Chicago Economic Fuel Gas Co. v. Myers

48 N.E. 66, 168 Ill. 139, 1897 Ill. LEXIS 2442
CourtIllinois Supreme Court
DecidedNovember 1, 1897
StatusPublished
Cited by48 cases

This text of 48 N.E. 66 (Chicago Economic Fuel Gas Co. v. Myers) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chicago Economic Fuel Gas Co. v. Myers, 48 N.E. 66, 168 Ill. 139, 1897 Ill. LEXIS 2442 (Ill. 1897).

Opinion

Mr. Justice Magruder

delivered the opinion of the court:

The question in this case, as presented by the briefs of counsel, is not whether there was negligence which caused the injury, but whether such negligence was or was not the negligence of the appellant. It is claimed by the appellant, that a corporation called the Chicago Contract Construction Company, was laying the mains and pipes in question under a contract with the appellant, and was in the possession and control of such mains and pipes. The contention of the appellant is, that the foreman and the watchman and all the laborers at work at the place of the accident were in the employ of the Chicago Contract Construction Company as an independent contractor, and that the appellant is not responsible for any negligence committed by them which caused the injury. In other words, the question of fact in the case is, whether the injury was caused by the appellant, or by said construction companju The principle of law invoked as a defense by the appellant is, that the entire work of laying the gas-pipes and constructing the gas plant was intrusted to an independent contractor, without any right of supervision or control by the appellant; and that, therefore, the appellant, although it authorized the work, is exempt from liability for any resulting injury.

The only error, complained of by the appellant, is, that the trial court refused to give two certain instructions, numbered 6 and 7, asked by the appellant; and modified, and gave as modified, three other instructions, numbered 8, 11 and 13, asked by the appellant.

Instructions 6 and 7 were to the effect, that, if the jury should believe from the evidence, that the appellant company was not the owner of and had no control over the system of gas-pipes, located at the place where the injury occurred, and that the Chicago Construction Company was the owner of such system of pipes, and that appellant simply had a contract to purchase the system of pipes and gas works from said construction company, then the appellant could not be held-liable in this case. It will be observed, that these instructions predicate the finding of the jury upon the assumed fact, that the appellant was not the owner of the gas-pipes, and say nothing about the ownership of the gas in the pipes.

Instructions 8, 11 and 13 lay down the proposition, that the appellant would not be liable, if it had made a contract for the construction of the system of pipes with the construction company, and retained no control over the manner, in which the construction company should prosecute the work; and the modification, made by the court, was in requiring the jury to find, that the construction company had the entire control of the gas in the pipes, as well as of the pipes themselves, at the time of the accident.

First—If it be assumed that the construction company was an independent contractor, the first question is, whether control by the construction company over the gas in the pipes, as well as over the pipes themselves, was necessary to be shown, in order to make the liability that of the construction company. The evidence tends to show, that, even if the mains and pipes were under the possession and control of the construction company, the gas, which was let into the pipes and propelled through them when the accident occurred, was owned by, and under the control of, the appellant. The gas was turned into the pipes when the joints of the pipes were cemented together, for the purpose of testing the strength and completeness of the juncture. It is clear, therefore, that, even if the accident was due to the negligence of the servants of the construction company in not properly' constructing or joining the pipes and mains, yet it was also due to the negligence of the appellant in propelling the gas into and through such pipes, without ascertaining and knowing beforehand that they were in proper condition. The fact, that the construction company had not, at the time of the accident, fully completed its contract, and had not formally turned over the plant to the appellant, would not relieve the appellant from liability for the negligent manner, in which the gas was conveyed through the carelessly constructed pipes, if the appellant was in the actual use of such gas. (Lebanon Light, Heat and Power Co. v. Leap, 139 Ind. 443).

“It is a familiar principle that where the negligence of two is, in combination, the proximate cause of an injury, either or both may be held responsible for the consequences resulting from their combined negligence.” (Pullman Palace Car Co. v. Laack, 143 Ill. 242; Kankakee Railroad Co. v. Horan, 131 id. 288).

