Chestnut Hill Development Corp. v. Otis Elevator Co.

653 F. Supp. 927, 4 U.C.C. Rep. Serv. 2d (West) 1359, 1987 U.S. Dist. LEXIS 1222
CourtDistrict Court, D. Massachusetts
DecidedFebruary 19, 1987
DocketCiv. A. 86-1387-C
StatusPublished
Cited by24 cases

This text of 653 F. Supp. 927 (Chestnut Hill Development Corp. v. Otis Elevator Co.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chestnut Hill Development Corp. v. Otis Elevator Co., 653 F. Supp. 927, 4 U.C.C. Rep. Serv. 2d (West) 1359, 1987 U.S. Dist. LEXIS 1222 (D. Mass. 1987).

Opinion

*929 MEMORANDUM

CAFFREY, Senior District Judge.

This is a contract and unfair trade practices action brought by Chestnut Hill Development Corporation (“Chestnut Hill”), the owner and developer of a condominium complex known as Hampton Place, against Otis Elevator Company (“Otis"), for the alleged defective installation and maintenance of five elevators. The action was commenced in the Superior Court of the Commonwealth of Massachusetts and was properly removed to this Court pursuant to 28 U.S.C. § 1441. Plaintiff is a Massachusetts corporation with its principal place of business in Boston. Defendant is á New Jersey corporation with its principal place of business in Farmington, Connecticut. The amount in controversy exceeds $10,-000. This Court exercises its diversity jurisdiction over the action pursuant to 28 U.S.C. § 1332. The matter is now before the Court on defendant's motion for summary judgment, or, in the alternative, for partial summary judgment.

I. Background

On January 21,1983, the plaintiff, Chestnut Hill, entered into a multi-million dollar contract with Vappi Construction Company (“Vappi”) for the construction of Hampton Place. On June 17, 1983, the defendant, Otis, entered into a subcontract with Vappi in which Otis agreed to furnish and install five elevators at Hampton Place, by March 1, 1984, for a price of $375,000. The five elevators to be installed included one hydraulic elevator, two geared-drive elevators and two battery-powered elevators known in the trade as “Mid-Rise Systems with Variable Frequency Drive Control” (“MRVF”). It is not disputed that two elevators were formally accepted by Vappi on August 3,1984, two others were accepted on November 20,1984, and that the final elevator was accepted on December 17, 1984. On May 3, 1985, Chestnut Hill and Otis entered into a separate maintenance contract covering the five Hampton Place elevators.

In its complaint, Chestnut Hill alleges that it sustained monetary damages as a result of the delayed installation of the elevators. Chestnut Hill further complains that the elevators are defective and that none of them function properly. The problems with the MRVF, as well as with the other three elevators, include excessive noise during operation, rough and shaky rides, uneven levelling at floors, and inoperative doors. Moreover, Chestnut Hill contends that during the negotiations over the Otis elevators Otis knew that its MRVF elevators presented similar operations problems nationwide. Chestnut Hill contends that such problems were the result of defective design and defective components. Despite Otis’ knowledge of such problems, Chestnut Hill alleges that Otis made representations regarding the MRVF system’s lower operating and maintenance costs, smoother rides, more accurate levelling and reduced noise during operation, thereby influencing Chestnut Hill’s selection of the Otis elevators.

On March 27, 1986, Chestnut Hill filed a five count complaint against Otis. Count I alleges that Otis breached its contract with Vappi, a contract to which Chestnut Hill asserts it is a third party beneficiary. Counts II, III and IV allege that Otis breached express and implied warranties arising out of that contract. In Count V Chestnut Hill alleges that Otis engaged in unfair and deceptive trade practices in violation of M.G.L. c. 93A § 2. Chestnut Hill requests this Court to award it $1,000,000 in direct damages, $10,000,000 in lost profits, which total amount is to be trebled pursuant to M.G.L. c. 93A § 11. In response to Chestnut Hill’s complaint, Otis requests this Court to grant summary judgment in its favor on all the counts pursuant to Fed.R.Civ.P. 56(c), or alternatively, to rule that Chestnut Hill’s claim for consequential damages fails as a matter of law.

