Neill v. Gates

54 S.W. 460, 152 Mo. 585, 1899 Mo. LEXIS 257
CourtSupreme Court of Missouri
DecidedDecember 12, 1899
StatusPublished
Cited by35 cases

This text of 54 S.W. 460 (Neill v. Gates) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Neill v. Gates, 54 S.W. 460, 152 Mo. 585, 1899 Mo. LEXIS 257 (Mo. 1899).

Opinion

BURGESS, J.

-This is an action by plaintiff as assignee of one James Pryor on six different tax bills aggregating, not including interest when the suit was begun, the sum of $2,515.85, and .issued by Kansas City against six different tracts of land owned by defendant, in Sewer District No. 167, in said city.

On April 18, 1891, an ordinance was passed by Kansas City establishing Sewer District No. 167, which embraced the land against which the tax bills involved in this litigation were issued. Thereafter on June 10, 1891, an ordinance No. 3247 was passed, authorizing the construction of sewers in said district,- by which it was provided that “the work should be completed within ninety days from the .time a contract binds and takes effect,” the ordinance reciting that “this work the Board of Public Works and Common Council deem necessary for sanitary and drainage purposes.”

The work was let by contract to said Pryor, and approved by ordinance of date July 23, 1891. By its terms work was to [589]*589be begun in ten days and to be completed in ninety days from tbe time tbe contract was executed. The contract provided that the contractor should not be entitled to any portion of the contract price until the work was completed to the satisfaction of the city engineer, and -then only in tax bills. The time in which the work was to be completed expired October 21, 1891. The work was begun, and continued up to August 21, 1891, when Jennie O. 'Wiltsee and others brought suit against the contractors and Kansas City, and obtained a temporary injunction restraining them from a continuation of the work. The injunction was dissolved on October 31, 1891, but from the time it was granted until its dissolution, no work was done on the sewer.

The contract provides that:

“6. The work embraced in this contract shall be begun within ten days after this contract binds and takes effect, and shall be prosecuted regularly'and uninterruptedly thereafter (unless the engineer shall specially direct otherwise in writing) with such force as to secure its full completion within ninety days from the date of its confirmation; the time of beginning, rate of progress, and time of completion being essential conditions of this contract. And if the contractor shall fail to complete the work within the time above specified, an amount equal to the sum of ten dollar’s per day for each and every day thereafter, until such completion, shall be deducted as liquidated damages for such breach of this contract from the amount of the final estimate of said work..
“T. If, in the opinion of the engineer, the first party, at any time during the progress of the work, is not prosecuting the work with a sufficient force to insure its completion within the time specified in this contract, he may notify the first party to employ such additional force as he deems sufficient; and on the failure of said first party to comply with such notice within three days after its delivery, the engineer may put on [590]*590such additional force at the cost of the said first party or he may, at his option, declare the contract annulled.
“And the power is reserved to the city engineer by Kansas 'City to suspend or annul this contract or to suspend the doing ■of any work thereunder at any time for any failure on the part of the first party to fulfill the same, or for other good cause; and any action of the city engineer in suspending or annulling this contract, or suspending the doing of the work thereunder, and his decision as to the existence of cause or reason for such annulment or suspension shall be conclusive as to the existence ■of such cause or reason in any controversy or litigation between the parties hereto, or others claiming under them. And if this contract be so suspended or annulled, the said first party ■shall not be entitled to anything on account of damages thereby nor shall such annulment or suspension in any wise affect the right of said Kansas City to damages and penalties claimed by it on account of the failure of said first party.”

The evidence showed that work amounting to $4,000 at the contract price, was done up to February 11, 1892.

On February 4, 1892, the city engineer, Butts, wrote Pryor, the contractor, and his sureties on his bond as contractor, to proceed with the work in three days, and on his failure to do so he would annul the contract, which he, -the ■engineer in so far as he had power to do so did on February 11, 1892, because Pryor would not proceed with the work, and, so notified the board of public works.

Butts, the engineer, went out of office in May, 1892, and was succeeded by John Donnelly. Pryor paid no attention to the cancellation of his contract by Butts, but continued to work on said sewer with the full knowledge and consent of Donnelly, the successor of Butts, until October 24, 1893, when the Common Council of Kansas City passed an ordinance, No. 5453, to construct a district sewer in Sewer District No. 167, .and by it repealed ordinance No. 3247 entitled: “An Ordi[591]*591nance to establish and cause to be constructed district sewer in Sewer District No. 167,” approved June 10, 1891.

