Cincinnati Ins. Co. v. LOMC, L.L.C.

2022 Ohio 930
Ohio Court of Appeals·Decided March 21, 2022·No. 21 JE 0012·Published·Cited by 1 cases

Opinion

IN THE COURT OF APPEALS OF OHIO SEVENTH APPELLATE DISTRICT JEFFERSON COUNTY

THE CINCINNATI INSURANCE COMPANY, Plaintiff-Appellant,

v.

LOMC LLC, et al.,

Defendants-Appellees.

OPINION AND JUDGMENT ENTRY Case No. 21 JE 0012

Civil Appeal from the

Court of Common Pleas of Jefferson County, Ohio Case No. 20-CV-333

BEFORE:

Cheryl L. Waite, Gene Donofrio, David A. D’Apolito, Judges.

JUDGMENT:

Affirmed.

Atty. John G. Farnan and Atty. Joshua M. Miklowski, Weston Hurd LLP, The AECOM Building, 1300 East 9th Street, Suite 1400, Cleveland, Ohio 44114, for Plaintiff-Appellant

Atty. Kristina S. Dahmann, Ice Miller LLP, 250 West Street, Columbus, Ohio 43215 for Defendants-Appellees.

Dated: March 21, 2022

WAITE, J.

{¶1} Appellant, The Cincinnati Insurance Company (“CIC”), appeals from a Jefferson County Common Pleas Court judgment entry dismissing its complaint against Appellee, Garrett, LLC (“Garrett”). Based on the following, the judgment of the trial court is affirmed.

Factual and Procedural History {¶2} This is a declaratory judgment action filed by CIC, an Ohio-based insurance company, seeking a determination regarding its coverage obligations to Garrett, a Kentucky-based limited liability company. The dispute centers around a former foundry located in Kendallville, Indiana (“the foundry”). A brief description of the project is necessary to address the claims alleged by the parties. The foundry was previously owned and operated by Dalton, Inc. While in operation, Dalton had obtained approval from the Indiana Department of Environmental Management (“Dept.”) to discard used foundry sands in an area west of the main foundry building creating a mound of material referred to by the parties as a monofill. Pursuant to its agreement with the Dept., Dalton capped the monofill with layers of clay, soil and vegetation, respectively. At the time the monofill was capped, the sand in the monofill had not been processed to recover any recyclable metals that it may have contained.

{¶3} After the foundry ceased operations, the property underwent an environmental assessment by the Dept. As part of the assessment, the Dept. approved Garrett for a scrap metals reclamation plan (“reclamation plan”). The reclamation plan provided that Garrett would hire a contractor to remove the cap from the monofill, remove

the foundry sands inside, and then sift through the sands for recyclable metals. The sifted sand would then be returned to the monofill and the cap would be replaced. The plan was approved by the Dept. on March 19, 2015.

{¶4} Garrett initially hired Industrial Steel Products, Inc. as contractor for the project. Shortly after beginning the project, work was halted and Industrial Steel went out of business. On October 20, 2016, Garrett hired LOMC, a Pennsylvania-based limited liability company, as contractor to complete the project. LOMC had locations in both Pennsylvania and Mingo Junction, Ohio, and was registered to work in Indiana. Under the terms of the contract, LOMC agreed to sift through the foundry site and remove the metals in accordance with the terms of the reclamation plan. LOMC would sell the metals and provide Garrett with a 15% royalty of the net sales. The contract required LOMC to provide $1 million of per occurrence general liability insurance, with Garrett listed as an additional named insured on the policy. The contract also specified that LOMC would indemnify and hold Garrett harmless. According to the record, LOMC informed their commercial general liability insurer, CIC, of the insurance requirements of its contract with Garrett. An agent for CIC, Assured Partners of Ohio, LLC, d/b/a Dawson Insurance Agency (“Dawson”), an Ohio limited liability company, informed LOMC that Garrett was a named insured on the policy and that the policy had the necessary liability amounts as well as an indemnification provision. LOMC presented a certificate of liability insurance with CIC, purchased through the Dawson agency, with Garrett listed as a named insured. A copy of the certificate has been made a part of the record.

{¶5} The work performed by Garrett was conducted over a time period which spanned two insurance policy periods. The first policy term was effective May 29, 2014

to May 29, 2017. The second policy provided the same coverage, with Garrett listed as a named insured, and was effective May 29, 2017 to May 29, 2020.

{¶6} On June 6, 2017, Garrett submitted a proposed addendum to the reclamation plan regarding modifications to the recapping of the monofill and cleanup of the site. On October 10, 2017, the Dept. approved the modifications to the reclamation plan and LOMC began working at the site. On December 21, 2017, the Dept. sent a violation letter to Garrett informing it that an inspection of the site had been performed on November 14, 2017, after LOMC had begun working. The letter stated that, after being sifted, the sand had to be returned to the monofill, which had not been performed appropriately. Garrett responded to the Dept. on January 21, 2018, informing them that the issue would be addressed. On March 6, 2018, the Dept. sent Garrett a second violation letter which listed three violations at the site: (1) exceeding the limited area in which reclamation activities were approved to take place; (2) disturbing the outer side slopes of the monofill; and (3) failing to control leaching and erosion on the site. Garrett responded on April 2, 2018, advising that LOMC had ceased collecting all the sand from the monofill and that, after sifting, the sand would be returned. Garrett informed the Dept. that the project would be completed a few weeks later. Garrett sent a second letter to the Dept. on April 27, 2018, notifying the Dept. that it had addressed the leaching and erosion issues which it claimed had been caused by LOMC’s negligence.

{¶7} On May 4, 2018, the Dept. sent a third violation letter to Garrett, stating that another inspection had been performed on April 11, 2018 and several additional violations had been found. Garrett informed the Dept. on May 7, 2018, that LOMC had been given a copy of the violation letter and was ordered to rectify the violations. On October 25,

2018, the Dept. issued a Notice of Violation and Proposed Agreed Order to Garrett that addressed all of the existing violations and notifying Garrett that failure to remedy the violations would result in escalated enforcement action, including a $25,000 per day penalty for each separate violation. Garrett began undertaking efforts to mitigate its damages at the site, but the Dept. required Garrett to investigate and remediate the environmental damage to the site, causing Garrett to incur additional environmental response costs.

{¶8} On August 6, 2020, counsel for Garrett sent a demand letter to LOMC at its Mingo Junction, Ohio location, demanding that LOMC and its insurers defend and indemnify Garrett for any alleged environmental liability or property damage associated with LOMC’s work at the foundry site. In the letter, Garrett alleged that LOMC had negligently handled the processing of the metals and caused waste to spill into ditches around the site and requested a response by August 30, 2020. A copy of the letter is included in the record. On August 11, 2020, Garrett sent a letter to CIC at its Indiana office, requesting that LOMC and CIC provide defense and indemnification to Garrett. Garrett sent a copy of the same letter, by email to CIC headquarters in Ohio. The letter requested a response by August 31, 2020.

Free access — add to your briefcase to read the full text and ask questions with AI

Cincinnati Ins. Co. v. LOMC, L.L.C., 2022 Ohio 930 (Ohio Ct. App. 2022).

2022 Ohio 930 (Cincinnati Ins. Co. v. LOMC, L.L.C.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Cincinnati Ins. Co. v. LOMC, L.L.C.
2022 Ohio 930 (Ohio Court of Appeals, 2022)