Cianbro Corporation v. Mueser Rutledge Consulting Engineers PLLC

CourtDistrict Court, D. Massachusetts
DecidedDecember 9, 2024
Docket1:24-cv-10535
StatusUnknown

This text of Cianbro Corporation v. Mueser Rutledge Consulting Engineers PLLC (Cianbro Corporation v. Mueser Rutledge Consulting Engineers PLLC) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cianbro Corporation v. Mueser Rutledge Consulting Engineers PLLC, (D. Mass. 2024).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF MASSACHUSETTS _________________________________________ ) CIANBRO CORPORATION, ) ) Plaintiff, ) ) v. ) Civil Action No. 24-cv-10535 ) ) MUESER RUTLEDGE CONSULTING ) ENGINEERS PLLC and LAMSON ) ENGINEERING CORPORATION, ) ) Defendants. ) _________________________________________ )

MEMORANDUM AND ORDER

CASPER, J. December 9, 2024 I. Introduction Plaintiff Cianbro Corporation (“Cianbro”) has filed this lawsuit against Defendants Mueser Rutledge Consulting Engineers, PLLC (“MRCE”) and Lamson Engineering Corporation (“Lamson”) (collectively, “Defendants”) alleging breach of contract (Counts I and III) and equitable indemnification (Counts II and IV). D. 1. Both MRCE and Lamson now have moved to dismiss the complaint pursuant to Fed. R. Civ. P. 12(b)(6). D. 10; D. 19. For the reasons stated below, the Court ALLOWS the motions to dismiss as to the equitable indemnification claims, but DENIES them as to the breach of contract claims. D. 10; D. 19. II. Standard of Review On a motion to dismiss for failure to state a claim upon which relief can be granted pursuant to Fed. R. Civ. P. 12(b)(6), the Court must determine if the facts alleged “plausibly narrate a claim for relief.” Schatz v. Republican State Leadership Comm., 669 F.3d 50, 55 (1st Cir. 2012) (citation omitted). Reading the complaint “as a whole,” the Court must conduct a two-step, context-specific inquiry. García-Catalán v. United States, 734 F.3d 100, 103 (1st Cir. 2013). First, the Court must perform a close reading of the claim to distinguish the factual allegations from the conclusory legal allegations contained therein. Id. Factual allegations must be accepted as true, while conclusory legal conclusions are not entitled credit. Id. Second, the Court must determine whether the factual

allegations present a “reasonable inference that the defendant is liable for the conduct alleged.” Haley v. City of Bos., 657 F.3d 39, 46 (1st Cir. 2011) (citation omitted). In sum, the complaint must provide sufficient factual allegations for the Court to find the claim “plausible on its face.” García-Catalán, 734 F.3d at 103 (citation omitted). III. Factual Background The following facts are drawn from Cianbro’s complaint, D. 1, and are accepted as true for the purposes of resolving Defendants’ motion to dismiss. A. The Project and the Contracts The Merrimack River Bridge in Haverhill, Massachusetts (the “Bridge”), was built more

than 125 years ago and carries commercial and passenger railroad traffic over the Merrimack River. D. 1 ¶ 11. The Bridge is supported by north and south abutments on either side and four in-water piers between the abutments. Id. In or about 2014, the Massachusetts Bay Transportation Authority (the “MBTA”) solicited requests for qualifications from design-builders for a project involving the rehabilitation and protection of the in-water parts of the Bridge while the Bridge remained in use for rail traffic. (“The Project”). Id. ¶¶ 12–13. The Project consisted of the design and construction of “scour countermeasures” to protect the Bridge’s abutments and piers from future scour (or erosion) events as well as some masonry repointing of these structures below the mean high-water mark. Id. ¶ 12. To submit their qualifications to the MBTA for the Project, Cianbro began working with a design team which was comprised of Louis Berger Group, Inc. (“LB”), now WSP USA, Inc. (“WSP”) after the latter purchased LB in 2018, see D. 19-1 at 17,1 and Defendants that served as WSP’s geotechnical subconsultants. D. 1 ¶ 14. After the MBTA issued a Request for Proposal (“RFP”) in or about April 14, 2014 to

