Barber Asphalt Paving Co. v. Kansas City Hydraulic Press Brick Co.

156 S.W. 749, 170 Mo. App. 503, 1913 Mo. App. LEXIS 359
CourtMissouri Court of Appeals
DecidedApril 21, 1913
StatusPublished
Cited by5 cases

This text of 156 S.W. 749 (Barber Asphalt Paving Co. v. Kansas City Hydraulic Press Brick Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barber Asphalt Paving Co. v. Kansas City Hydraulic Press Brick Co., 156 S.W. 749, 170 Mo. App. 503, 1913 Mo. App. LEXIS 359 (Mo. Ct. App. 1913).

Opinion

TRIMBLE, J. —

Suit on special tax bills for paving with asphalt a business street in Kansas City.

The answer set up nine separate and distinct defenses. Some of these were concluded by the verdict of the jury in plaintiff’s favor. The others, when carefully analyzed, are found to contain really but four matters of defense, some stating the same defense twice in a different way.

On motion of the plaintiff, the court struck out the third, fourth, fifth, sixth and seventh defenses before entering upon the trial. And we are asked to review this action along with other errors claimed.

We shall first take up the fourth and fifth defenses, they being really directed at one and the same [505]*505point. That is, that the pavement was laid nnder a guarantee that it would he constructed of such materials and in such manner as would enable it to endure for ten years without repair, and that as the pavement did not so endure, the tax hillá are void. This point will not avail as a défense. The clause requiring the plaintiff to guarantee the pavement for ten years without repair was within the power of the city to make. [Asphalt Paving Co. v. Ullman, 137 Mo. 543; Seaboard National Bank v. W. S. Woesten, 176 Mo. 49.] This guarantee does not mean that the pavement shall not need repair within that time hut merely hinds the contractor to keep it in repair during that period without further compensation. [Gilsonite Construction Co. v. Coal Co., 205 Mo. 49.] Hence the tax bills are not void hy reason of such guarantee, and the court did not err in striking out said fourth and fifth defenses.

The sixth defense is that a particular brand of asphalt, to-wit, Trinidad Lake asphalt, was required to he used, and, as it was owned and controlled solely hy plaintiff, this excluded competition and rendered nugatory the requirement that the work be let to the lowest bidder. This defense cannot be upheld by this court since, whatever might be our views on that matter, we are required to follow the Supreme Court’s rulings. That court holds that the designation of such-material does not render the tax bill void; [Barber Asphalt Paving Co. v. Field, 188 Mo. 182.] The same doctrine is announced, and reasons therefor given, in Paving Co. v. Hunt, 100 Mo. 22; Verdin v. St. Louis, 131 Mo. 26; and Swift v. St. Louis, 180 Mo. 80. While it is true the decisions in some of these cases last cited were by a divided court, and that tribunal has later manifested a disposition to limit the doctrine, yet we do not think it intended, in the case of Curtice v. Schmidt, 202 Mo. 703, to overturn or abandon it. At any rate we shall continue to fol[506]*506low this doctrine until that conrt shall clearly and unequivocally set it asidé. There was no error in striking out this defense.

The third defense set up in the answer alleged that the ordinance authorizing the work was passed July 30, 1900, and the contract under which the work was done was not let until May 26, 1902; that by reason of the long and unreasonable delay in letting the contract and causing said work to be done, the power to make a contract ceased and the tax bills are, therefore, null and void, of all which plaintiff had notice.

It is held that, where the original ordinance prescribes the time in which the work must be done, the authorities must proceed in the usual course of such matters and within the limits thus prescribed, and they cannot abandon an improvement and then after the lapse of a long period of time resume jurisdiction at the place where it was left off. [Marshall v. Wisdom, 127 Mo. App. 640.] It is also well settled that proceedings had under an ordinance which specifies no time in which the work is to be done are not invalid merely because no time is specified in the ordinance. But it is further held, that where the original ordinance specifies no time, a reasonble time is implied. [Ayers v. Schmohl, 86 Mo. App. 349; Heman v. Gilliam, 171 Mo. 258, l. c. 269, 271.] So that, if the ordinance specifies no time, this does not mean that there is no limit upon the time when the work is to begin or in which it is to be finished. All the authorities hold that the time limits provided in the original ordinance must be observed and the work done within those limits or the tax bills will be void. If, therefore, the original ordinance gives a reasonable time for the work to be done, this reasonable limit must be observed just the same as a specified limit would have to be observed had it been imposed. In the case at bar there was a delay of one year, nine months and twenty-three days before the letting of the contract [507]*507under which the work was done. This length of time unexplained is not a reasonable time. If the contract can be delayed thus long without explanation, what is to prevent a delay of two years, or three or five? When the work was finally begun it was finished within sixty days, consequently, on the face of things, a delay of nearly two years before the' work is even begun is unreasonable and beyond the limit of time implied in the original ordinance. What is a reasonable time usually depends upon the facts in the ease and must be determined in the light of all the circumstances. [Grunby v. Brown, 86 Mo. 1. c. 258.] But the court struck out the defense setting up the fact that there was an unreasonable delay. Hence no inquiry could be made into the question whether, under the facts,-the delay was reasonable or unreasonable. This was error. If we approve this ruling by affirming this case we thereby say, in effect, that no delay will invalidate the proceeding where the ordinance does not fix a precise time limit. Because, if an unexplained delay of nearly two years is allowable, where is the limit to be fixed? We do not think the case of Jaicks v. Middlesex Inv. Co., 201 Mo. 111, when carefully examined, holds that if no time is specified in the original ordinance, then no delay in letting the contract, no matter how long nor from what cause, will be sufficient to render the tax bills void. It is true the second syllabus of the case reads as if the opinion were this broad, and the judge, in deciding the case, says on page 114 that the cause of the delay is “immaterial,” yet he says it is so “upon the disclosures of the record in this case” and-then proceeds to find an exceedingly good reason for the delay and concludes his discussion of such reason by saying on page 116, .“We are of the opinion that such delay, under the facts disclosed, was insufficient to in any way affect either the validity of the ordinance, or power to contract in pursuance of it or the right of the contractor [508]*508to perform the work.” Certainly the learned judge who wrote that, never intended that his decision in that case should be authority for -the view that no delay of any sort will constitute a defense to the tax bill. Besides, in that case, the delay was one on the part of city authorities only, and the judge in writing the opinion seems to have also had this in mind since he says, on page 115, he is unwilling to deprive the contractor of his money “by reason of any delay or neglect on the part of the governing board who had authority by virtue of the ordinance to let the contract.” In the case before us, however, as will appear in our discussion of the striking out of the seventh defense, there was a contract entered into with plaintiff and confirmed and thus made final and binding but which was not performed by plaintiff. In other words, so far as the record now stands, there was a delay participated in by the plaintiff;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bremerton Municipal League v. City of Bremerton
124 P.2d 798 (Washington Supreme Court, 1942)
Missouri Electric Power Co. v. Smith
155 S.W.2d 113 (Supreme Court of Missouri, 1941)
Town of Tonawanda v. Stapell, Mumm & Beals Corp.
147 Misc. 768 (New York Supreme Court, 1933)
Perkins v. City of Pawhuska
1924 OK 1110 (Supreme Court of Oklahoma, 1924)
Heman Construction Co. v. Lyon
211 S.W. 68 (Supreme Court of Missouri, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
156 S.W. 749, 170 Mo. App. 503, 1913 Mo. App. LEXIS 359, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barber-asphalt-paving-co-v-kansas-city-hydraulic-press-brick-co-moctapp-1913.