Cherwell-Ralli, Inc. v. Rytman Grain Co.

433 A.2d 984, 180 Conn. 714, 1980 Conn. LEXIS 806
CourtSupreme Court of Connecticut
DecidedMay 20, 1980
StatusPublished
Cited by19 cases

This text of 433 A.2d 984 (Cherwell-Ralli, Inc. v. Rytman Grain Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cherwell-Ralli, Inc. v. Rytman Grain Co., 433 A.2d 984, 180 Conn. 714, 1980 Conn. LEXIS 806 (Colo. 1980).

Opinion

Peters, J.

This case involves a dispute about which of the parties to an oral instalment contract was the first to be in breach. The plaintiff, Cherwell-Ralli, Inc., sued the defendant, Rytman Grain Co., Inc., for the nonpayment of moneys due and owing for accepted deliveries of products known as Cherco Meal and C-R-T Meal. The defendant, conceding its indebtedness, counterclaimed for damages arising out of the plaintiff’s refusal to deliver remaining instalments under the contract. The trial court, Bor don, J., trial referee, having found all issues for the plaintiff, rendered judgment accordingly, and the defendant appealed.

The trial court’s unchallenged finding of fact establishes the following: The parties, on July 26, 1974, entered into an instalment contract for the sale of Cherco Meal and C-R-T Meal on the basis of a memorandum executed by the Getkin Brokerage House. As modified, the contract called for shipments according to weekly instructions from the buyer, with payments to be made within ten days after delivery. Almost immediately the buyer was behind in its payments, and these arrearages were often quite substantial. The seller repeatedly called these arrearages to the buyer’s attention but continued to make all shipments as requested by the buyer from July 29, 1974, to April 23, 1975.

By April 15, 1975, the buyer had become concerned that the seller might not complete performance of the contract, because the seller’s plant might [716]*716close and because the market price of the goods had come significantly to exceed the contract price. In a telephonic conversation between the buyer’s president and the seller’s president on that day, the buyer was assured by the seller that deliveries would continue if the buyer would make the payments for -which it was obligated. Thereupon, the buyer sent the seller a check in the amount of $9825.60 to cover shipments through March 31,1975.

Several days later, on April 23, 1975, the buyer stopped payment on this check because he was told by a truck driver, not employed by the seller, that this shipment would be his last load. The trial court found that this was not a valid reason for stoppage of payment. Upon inquiry by the seller, the buyer restated his earlier concerns about future deliveries. Two letters, both dated April 28, 1975, describe the impasse between the parties: the seller again demanded payment, and the buyer, for the first time in writing, demanded adequate assurance of further deliveries. The buyer’s demand for assurance was reiterated in its direct reply to the seller’s demand for payment. The buyer, however, made no further payments, either to replace the stopped check or otherwise to pay for the nineteen accepted shipments for which balances were outstanding. The seller made no further deliveries after April 23, 1975, when it heard about the stopped check; the buyer never made specific requests for shipments after that date. Inability to deliver the goods forced the seller to close its plant, on May 2, 1975, because of stockpiling of excess material.

The trial court concluded, on the basis of these facts, that the party in breach was the buyer and not the seller. The court concluded that the seller [717]*717was entitled to recover the final balance of $21,013.60, which both parties agreed to be dne and owing. It concluded that the buyer could not prevail on its counterclaim because it had no reasonable grounds to doubt performance from the seller and had in fact received reasonable assurances. Further, the buyer had presented no reasonably accurate evidence to establish the damages it might have sustained because of the seller’s failure to deliver.

The buyer on this appeal challenges first the conclusion that the buyer’s failure to pay “substantially impaired the value of the whole contract” so as to constitute “a breach of the whole contract,” as is required by the applicable law governing instalment contracts. General Statutes §42a-2-612 (3).1 What constitutes impairment of the value of the whole contract is a question of fact. Graulich Caterer, Inc. v. Holterbosch, Inc., 101 N.J. Super. 61, 75, 243 A.2d 253 (1968); Holiday Mfg. Co. v. B.A.S.F. Systems, Inc., 380 F. Sup. 1096, 1102 (D. Neb. 1974). The record below amply sustains the trial court’s conclusion in this regard, particularly in light of the undenied and uncured stoppage of a check given to comply with the buyer’s promise to reduce significantly the amount of its outstanding arrearages. See Frigiking, Inc. v. Century Tire & Sales Co., 452 F. Sup. 935, 933 (N.D. Tex. 1978).