This last named ordinance makes no reference to the ordinance approving the contract between the city and the contractor, nor does it refer to the contract.

On December 6, 1893, the Common Council of Kansas City passed “an ordinance to repeal an ordinance of Kansas City No. 5453, entitled: ‘An ordinance to construct a district sewer in Sewer District No. 167,’ approved October 24, 1893.”

On March 19, 1894, said council passed an ordiance extending the time for the completion of said work under the original ordinance, No. 3247, to April 1, 1894.

The tax bills were issued March 20, 1894.

At the close of all the evidence the defendant interposed, and the court sustained, a demurrer to the evidence, and in accordance therewith ruled that plaintiff was not entitled t) recover, and rendered judgment for defendant.

Plaintiff then filed motion for new trial, which was overruled and he appeals.

By express provision of the ordinance under which the-work was done, it was to be completed within ninety days from the time a contract for the work bound and took effect, and by the terms of the contract entered into between Pryor and the city for the work it was provided that “the work embraced in this contract shall be begun within ten days after the contract, binds and takes effect., and shall be prosecuted regularly and uninterruptedly thereafter (unless the engineer shall specially direct otherwise in writing) with such force as to secure its frill completion within ninety days from the date of its confirmation; the time of beginning, rate of progress, and time of completion being essential conditions of this contract. And if the-contractor shall fail to complete the work within the time above-specified an amount equal to the sum of ten dollars per day for each and every day thereafter, until such completion,, [592]*592shall be deducted as liquidated damages for such breach of this contract from the amount of the final estimate of said work.”

That the work was not completed within the time prescribed by the ordinance and contract under which it wás done, is not disputed, and as time was the essence of the contract and material, the tax bills issued for the work and here sued on must be held void (Rose v. Trestrail, 62 Mo. App. 352; McQuiddy v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Riggins v. City of Kansas City
351 S.W.3d 742 (Missouri Court of Appeals, 2011)
St. Louis Terminals Corp. v. City of St. Louis
535 S.W.2d 593 (Missouri Court of Appeals, 1976)
State Ex Rel. Prichard v. Ward
305 S.W.2d 900 (Missouri Court of Appeals, 1957)
Stewart v. City of Springfield
165 S.W.2d 626 (Supreme Court of Missouri, 1942)
Arkansas-Missouri Power Co. v. City of Kennett, Mo.
78 F.2d 911 (Eighth Circuit, 1935)
Fisher v. L. E. Whitham & Co.
39 S.W.2d 869 (Texas Supreme Court, 1931)
Casteel v. Dearmont
299 S.W. 816 (Missouri Court of Appeals, 1927)
Stewart v. City of Goshen
143 N.E. 301 (Indiana Court of Appeals, 1924)
Byrne Real Estate Co. v. Welsh
258 S.W. 743 (Missouri Court of Appeals, 1924)
City of Brunswick Ex Rel. Barkwell v. Beneke
233 S.W. 169 (Supreme Court of Missouri, 1921)
Kershner v. Kershner
216 S.W. 547 (Missouri Court of Appeals, 1919)
Coatsworth Lumber Co. v. Owen
172 S.W. 436 (Missouri Court of Appeals, 1915)
Gratz v. City of Kirkwood
166 S.W. 319 (Missouri Court of Appeals, 1914)
Barber Asphalt Paving Co. v. Kansas City Hydraulic Press Brick Co.
156 S.W. 749 (Missouri Court of Appeals, 1913)
Ohio County v. Baird
181 F. 49 (Sixth Circuit, 1910)
Merchants Exchange v. Knott
111 S.W. 565 (Supreme Court of Missouri, 1908)
State ex rel. Judah v. Fort
109 S.W. 737 (Supreme Court of Missouri, 1908)
Whitworth v. Webb City
103 S.W. 86 (Supreme Court of Missouri, 1907)
Merine v. Barber Asphalt Paving Co.
103 S.W. 508 (Missouri Court of Appeals, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
54 S.W. 460, 152 Mo. 585, 1899 Mo. LEXIS 257, Counsel Stack Legal Research, https://law.counselstack.com/opinion/neill-v-gates-mo-1899.