Chestnut Development LLC v. Township of Genoa

CourtMichigan Court of Appeals
DecidedDecember 18, 2014
Docket317199
StatusUnpublished

This text of Chestnut Development LLC v. Township of Genoa (Chestnut Development LLC v. Township of Genoa) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chestnut Development LLC v. Township of Genoa, (Mich. Ct. App. 2014).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

CHESTNUT DEVELOPMENT, LLC, UNPUBLISHED December 18, 2014 Plaintiff-Appellee,

v No. 317199 Livingston Circuit Court TOWNSHIP OF GENOA and GENOA LC No. 12-027123-CZ TOWNSHIP ZONING ADMINISTRATOR,

Defendants-Appellants.

Before: M. J. KELLY, P.J., and CAVANAGH and METER, JJ.

PER CURIAM.

Defendants appeal as of right an order granting plaintiff a writ of mandamus compelling defendants to issue a land use permit. We affirm in part, vacate in part, and remand this matter for proceedings consistent with this opinion.

Plaintiff owns two contiguous parcels of real property in Genoa Township. In 2004, plaintiff’s predecessor in interest, Crescendo Homes, sought to develop the subject property as a planned unit development (PUD) under Article 10 of the Township’s zoning ordinance.1 The property was zoned agricultural (AG); thus, rezoning was requested. In that regard, Crescendo Homes submitted its conceptual PUD site plan, a PUD agreement, and its impact statement as required under Section 10.05. The Township board approved the conceptual PUD site plan and, pursuant to Section 10.03, the property was rezoned.2 Thereafter, Crescendo Homes abandoned the project and the property. Plaintiff acquired the property from the Department of Treasury through tax foreclosure proceedings.

1 Our references to an “Article” or a “Section” refer to the Genoa Township Zoning Ordinance. 2 While there was some confusion regarding whether the property was rezoned to a residential PUD or a mixed use PUD, we refer to the rezoning classification as “PUD” for purposes of this opinion.

-1- Eventually plaintiff applied for a land use permit to construct a single-family home and to enlarge an existing pond on its property.3 Defendants denied the application on the ground that the property was zoned PUD and plaintiff had to comply with Article 10 or, alternatively, seek rezoning. Plaintiff then filed this action seeking, in relevant part, a writ of mandamus compelling defendants to issue the land use permit.4 Plaintiff argued that it was seeking to construct a single family home, not a PUD. And because it was in compliance with the residential zoning requirements, plaintiff was entitled to a land use permit under Section 13.01 to “change the topography of the site” prior to its development.5 Defendants responded, arguing that this matter was not ripe for adjudication and, in any case, plaintiff could not merely apply for a land use permit but had to comply with the requirements of Article 10 as a consequence of the property’s PUD zoning or seek rezoning. Further, defendants argued, plaintiff actually sought to mine sand from its property to sell which is only permitted in industrial districts with special land use approval.

Following a hearing, the trial court ordered additional discovery and briefing. In its supplemental brief, plaintiff argued that discovery revealed its property was never validly rezoned to PUD. That is, plaintiff argued, the property was zoned AG because plaintiff’s predecessor in ownership did not complete the rezoning process by complying with the requirements of Article 10. A single-family residence and a pond is allowed on property zoned AG. Further, defendants’ characterization of its sand excavation as a “mining operation” was erroneous. Accordingly, plaintiff requested the trial court to compel defendants to issue the requested land use permit.

Defendants argued in their supplemental brief that plaintiff’s property was zoned PUD so a single-family residence was not allowed and plaintiff’s extraction of sand was a mining operation. Further, defendants argued that plaintiff’s claim was not ripe for adjudication because plaintiff failed to appeal the denial of its application to the Township’s Zoning Board of Appeals (ZBA), which could have determined the type of PUD at issue and the characterization of the sand extraction at issue. Accordingly, defendants argued, plaintiff was not entitled to a writ of mandamus compelling the issuance of a land use permit.