[718]*718The buyer argues that the seller in an instalment contract may never terminate a contract, despite repeated default in payment by the buyer, without first invoking the insecurity methodology of General Statutes § 42a-2-609.2 That is not the law. If there is reasonable doubt about whether the buyer’s default is substantial, the seller may be well advised to temporize by suspending further performance until it can ascertain whether the buyer is able to offer adequate assurance of future payments. Kunian v. Development Corporation of America, 165 Conn. 300, 312, 334 A.2d 427 (1973); Dangerfield v. Markel, 252 N.W.2d 184, 192-93 (N.D. 1977). But if the buyer’s conduct is sufficiently egregious, such conduct will, in and of itself, constitute substantial impairment of the value of the whole contract and a present breach of the contract as a whole. An aggrieved seller is expressly permitted, by General Statutes § 42a-2-703 (f),3 upon breach of a contract [719]*719as a whole, to cancel the remainder of the contract “with respect to the whole undelivered balance.” See Frigiking, Inc. v. Century Tire & Sales Co., supra. Nor is the seller’s remedy to cancel waived, as the buyer argues, by a law suit seeking recovery for payments due. While § 42a-2-61.2 (3) states that a contract is reinstated if the seller “brings an action with respect only to past instalments” (emphasis added), it is clear in this case that the seller intended, as the buyer well knew, to bring this contract to an end because of the buyer’s breach.

The buyer’s attack on the court’s conclusions with respect to its counterclaim is equally unavailing. The buyer’s principal argument is that the seller was obligated, on pain of default, to provide assurance of its further performance. The right to such assurance is premised on reasonable grounds for insecurity. Whether a buyer has reasonable grounds to be insecure is a question of fact. AMF, Inc. v. McDonald’s Corporation, 536 F.2d 1167, 1170 (7th Cir. 1976). The trial court concluded that in this case the buyer’s insecurity was not reasonable and we agree. A party to a sales contract may not suspend performance of its own for which it has “already received the agreed return.” At all times, the buyer had received all of the goods which it had [720]*720ordered. The buyer could not rely on its own nonpayments as a basis for its own insecurity.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson Industries v. Thermal Intelligence
2025 S.D. 47 (South Dakota Supreme Court, 2025)
Simkins Industries v. Standard Group, No. X01 Cv 00 0165315 S (Jun. 5, 2002)
2002 Conn. Super. Ct. 7213 (Connecticut Superior Court, 2002)
Cargill, Inc. v. Storms Agri Enterprises, Inc.
878 S.W.2d 786 (Court of Appeals of Arkansas, 1994)
Roessler v. New England Glass Enc. Inc., No. Cv 90 0108712 (Jan. 7, 1993)
1993 Conn. Super. Ct. 834 (Connecticut Superior Court, 1993)
S & S, INC. v. Meyer
478 N.W.2d 857 (Court of Appeals of Iowa, 1991)
County Fire Door Corp. v. C. F. Wooding Co.
520 A.2d 1028 (Supreme Court of Connecticut, 1987)
Stinnes Interoil, Inc. v. Apex Oil Co.
604 F. Supp. 978 (S.D. New York, 1985)
Glennville Elevators, Inc. v. Beard
326 S.E.2d 185 (Court of Appeals of South Carolina, 1985)
Clem Perrin Marine Towing, Inc. v. Panama Canal Co.
730 F.2d 186 (Fifth Circuit, 1984)
Conference Center Ltd. v. TRC—The Research Corp.
455 A.2d 857 (Supreme Court of Connecticut, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
433 A.2d 984, 180 Conn. 714, 1980 Conn. LEXIS 806, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cherwell-ralli-inc-v-rytman-grain-co-conn-1980.