Winston & Co. v. Clark County Construction Co.

217 S.W. 1027, 186 Ky. 743, 1920 Ky. LEXIS 26
CourtCourt of Appeals of Kentucky
DecidedJanuary 16, 1920
StatusPublished
Cited by8 cases

This text of 217 S.W. 1027 (Winston & Co. v. Clark County Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Winston & Co. v. Clark County Construction Co., 217 S.W. 1027, 186 Ky. 743, 1920 Ky. LEXIS 26 (Ky. Ct. App. 1920).

Opinion

Opinion of the Court by

Judge Thomas —

Affirming.

The appellant and defendant below, Winston & Company, is a partnership, and will hereafter be referred to as defendants. The appellee and plaintiff below, Clark County Construction Company, is a corporation, and will hereafter be referred to as plaintiff.

The plaintiff, claiming a contract with the defendants to construct a concrete culvert and a concrete viaduct on a line of railroad between Winchester, Kentucky, and Irvine. Kentucky, brought this suit to recover the unpaid balance of $5,048.43 alleged to be due it in the performance of such work.

The answer was a denial of the allegations of the petition, and the jury empaneled to try the issue as to the existence of the contract returned a verdict in favor of plaintiff. The issue as to the amount due plaintiff, if anything, involving complicated accounts, was referred to the master commissioner of the Clark circuit court, and he reported a balance due it of $3,704.10. Both parties filed exceptions to the report, some of which were sustained and others overruled. The court gave judg[745]*745ment in favor of plaintiff for $3,542.86, and to reverse that judgment the defendants prosecute this appeal.

The defendants are engaged in construction work, and in the year 1913 they had a contract with the Louisville & .Nashville Railroad Company (hereinafter referred to as the railroad company) to construct a new line of railroad from Winchester, Kentucky, to Irvine, Kentucky. They sublet the ‘work in sections to other contractors, one of whom was the Jones-Gray Construction Company (hereinafter referred to as the subcontractor), who had a contract for a three-mile section, and in which it was necessary to build a box culvert at one place and a viaduct at another. In the original contract between the defendants and the subcontractor it was stipulated that these structures should be built of wood, but it is said by the attorneys that the contract provided that if the railroad company should conclude before the completion of the work to have the structures made of concrete, the subcontractor would do so, receiving therefor increased pay for that character of work.

Under the contract between the railroad company and the defendants the entire work, including that section sublet to the subcontractor, was to be completed some time in October. Before the latter part of July the railroad company concluded to have the culvert and the viaduct made of concrete, and so notified the defendants, who mentioned the matter to their subcontractor, whereupon there was some dispute as to whether the latter was compelled under its contract to construct the work in the altered form. It seems, however, that this was soon agreed to, and the subcontractor approached plaintiff, it being engaged in doing concrete work, to build the culvert and viaduct, they being at stations 884 and 885 in the line of railroad being built by the subcontractor.

In the negotiations which followed, the subcontractor submitted to the plaintiff a list of prices, as well as. stipulations for the concrete work, and the latter declined to undertake it at the prices submitted. Subsequent meeting of the parties resulted in no further progress, and about the last of July or the first of August the plaintiff’s president, and also its general manager, went to the office of defendants, who were anxious for the work to be completed in the time specified in their contract, and plaintiff proves by its president and also by its general manager that in this meeting there was [746]*746an oral contract agreed to in which, the price for each item of the work, as well as material, was stipulated, and plaintiff soon thereafter moved its machinery to the place where the concreting was to be done and commenced work. The first estimate for work done by it was due on September 20, following. It was made out, but the railroad company declined to pay because plaintiff had no written contract. Application was then made by plaintiff to defendants to reduce the contract to writing, which up to that time rested in parol only, and on October 10, 1913, defendants sent to plaintiff a prepared contract dated September 25th, accompanied by this letter:

“Winchester, Ky., October 10th, 1913.
“The Clark County Construction Company, Winchester, Ky.
"Gentlemen:—
“Enclosed we send you contract between yourselves and the Jones-Cray Construction Company for concrete work on the Jones-Cray contract.
“On receipt of the enclosed contract signed by you, we will then give you memorandum of agreement between W. & Company and yourselves. Yours very truly,
“Winston & Company.”

The next day plaintiff returned the contract to defendants unsigned, with a letter pointing out wherein its terms differed from those orally agreed to, that difference consisting in the price to be paid for the construction of the two abutments to the viaduct, and for three other items relating to the price of sand, cement, etc. Later plaintiff received the contract sued on from the subcontractor, with the suggested alterations therein with reference to the three items of the cost of material, but it did not contain what plaintiff claimed to be the contract with reference to the construction of the abutments. Plaintiff added that clause and returned the contract to the subcontractor, inasmuch as it had been sent by the subcontractor, and it was signed by the latter on November 8, 1913.

It would serve no useful purpose to set out the contract in full in this opinion, since it is quite long, and would throw no light upon the questions involved. Suffice it to say that it purports on its face to be executed between the subcontractor on the one side and the plaintiff on the fither.

[747]*747One of the chief contentions urged by defendants for a reversal of the judgment is that the contract sued on was never entered into by them, but that it was one exclusively between the subcontractor and plaintiff. On the trial before the jury which found this issue in favor of plaintiff, its president and also its general manager testified that the contract was with defendants and not with the subcontractor. Opposing this, defendants’ general manager testified that his company: entered into no such contract, and Mr. Jones, an officer of the subcontractor, gave the same testimony. -

It is also urged in behalf of defendants that they already had a contract with the subcontractor for the work out of which this litigation grows, and there was no need to make a contract with another for the same work. The fact that the contract on its face purports to be one made between plaintiff and the subcontractor is another circumstance relied on by defendants, who say that they did not write the letter quoted above, of date October 10, but that their stenographer, without their authority, wrote it. But be this as it may, before the contract was signed by the subcontractor, and while plaintiff was making efforts to have, the contract reduced to writing, defendants wrote plaintiff a-letter of date October 21, in which they said, inter alia, "

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gruschus v. CR Davis Contracting Company
409 P.2d 500 (New Mexico Supreme Court, 1965)
Churchill v. Anderson
128 F. Supp. 425 (W.D. Kentucky, 1955)
Rochell v. Moore-Handley Hardware Co.
196 So. 143 (Supreme Court of Alabama, 1940)
Ross v. Ross' Administrator
24 S.W.2d 287 (Court of Appeals of Kentucky (pre-1976), 1930)
Walker v. Walker
15 S.W.2d 298 (Court of Appeals of Kentucky (pre-1976), 1929)
Ferguson v. A. F. Stewart Const. Co.
1925 OK 905 (Supreme Court of Oklahoma, 1925)
Federal Chemical Co. v. Pioneer Coal & Coke Co.
246 S.W. 127 (Court of Appeals of Kentucky, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
217 S.W. 1027, 186 Ky. 743, 1920 Ky. LEXIS 26, Counsel Stack Legal Research, https://law.counselstack.com/opinion/winston-co-v-clark-county-construction-co-kyctapp-1920.