopted its terms as its policy. Id at 3.

About one year later, on September 1, 2015, FPUC petitioned the Commission for approval of its fuel adjustment and purchased power cost recovery factors for the period of January 2016 through December 2016. In pertinent part, and contrary to the settlement agreement, FPUC’s petition sought to recover costs associated with constructing a new interconnection with Florida Power & Light Company (FPL). Specifically, FPUC sought to initially recover $107,333 in depreciation expense, taxes other than income taxes, and a return on investment associated with the $3.5 million dollar cost of its interconnection project. According to FPUC’s petition, the FPL interconnection “will result in [FPUC] being better situated in terms of negotiating a new power purchase agreement for [its] Northeast Division to follow [its] current agreement.” Indeed, at the time, FPUC had a purchased power agreement with which it purchased power exclusively from Jacksonville Electric Authority (JEA) to serve its Northeast Division, which encompasses its customers on Amelia Island. FPUC’s agreement with JEA is set to expire on December 31, 2017. Thus, with construction of the FPL interconnection, FPUC asserts that it will increase its potential providers from one to two, and presumably give it a basis to negotiate a [707]*707more favorable price for its purchased power, the savings from which will be passed on to its customers in the form of lower rates.

Despite the stated altruistic intentions of this proposed project, the OPC objected to FPUC’s petition. In relevant part, the OPC asserted that the costs associated with the FPL interconnection were among the types of costs barred by the provisions of the settlement agreement quoted above. Likewise, the Commission’s staff prepared a memorandum in which it recommended that FPUC’s petition be denied due to the settlement agreement’s provisions. During a subsequent hearing, a commissioner questioned staff about the settlement agreement’s effect and suggested it prohibited FPUC’s request. Nevertheless, the Commission ultimately voted to reject the staffs recommendation and approved the recovery of the entire FPL interconnection costs, contrary to the terms of the settlement agreement. The dissent simply ignores this information and materials submitted by the Commission’s own staff and OPC.

Despite the prior objections and discussions concerning the settlement agreement’s application to the FPL interconnection, such consideration and analysis were conspicuously missing from the Commission’s order with regard to the FPL interconnection costs. In re Fuel & Purchased Power Cost Recovery Clause with Generating Performance Incentive Factor (Order Below), No. PSC-15-0586-F0F-EI, at 11-15, 2015 WL 9450334 (Fla. P.S.C. Dec. 23, 2015). Specifically, the order only addressed and analyzed the settlement agreement’s effect on the entirely separate issue of FPUC’s ability to recover legal and consulting fees associated with the project, not the entire construction costs. Id. at 13-14. This factor is also ignored by the dissent. Instead, the only analysis offered by the Commission that related to construction of the transmission interconnection centered on the reliability enhancements and the potential savings to customers:

All parties agree that the proposed interconnection with FPL will result in improved system reliability for Amelia Island. Nor is there disagreement that interconnection with FPL will offer wholesale power purchase options not currently available to FPUC when its wholesale power agreement with JEA expires in December 2016.[2] The disagreement rests with the OPC’s conclusion that [Commission] Order No. 14546 prohibits cost recovery until cost savings are received by ratepayers. We do not read Order No. 14546 that restrictively.
Therefore, we find that the interconnection with FPL and the consulting and legal fees associated with the development and enactment of projects designed to reduce fuel rates to FPUC’s customers, costs associated with the development and negotiations of power supply contracts, and costs to consultants engaged in performing due diligence in review and analysis of the Renewable Energy Agreement between FPUC and Rayonier shall be recovered through the fuel cost recovery clause.

Id. at 15.

Left without an explanation as to why FPUC’s petition was approved over its objections without consideration and application of the terms of the settlement agreement, the OPC has now appealed the Commission’s order. This review follows.

[708]*708ANALYSIS

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
213 So. 3d 703, 42 Fla. L. Weekly Supp. 312, 2017 WL 1021849, 2017 Fla. LEXIS 585, Counsel Stack Legal Research, https://law.counselstack.com/opinion/citizens-of-the-state-of-florida-v-art-graham-etc-fla-2017.