Citizens for a Better Henderson v. Hodel

768 F.2d 1051, 15 Envtl. L. Rep. (Envtl. Law Inst.) 20
Court of Appeals for the Ninth Circuit·Decided August 13, 1985·No. Nos. 84-2149, 84-2177·Published·Cited by 27 cases

Opinion

GOODWIN, Circuit Judge.

Citizens for a Better Henderson, the City of Henderson and other plaintiffs (Henderson) appeal from dismissal of their action for injunctive and declaratory relief. Henderson sought to enjoin construction of a direct-current transmission line on multistory towers within the city limits. The case turns on the sufficiency of an environmental impact statement. We affirm.

The Intermountain Power Project (the Project) involves the construction of an electricity generating facility near Hanks-ville, Utah, and a transmission system to carry power from the generator to users in southern California and Utah. The part of the Project at issue in this case is a 490-mile direct-current transmission line from Utah to a converter station outside Los Angeles. Following the several-year preparation of the Project Environmental Impact Statement, which covered construction of both the generator and the transmission system, in December 1979 the Secretary of the Interior approved the transmission route challenged in this action. Most of the route crosses federal lands, over which the Bureau of Land Management has granted a right-of-way. Where the line crosses nonfederal property, the Project has generally been able to secure the appropriate routing permission from local authorities.

A small portion of the route goes through Henderson, Nevada. The original [1054]*1054path approved by the Secretary crossed nonfederal property within the municipal boundaries and lay approximately 130 feet east of an existing transmission line. In 1982, when Henderson refused to grant a conditional use permit to allow construction of the line on nonfederal land, the Project moved the line approximately 260 feet west, to a path which was still within the federally approved route but which, according to Bureau of Land Management records, was entirely over federal land.

On May 3, 1983, Henderson filed a complaint in federal district court for the District of Nevada against the Project, the Los Angeles Department of Water and Power (which is acting as the Project Manager) and the Secretary of the Interior. Henderson asked for injunctive and declaratory relief for alleged violations of the National Environmental Policy Act (NEPA), 42 U.S.C. § 4321 et seq. and the Federal Land Policy and Management Act, 43 U.S.C. § 1701 et seq. In September and October 1983, Henderson filed motions for a preliminary injunction and a temporary restraining order. Both were denied. After a two-month trial in 1984, Henderson’s action was dismissed by a second judge.

Henderson urges four grounds for reversal. First, Henderson argues that the new route of the transmission line crosses non-federal land, making it possible for the city to block construction for which no conditional use permit has been granted. Second, Henderson argues that even if the new route is entirely over federal land, the Project is required by the terms of the Bureau of Land Management right-of-way to comply with local land use requirements. Third, Henderson contends that the federal government has violated the Federal Land Policy and Management Act by informally designating the route through the City of Henderson as a corridor for power transmission lines. Henderson’s final argument is that the Project Environmental Impact Statement did not adequately address alternative routes for the transmission line, or the potential health hazard of a right-of-way through Henderson.

I. The Transmission Line Crosses Only Federal Property.

Henderson argues that the district court erred in concluding that within Henderson city limits the transmission line crosses only federal property. Henderson contends that the line crosses a small parcel of nonfederal land (“Section 27”) and that private property is subject not to the federal right-of-way but to local land use controls. While the district court memorandum decision did not include a specific finding of federal ownership of the entire Henderson route, such a finding is implicit in its consideration of the preemption problem. We must affirm the district court determination on this fact question unless it is clearly erroneous. Fed.R.Civ.P. § 52(a); United States v. McConney, 728 F.2d 1195, 1201 (9th Cir.) (en banc), cert. denied, — U.S. -, 105 S.Ct. 101, 83 L.Ed.2d 46 (1984).

The Project’s evidence consisted of an affidavit by a Bureau of Land Management official about Bureau records, and a Bureau land status map. That evidence showed that Section 27 had been under federal jurisdiction, either continuously or since passage in 1976 of the Federal Land Policy and Management Act. Section 314 of that Act erased unpatented mining claims not renewed by 1979. 43 U.S.C. §§ 1744(a) and (c). On appeal the Project asserts that any patented mining claim to Section 27 would have resulted in permanent divestment of the government’s title, and would have been recorded by the Bureau of Land Management. See 43 U.S.C. § 6.

Henderson’s evidence, which consisted of testimony by the city’s Director of Planning about conclusions he drew from county tax records, but not the records themselves, tended to show that Section 27 has also been for some years on the County assessor’s tax rolls. However, Henderson did not offer proof of private title in the land, or demonstrate that a listing on county tax rolls was necessarily inconsistent with federal ownership.

[1055]*1055It was the task of the trial judge and not this court to examine the Project’s documentary evidence and weigh the credibility of the Bureau of Land Management affidavit against unsupported testimony of Henderson’s witness. The evidence, although somewhat sparse on both sides, convinces us that the indicia of federal ownership offered by the Project were less ambiguous than the indicia of private ownership offered by Henderson, and that the judge’s findings in favor of the Project on this question were not clearly erroneous.

II. Local Law is Preempted.

Henderson next argues, in the alternative to its claim that Section 27 is privately owned, that even if the entire route is federally owned, the Project is nevertheless subject to Henderson’s land use requirements, for two reasons. The first reason is that the Project is a private, not a federal, venture. The second reason is that the terms of the right-of-way mandate federal acquiescence with local restrictions. Neither argument withstands scrutiny.

We need not decide whether the Project is a federal undertaking. Even assuming it is not federal, there is no reason that the Secretary cannot authorize certain private Project activities, for example, construction of a transmission line on federal land. This court has supported the right of the federal government to exercise such authority, whether the authorized party is public or private, free of any regulatory interference by local agencies. See Ventura County v. Gulf Oil Corp., 601 F.2d 1080

Free access — add to your briefcase to read the full text and ask questions with AI

Citizens for a Better Henderson v. Hodel, 768 F.2d 1051, 15 Envtl. L. Rep. (Envtl. Law Inst.) 20 (9th Cir. 1985).

768 F.2d 1051 (Citizens for a Better Henderson v. Hodel) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

SOUTHEAST ALASKA CONSERV. v. Fed. Highway Admin.
649 F.3d 1050 (Ninth Circuit, 2011)
Center for Biological Diversity v. U.S. Bureau of Land Management
746 F. Supp. 2d 1055 (N.D. California, 2009)
Kootenai Tribe of Idaho v. Veneman
142 F. Supp. 2d 1231 (D. Idaho, 2001)
Surfrider Foundation v. Dalton
989 F. Supp. 1309 (S.D. California, 1998)
Idaho Conservation League v. John Mumma
956 F.2d 1508 (Ninth Circuit, 1992)
Havasupai Tribe v. United States
752 F. Supp. 1471 (D. Arizona, 1990)
Fallini v. Hodel
725 F. Supp. 1113 (D. Nevada, 1989)
Town of Beverly Shores v. Lujan
736 F. Supp. 934 (N.D. Indiana, 1989)
Hirt v. Hodel
840 F.2d 1432 (First Circuit, 1988)
NORTHWEST COAL. FOR ALTERN. TO PESTICIDES v. Lyng
673 F. Supp. 1019 (D. Oregon, 1987)