At the conclusion of the continued hearing, the trial court entered an order finding that the matter was not ripe for adjudication because plaintiff had submitted revised site plan drawings in support of its request for a land use permit and defendants had neither reviewed them nor made a decision. Defendants later denied plaintiff’s application. Thereafter the court held an evidentiary hearing over defendants’ objections premised on the arguments that the case was not ripe for review and discretionary issues precluded a writ of mandamus. At the

3 We note that plaintiff’s application for a land use permit, dated October 10, 2012, indicated that the type of improvement sought was a “new single family” structure. The box associated with “Grading/Site Work” was not checked and a “pond expansion” was not noted on the application. 4 Plaintiff’s complaint indicated that the subject property was zoned residential PUD as set forth on the Township’s zoning map. 5 See footnote 3.

-2- conclusion of the hearing, the court held: (1) the rezoning of the property from AG to PUD was not completed because the requirements set forth in Article 10 were not complied with by plaintiff’s predecessor in interest so the property remained zoned AG; (2) AG zoning allows for a residence and a pond expansion; (3) plaintiff’s proposed land use did not constitute a sand mining operation; and (4) an appeal to the ZBA would have been futile because the ZBA did not have the authority to alter zoning districts. Accordingly, the trial court granted plaintiff’s request for a writ of mandamus and ordered defendants to issue plaintiff a land use permit.

Defendants filed a motion for reconsideration, arguing that the case was not ripe for adjudication because plaintiff did not challenge the denial before the ZBA, where it could have obtained the requested relief or, at least, a final decision before it pursued this matter in court. Further, defendants argued that the court’s rulings circumvented the Township’s zoning ordinance and included palpable errors. In particular, the court’s conclusions that the property reverted to AG zoning from PUD and that plaintiff’s proposed use was not sand mining constituted palpable errors. Moreover, mandamus was precluded as a matter of law because the issuance of a land use permit is discretionary.

Subsequently, the court denied defendants’ motion for reconsideration. First, the court held that plaintiff’s claim was ripe for adjudication. An appeal to the ZBA would have futile because the issuance of the land use permit hinged on the property’s zoning classification and, under Section 23.02.06(a), the ZBA had no “power to alter or change the zoning district classification of any property.” Second, the court held that rezoning to PUD never occurred or expired because Section 1.03.04 states “[p]rior to establishing a PUD, all requirements of Article 10 must be complied with” and they were not. Further, to the extent the property was rezoned, the rezoning expired when plaintiff’s predecessor in interest failed to seek approval of its final PUD site plan within two years as set forth in Section 10.04.02. That is, “the property’s zoning had to have reverted back to Agricultural (AG), its original zoning.” Third, the court held that the issuance of the land use permit was ministerial because plaintiff’s proposed use did not violate any zoning ordinance and, thus, plaintiff was legally entitled to the permit. And, finally, the court held that plaintiff was not engaged in a commercial sand mining operation; rather, the removal of sand was temporary in nature and for the purpose of expanding a pond. This appeal followed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lansing Schools Education Ass'n v. Lansing Board of Education
487 Mich. 349 (Michigan Supreme Court, 2010)
Goldstone v. Bloomfield Township Public Library
737 N.W.2d 476 (Michigan Supreme Court, 2007)
Carter v. Ann Arbor City Attorney
722 N.W.2d 243 (Michigan Court of Appeals, 2006)
Trojan v. Township of Taylor
91 N.W.2d 9 (Michigan Supreme Court, 1958)
Lake Angelo Associates v. Township of White Lake
498 N.W.2d 1 (Michigan Court of Appeals, 1993)
City of Huntington Woods v. City of Detroit
761 N.W.2d 127 (Michigan Court of Appeals, 2008)
Sun Communities v. Leroy Township
617 N.W.2d 42 (Michigan Court of Appeals, 2000)
Bloomfield Township v. Kane
839 N.W.2d 505 (Michigan Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Chestnut Development LLC v. Township of Genoa, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chestnut-development-llc-v-township-of-genoa-michctapp-2014.