Childers v. Holmes

68 S.W. 1046, 95 Mo. App. 154, 1902 Mo. App. LEXIS 23
CourtMissouri Court of Appeals
DecidedJune 2, 1902
StatusPublished
Cited by8 cases

This text of 68 S.W. 1046 (Childers v. Holmes) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Childers v. Holmes, 68 S.W. 1046, 95 Mo. App. 154, 1902 Mo. App. LEXIS 23 (Mo. Ct. App. 1902).

Opinion

ELLISON, J.

This is an action on two special taxbills issued for putting in curbing on one of the streets of Kansas City. The plaintiff is assignee of the contractor and obtained judgment in the trial court.

The facts necessary to an understanding of the case are that on the twenty-third day of November, 1895, an ordinance was passed by the council of Kansas City providing for the work. The ordinance provided that the curbing was deemed necessary to be done by the council; and that all of the curbing not done by owners of the property liable to be charged should be paid for by special taxbills. It further provided for notice by advertisement to the owners of the property to put in the curbing within thirty days of the first day of publication, and after the expiration of the thirty days the city engineer should give ten days’ notice of a public letting of the work not put in by the owners. None of the work was done by the owners within said thirty days’ period, and thereafter, on February 25, 1896, the entire work was contracted to J. A. Elliott at forty-five and three-fourths cents per lineal foot in [157]*157pursuance of a letting to Mm after proper notice. He gave bond as requiréd by law with T. L. Rowland and James G-. Minear as sureties for the faithful performance of the contract. The contract provided that the work should be completed witbin one hundred days. On the fourth of March, 1896, the city council passed an ordinance confirming said contract. The one hundred days limited to do the work expired in the month of June thereafter; and the work not being then completed, the.city council, on July 29, 1896, passed an ordinance extending the time in which to complete it for forty-five days. The curbing was to be upon both sides of Fifteenth street from Virginia avenue to the eastern city limits. A material portion of this work thus contracted to Elliott by the city (that fronting the property of Foster) was not done under the contract. It was done by Elliott for Foster under a private contract at a less price per foot than bis bid for the whole work, and which be bad secured from Foster before be bid in and contracted the work from the city. The contract with the city contained provisions in regard to forfeiture of ten dollars per day if the work was not completed in the time agreed, and of the right of the city engineer to stop work or extend the time thereunder. And that if it was not begun in ten days after the contract was binding and prosecuted uninterruptedly with sufficient force to complete it witbin the one hundred days, that the contractor would forfeit six hundred dollars, etc. Similar provisions were discussed in Mc-Quiddy v. Brannock, 70 Mo. App. 535, and need not be further noticed.

The trial court refused a demurrer to the evidence, and refused instructions declaring that the private contract with Foster avoided the taxbills. It likewise refused an instruction declaring that if the work was not completed witbin the one hundred days limited by the contract, the bills were void. And an instruction that [158]*158if the work was not done within the time as extended forty-five days, the bills were void.

1. Prom the foregoing statement it will be observed that the ordinance providing for the work did not prescribe a specific time in which it should be done. That the contract did prescribe the specific time of one hundred days, and that the contract was confirmed by ordinance. This state of facts fixed the time at one hundred days. Ayers v. Schmohl, 86 Mo. App. 349. It may be conceded in plaintiff’s behalf (without deciding') that the time was properly extended by ordinance for forty-five days. If, therefore, the fact be that the work was not completed within that time, the bills are void and the judgment should have been for the defendant. Barber Asphalt Co. v. Ridge, 169 Mo. —; Neill v. Gates, 152 Mo. 585; McQuiddy v. Brannock, 70 Mo. App. 535; Rose v. Trestrail, 62 Mo. App. 352; Whittemore v. Sills, 76 Mo. App. 248; Trust Co. v. James, 77 Mo. App. 616; Winfrey v. Linger, 89 Mo. App. 159; City of Springfield v. Davis, 80 Mo. App. 574. An examination of the record discloses that the work contracted for was not completed until several months after the expiration of the time, counting in the extension aforesaid.

There is much urged by plaintiff as to the city engineer having either extended the time, or by his conduct so hindered the contractor that he could not complete the work within the time limited. It has been frequently decided in taxbill and kindred cases, under charters similar to the one now being considered, that the power of extending time could not be delegated to the city engineer. Neill v. Gates, 152 Mo. 585; McQuiddy v. Brannock, 70 Mo. App. 535; St. Louis v. Clemens, 43 Mo. 395; Ruggles v. Collier, 43 Mo. 353; St. Louis v. Russell, 116 Mo. 248. As to any act of the city, through its engineer or other officer, preventing the contractor from completing the contract, wregard the case as showing an entire failure of evi [159]*159dence. All time of interruption on the part of city officials may he excluded, and yet the work was .not completed within the time-limit.

2. It is practically conceded that that portion of the work let to plaintiff, but which he performed under private contract with Foster, was not completed until the first part of December, 1896, and it is contended that though such portion was not completed in the time limited, yet that could not affect that part done under the public contract. That contention is not sound; it will not do to say that such part was taken from under the provisions of the contract with the city because done under private contract. The city and the property-owners are interested in the completion of the whole work, as originally publicly contracted for. If that portion of the work which is thus done under private contract can be delayed beyond the time agreed in the public contract, it is easily seen how a street might be left in an unfinished state indefinitely, and that public work could be placed beyond the control of the city.

3. But did not the private contract with Foster have the effect of avoiding these bills'? We believe it did. It appears from what we stated at the outset, that an ordinance provided that notice by advertisement should be given the property-holders advising and authorizing them to do the work in front of their own property, and that at the expiration of that time the engineer should advertise for bidders on the work not elected to be done by the property-owners. In such case, whatever work is elected to be done privately by the owner should be omitted from the public bids and public letting. In this case Foster elected to do the work in front of his property by private contract with the same party who afterwards got the public contract. But instead of omitting such portion from the public bid and public letting, it was included and the whole was let as public work. This was both unjust and [160]*160illegal, as will appear from the following considerations.

The law is that the cost of the work must be apportioned among all the work, each piece ‘of property bearing its proportion of the whole work and not the mere cost of the work in its immediate front. Neenan v. Smith, 50 Mo. 525; Smith v. Small, 50 Mo. App. 401. So that if, in apportioning the cost to the different pieces of property, one tract is omitted, it vitiates the whole, for the reason that the burden had not been fairly or legally distributed. City of Independence v. Grates, 110 Mo. 374; Leach v. Cargill, 60 Mo. 316; Diggins v. Brown, 76 Cal. 318; Rentz v. Detroit, 48 Mich. 544.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fisher v. L. E. Whitham & Co.
39 S.W.2d 869 (Texas Supreme Court, 1931)
McKine v. City of Independence
162 S.W. 326 (Missouri Court of Appeals, 1914)
Fellows v. Dorsey
157 S.W. 995 (Missouri Court of Appeals, 1913)
Rider v. Parker Washington Co.
128 S.W. 226 (Missouri Court of Appeals, 1910)
Kurtz v. Knapp
106 S.W. 537 (Missouri Court of Appeals, 1907)
Merine v. Barber Asphalt Paving Co.
103 S.W. 508 (Missouri Court of Appeals, 1907)
Spalding v. Forsee
83 S.W. 540 (Missouri Court of Appeals, 1904)
Heman v. Gilliam
71 S.W. 163 (Missouri Court of Appeals, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
68 S.W. 1046, 95 Mo. App. 154, 1902 Mo. App. LEXIS 23, Counsel Stack Legal Research, https://law.counselstack.com/opinion/childers-v-holmes-moctapp-1902.