formally solicit design-builders for the Project, Cianbro relied upon the design team, including the Defendants, to, inter alia, “determine how to meet the MBTA’s scour criteria, prepare a technical proposal for Cianbro to bid the Project, develop the design and construction documents based on that technical proposal, and provide construction phase services.” Id. ¶ 16. With the design and calculations prepared by Defendants, Cianbro submitted the technical proposal to MBTA on or about July 30, 2015. Id. ¶ 17. The technical proposal was based upon an “alternative technical concept” (the “ATC”) developed by the design team, in which MRCE was responsible for the grouting design and Lamson was responsible for the steel sheet pile design. Id. ¶ 18. The ATC called for “the installation of protective secant pile walls at the abutments and

a combination of sheet pile containment walls surrounding the piers and permeation grouting to create a grouted soil mass (“GSM”) within the footprint of those sheet pile walls.” Id. The ATC “was labeled ‘alternative’ because it differed from the approaches laid out in the MBTA’s base technical concept (the “BTC”) which were part of the Project’s RFP.” Id. Lamson and WSP entered into a written subcontract for professional services on June 30, 2015 and August 28, 2015. Id. ¶ 20. MRCE entered into a written subcontract with WSP on August 28, 2015. Id. ¶ 21.

1 Accordingly, the Court will refer to WSP throughout this Memorandum and Order in the place of LB. WSP and Cianbro entered into a written contract on August 28, 2015. Id. ¶ 22. WSP and Cianbro later entered into a modified agreement on December 7, 2015, which superseded and replaced the August 28, 2015 contract. Id. In or about September 2015, the MBTA awarded the Project to Cianbro. Id. ¶ 23. In or about October 21, 2015, Cianbro and the MBTA formally entered into a contract for the Project

“for a contract lump sum amount of $28,270,000 based on the ATC prepared with the geotechnical designs from Defendants.” Id. ¶ 24. B. The Alleged Design Issues As alleged, there were issues with the design that resulted in Cianbro incurring substantial additional costs “with the total approaching 60% of the lump-sum contract price in the MBTA contract.” Id. ¶ 25. Cianbro alleges that the first, major design error concerns the pier protection for which MRCE was responsible. Id. ¶¶ 18, 26. As alleged, given the known geotechnical conditions of the Project, reasonable geotechnical engineers would not have chosen this particular design,

“which relied on the effectiveness of permeation grout to create the required GSM and the adequacy of the sheet piles’ load-bearing capacity.” Id. ¶ 26. The second, major design error concerned the placement of sheet piles for which Lamson was responsible. Id. ¶ 18, 34. As alleged, the ATC sheet pile design called for driving sheets “so close to the piers that it caused the soil under the piers to densify and the piers, in particular Pier 3, to settle into sediment.” Id. ¶ 35. The MBTA advised Cianbro that its design proposal did not satisfy MBTA’s technical criteria and the MBTA would not accept the Project work as designed. Id. ¶ 29. As a result, WSP had to develop new designs for the piers to address Defendants’ alleged defective designs, id. ¶ 32, and Cianbro was forced to perform substantial extra, remedial work as well as absorb the cost of delay impacts. Id. ¶¶ 33, 36. After Cianbro completed this remedial work, the Project was complete and approved by the MBTA. Id. ¶ 36. C. Cianbro’s Settlement with WSP and Assignment of Claims

Cianbro asserted design claims against WSP, which in turn asserted claims against Defendants for, among other things, breach of the subcontracts, negligence and indemnification. Id. ¶ 38.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cepero-Rivera v. Fagundo
414 F.3d 124 (First Circuit, 2005)
Valerie Watterson v. Eileen Page
987 F.2d 1 (First Circuit, 1993)
Haley v. City of Boston
657 F.3d 39 (First Circuit, 2011)
Schatz v. Republican State Leadership Committee
669 F.3d 50 (First Circuit, 2012)
Hendrickson v. Sears
310 N.E.2d 131 (Massachusetts Supreme Judicial Court, 1974)
Fall River Hous. Auth. v. HV COLLINS CAPE COD LATH
604 N.E.2d 1310 (Massachusetts Supreme Judicial Court, 1992)
Riley v. Presnell
565 N.E.2d 780 (Massachusetts Supreme Judicial Court, 1991)
Anthony's Pier Four, Inc. v. Crandall Dry Dock Engineers, Inc.
489 N.E.2d 172 (Massachusetts Supreme Judicial Court, 1986)
Gomes v. Pan American Associates
549 N.E.2d 1134 (Massachusetts Supreme Judicial Court, 1990)
García-Catalán v. United States
734 F.3d 100 (First Circuit, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Cianbro Corporation v. Mueser Rutledge Consulting Engineers PLLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cianbro-corporation-v-mueser-rutledge-consulting-engineers-pllc-mad-2024.