Second—We are of the opinion, however, that the doctrine of “independent contractor” does not apply to the present case. In the first place, the construction company was a mere means or mode, adopted by the gas company for the construction of its system of gas-pipes and gas works. The construction company was a mere instrument or tool used by the gas company for that purpose. The evidence tends fairly and clearly to show, that the construction company was organized and acted simply as the agent or servant of the appellant company. An attempt is here made to evade liability by interposing a construction company as the guilty party. The officers of the gas company were also officers of the construction company. The construction company and the gas company had their offices in the same building, the offices of the gas company being on the first floor and the offices of the construction company being on the second floor. One Judson was the president of the gas company, and at the same time was consulting and supervising engineer of the construction company. One Yuille was paymaster of the construction company and also an officer of the gas company. One Bryant was supervising the office and fixtures of the construction company in December, -1892, and was also secretary and treasurer of the gas company. One Jelps was in the employ of the gas company and left such employment and worked for the construction company, but at once went back into the service of the gas company. All the officers and employees of the construction company, who testified in this case, were either at the same time connected in some way with the gas company, or passed alternately from the service of one to the service of the other. The contract between the construction company and the gas company contained a provision, that the size of the pipes to be laid should be determined by the gas company; and there are other provisions in the contract, whicli go to show that the gas company was not to be entirely without control and supervision over the construction of the pipes and the gas plant. The evidence shows, that, on the afternoon of December 1,1892, two or three hours before the accident occurred, Judson gave the order for letting the natural gas into the pipes; and he testifies, that he is unable to state whether he gave such order as the president of the gas company, or as the supervising engineer of the construction company. Certain it is, that he supervised the construction of the gas-pipes and the gas plant; and it is just as natural to suppose, that he did it as the president of the gas company, as that he did it as the supervising engineer of the construction company. The law is quite clear, that a corporation cannot thus shift its responsibility upon another corporation which is its mere ag'ent and tool.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daniels v. Venta Corp.
2022 IL App (2d) 210244 (Appellate Court of Illinois, 2022)
Apostal v. Oliveri Construction Co.
678 N.E.2d 756 (Appellate Court of Illinois, 1997)
Schoenbeck v. Du Page Water Commission
607 N.E.2d 693 (Appellate Court of Illinois, 1993)
Milz v. M.J. Meadows, Inc.
599 N.E.2d 1290 (Appellate Court of Illinois, 1992)
Central Trust & Savings Bank v. Toppert
554 N.E.2d 820 (Appellate Court of Illinois, 1990)
Cooper v. Metropolitan Government of Nashville & Davidson County
628 S.W.2d 30 (Court of Appeals of Tennessee, 1981)
Graves v. North Shore Gas Co.
424 N.E.2d 1279 (Appellate Court of Illinois, 1981)
Montanez v. Cass
546 P.2d 1189 (New Mexico Court of Appeals, 1976)
Reith v. General Telephone Co.
317 N.E.2d 369 (Appellate Court of Illinois, 1974)
Hulke v. International Manufacturing Co.
142 N.E.2d 717 (Appellate Court of Illinois, 1957)
Opal v. Material Service Corp.
133 N.E.2d 733 (Appellate Court of Illinois, 1956)
Taylor v. Oakland Scavenger Co.
110 P.2d 1044 (California Supreme Court, 1941)
Cotton v. Ship-By-Truck Co.
85 S.W.2d 80 (Supreme Court of Missouri, 1935)
Longo v. Lewis
252 Ill. App. 401 (Appellate Court of Illinois, 1929)
Birmingham Realty Co. v. Crossett
98 So. 895 (Supreme Court of Alabama, 1923)
Donohue v. George W. Stiles Construction Co.
214 Ill. App. 82 (Appellate Court of Illinois, 1919)
Girdzus v. Van Etten
211 Ill. App. 524 (Appellate Court of Illinois, 1918)
New York Trust Co. v. Carpenter
250 F. 668 (Sixth Circuit, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
48 N.E. 66, 168 Ill. 139, 1897 Ill. LEXIS 2442, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chicago-economic-fuel-gas-co-v-myers-ill-1897.