Churchill v. Anderson

128 F. Supp. 425, 1955 U.S. Dist. LEXIS 3671
CourtDistrict Court, W.D. Kentucky
DecidedMarch 4, 1955
DocketCiv. No. 2405
StatusPublished
Cited by2 cases

This text of 128 F. Supp. 425 (Churchill v. Anderson) is published on Counsel Stack Legal Research, covering District Court, W.D. Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Churchill v. Anderson, 128 F. Supp. 425, 1955 U.S. Dist. LEXIS 3671 (W.D. Ky. 1955).

Opinion

SHELBOURNE, Chief Judge.

This action was filed July 9, 1952 by the plaintiff, B. F. Churchill, a resident of Tennessee, against the defendant Andy Anderson, a resident of Kentucky, to recover the alleged balance of an amount equal to ten percent of the construction cost of a six hundred seat theater, a drug store and three store buildings in the town of Hodgenville, Kentucky.

The period of construction under plaintiff’s supervision began on March 24, 1949 and ended January 9, 1950, on which latter date the building project was approximately ninety percent complete.

The complaint alleged that there was due plaintiff in excess of $3,540.33, after allowing defendant credit for $7,300 paid during the progress of the work.

The defendant by answer admitted contracting with plaintiff and agreeing to [426]*426pay him an amount equal to ten percent of the construction costs of the building but denied owing plaintiff any sum whatever.

By counterclaim, defendant alleged that the heating and air conditioning systems, the walls, roof and stage equipment were so negligently and carelessly constructed and installed that the roof and walls leaked, the furnace in the heating system blew up, the air conditioning system would not function properly and the curtain would require extensive repair because of its inefficient installation. He alleged that plaintiff took and carried away from the job a portable electric welder, the property of defendant, and of the value of $600. It was further claimed that by inefficient supervision of the work and paying wages to employees who were not required to work, the cost of the building was unnecessarily augmented. This latter claim was particularly leveled at the compensation of Charles (Chic) Churchill, a son of plaintiff, to whom there was paid $2,938.80 and that of Frank B. Churchill another son, to whom there was paid $979.35.

Defendant claimed that the sons were partners with their father and could be compensated only by plaintiff out of the ten percent which he said should go to B. F. Churchill and Sons the real contracting party plaintiff.

The allegations of the counterclaim were denied by reply and the case was tried to the Court without a jury.

The Court, from the stipulations of the parties and the evidence heard, makes the following—

Findings of Fact.

1. The plaintiff, B. F. Churchill, was at all times material to this action a resident of the State of Tennessee. The defendant, Andy Anderson, was at all such times a resident of the Western District of Kentucky.

2. The amount in dispute between the parties and in controversy exceeds $3,000 exclusive of interest and cost.

3. Shortly prior to March 24, 1949, as result of a short series of telephone and personal conversations, the plaintiff, B. F. Churchill and defendant, Andy Anderson made an agreement by which, in consideration of an amount to be paid plaintiff by defendant equal to ten percent of the total cost of construction, the former agreed to raze a building then standing on the proposed building site of a theater and four store buildings in ■the town of Hodgenville, Kentucky, and to design and supervise the building of the theater and store buildings.

4. It is the contention of the defendant that under the terms of the agreement the plaintiff was to be paid an amount equal to ten percent of the costs of “labor and materials used by plaintiff and his crew in such construction work as plaintiff and his crew should do under the direct supervision of the plaintiff”; that plaintiff was to receive no compensation based upon a percentage of cost of labor or materials under contracts entered into by defendant with workmen other than plaintiff’s.

5. The plaintiff’s contention is that he was to be paid an amount equal to ten percent of the cost of the building, i. e. cost of labor and material.

6. From the evidence heard and the exhibits filed the Court finds the total cost of construction $122,340.08 including following items and amounts, which the parties stipulate should be deducted for the purpose of finding plaintiff’s compensation:

B. F. Churchill drawing
account $6,800.00
Freight on air-conditioning parts 10.49
Seats 7,607.30
Sound Equipment 1,178.32
Poster Frames 715.74
Two Simplex Projects 450.00
Carpeting 2,585.23
Wheelbarrow 22.00
Weedburner 22.56
Air-conditioning 6,395.84
Total '$25,787.48

[427]*427Deducting the total of $25,787.48 from $122,340.08, leaves $96,552.60. To this last found sum there should be added the following amounts which are hereby held to be amounts constituting cost of construction :

I. Amounts paid as premiums on plaintiff’s payrolls on account of Workmen’s Compensation Insurance
II. Social Security payments on payroll to Department of Health, Education and Welfare.
III. Unemployment compensation Tax to State of Kentucky Total of I, II and III $2,500.00
IV. Water service charge paid City of Hodgenville which is allowed for nine months at average of ten dollars per month 90.00
V. Finish Hardware 50.00
Total $2,640.00

Adding the amount of $2,640 to $96,-552.60 makes the total cost of construction in labor and materials of the building project of $99,192.60, upon which the percentage due plaintiff is to be calculated.

7. The defendant seriously contends that this amount, $99,192.60, should be reduced by the amount of $22,237.15 representing the total of the following items and amounts.

I. Plastering contract, including supplies and materials $3,078.21
II. Electrical contract, including materials and supplies 6,006.75
III. Marquee 4,150.00
IV. Motion picture screen 135.38
V. Air conditioning ducts 2,894.66
VI. Glass Contract 3,240.00
VII. Draperies and Curtains 2,396.75
VIII. Adjustment in lumber bills 335.40
$22,237.15 Total

These items, defendant claims, should not be considered a part of construction which the plaintiff supervised and therefore the amounts should not be considered parts of the whole of costs of labor and materials upon which plaintiff’s percentage of compensation should be calculated.

The plastering, electrical wiring, the marquee, the motion picture screen, the window glass, are all essential parts of the theater building. The fact that a plasterer and electrician were employed who were neither employed by plaintiff at the time he contracted with defendant to plan and supervise the building has no bearing on the question.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D. C. Edwards & Co. v. Fisher
610 S.W.2d 546 (Court of Appeals of Texas, 1980)
Albert Alexander Pinkney v. United States
380 F.2d 882 (Fifth Circuit, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
128 F. Supp. 425, 1955 U.S. Dist. LEXIS 3671, Counsel Stack Legal Research, https://law.counselstack.com/opinion/churchill-v-anderson-kywd-1955.