Summary judgment is appropriate when the moving party persuades the Court that based on “the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, ... *930 there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed.R. Civ.P. 56(c). Otis is thus entitled to summary judgment only if the record, when considered in the light most favorable to Chestnut Hill, fails to reveal questions of fact that are both “genuine” and “material.” Hahn v. Sargeant, 523 F.2d 461, 464 (1st Cir.1975), cert, denied, 425 U.S. 904, 96 S.Ct. 1495, 47 L.Ed.2d 754 (1976). In this matter, for the following reasons, defendant’s motion for summary judgment should be denied, and defendant’s alternative motion for partial summary judgment on the issue of consequential damages should be allowed.

II. The Third Party Beneficiary Theory

Otis’ primary argument in support of its motion for summary judgment on Chestnut Hill’s third party beneficiary claim is that an owner-developer like Chestnut Hill is not a third party beneficiary of a contract entered into by a general contractor and a subcontractor. Otis argues that in order for Chestnut Hill to prevail on its claim that it suffered damages as a result of Otis’ alleged breach of the Otis-Vappi subcontract, Chestnut Hill must be an intended beneficiary of that subcontract. Otis maintains that Chestnut Hill is instead an incidental beneficiary of that subcontract and as such has no contractual relationship with Otis. Otis relies primarily on Rae v. Air Speed, Inc., 386 Mass. 187, 195, 435 N.E.2d 628 (1982), where the Massachusetts Supreme Judicial Court adopted the test set forth in the Restatement (Second) of Contracts for determining whether a party is an intended or incidental beneficiary of a contract. Section 302 of the Restatement provides:

(1) Unless otherwise agreed between promisor and promisee, a beneficiary of a promise is an intended beneficiary if recognition of a right to performance in the beneficiary is appropriate to effectuate the intention of the parties and either

(a) the performance of the promise will satisfy an obligation of the promisee to pay money to the beneficiary; or

(b) the circumstances indicate that the promisee intends to give the beneficiary the benefit of the promised performance. (2) An incidental beneficiary is a beneficiary who. is not an intended beneficiary.

Otis contends that Chestnut Hill gained no third party beneficiary rights against Otis because the performance of Otis’ promise to Vappi was to satisfy a contractual obligation to Vappi, not to Chestnut Hill. Moreover, Otis contends that it did not promise to fulfill Vappi’s promise to Chestnut Hill, which was to furnish completed condominium units. Instead, Otis promised only to furnish and install the five elevators.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arco Ingenieros, S.A. de C.V. v. CDM International Inc.
368 F. Supp. 3d 256 (District of Columbia, 2019)
Hayes v. CRGE Foxborough, LLC
167 F. Supp. 3d 229 (D. Massachusetts, 2016)
Reisman v. KPMG Peat Marwick LLP
787 N.E.2d 1060 (Massachusetts Appeals Court, 2003)
John Beaudette, Inc. v. Sentry Insurance a Mutual Co.
94 F. Supp. 2d 77 (D. Massachusetts, 1999)
Mitzan v. Medview Services, Inc.
10 Mass. L. Rptr. 242 (Massachusetts Superior Court, 1999)
Sebago, Inc. v. Beazer East, Inc.
18 F. Supp. 2d 70 (D. Massachusetts, 1998)
Bath v. Hi-Tech International, Inc.
704 So. 2d 292 (Louisiana Court of Appeal, 1997)
Commonwealth v. Homart Development Co.
6 Mass. L. Rptr. 517 (Massachusetts Superior Court, 1997)
Klein v. Boyd
949 F. Supp. 280 (E.D. Pennsylvania, 1996)
Lambert v. Fall River Five Cent Savings Bank
3 Mass. L. Rptr. 633 (Massachusetts Superior Court, 1995)
Standard Register Co. v. Bolton-Emerson, Inc.
649 N.E.2d 791 (Massachusetts Appeals Court, 1995)
Cambridge Plating Co., Inc. v. Napco, Inc.
991 F.2d 21 (First Circuit, 1993)
John Boyd Co. v. Boston Gas Co.
775 F. Supp. 435 (D. Massachusetts, 1991)
Chestnut Hill Development Corp. v. Otis Elevator Co.
739 F. Supp. 692 (D. Massachusetts, 1990)
Logan Equipment Corp. v. Simon Aerials, Inc.
736 F. Supp. 1188 (D. Massachusetts, 1990)
J. M. Westall & Co. v. Windswept View of Asheville, Inc.
387 S.E.2d 67 (Court of Appeals of North Carolina, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
653 F. Supp. 927, 4 U.C.C. Rep. Serv. 2d (West) 1359, 1987 U.S. Dist. LEXIS 1222, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chestnut-hill-development-corp-v-otis-elevator-co-mad-1987.