Cheek v. Clay Bulloch Construction, Inc.

2011 UT App 418, 269 P.3d 964, 697 Utah Adv. Rep. 30, 2011 Utah App. LEXIS 420, 2011 WL 6091676
CourtCourt of Appeals of Utah
DecidedDecember 8, 2011
DocketNo. 20100479-CA
StatusPublished
Cited by8 cases

This text of 2011 UT App 418 (Cheek v. Clay Bulloch Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cheek v. Clay Bulloch Construction, Inc., 2011 UT App 418, 269 P.3d 964, 697 Utah Adv. Rep. 30, 2011 Utah App. LEXIS 420, 2011 WL 6091676 (Utah Ct. App. 2011).

Opinion

MEMORANDUM DECISION

ORME, Judge:

1 1 We are asked to reverse a dismissal for failure to prosecute. The dispute between plaintiff Dennis Cheek and defendants Clay Bulloch Construction, Inc. and Clay Bulloch {collectively, Bulloch) arose over alleged breaches of a construction contract in 2008. Cheek's claims of breach were twofold: first, that Bulloch erected the building partly on another's property, and second, that Bulloch defectively constructed the building. Bulloch counterclaimed, seeking to foreclose its me-chanie's lien on the property and also claiming breach of contract and unjust enrichment for Cheek's failure to pay all amounts allegedly due to Bulloch.

T2 Over the next six-and-a-half years, some initial discovery was done, followed by several years of unproductive correspondence between the parties' counsel. In its dismissal ruling, the trial court identified in detail what this communication and discovery entailed. Pertinent to this appeal was a relatively productive discovery period lasting from June 2003, when Cheek filed his complaint, through January 2005, followed by very little progress, at least as documented in the court's file, for the next five years.

18 At the beginning of this five-year period, in March 2005, the trial court asked Cheek to prepare a scheduling order, which Cheek-then represented by counsel who later withdrew-failed to do even after the court reminded Cheek of his responsibility in both June and November of that same year. In April 2006, the parties agreed to submit a discovery plan to the court, which also never happened. In July and August of 2006, Cheek's new counsel attempted to contact Bulloch's attorney several times with no sue-cess. After these failed attempts, Cheek's counsel began discussing a possible settlement of the case with Bulloch's insurance company.

T4 Cheek's counsel's communication with the insurance company and with Bulloch's counsel continued throughout 2007 and 2008. In October 2008, Cheek's counsel mailed a motion for a scheduling and case management conference to Bulloch's counsel. However, this motion was never filed with the court, and the parties never followed through on it. Counsel for the parties then agreed to meet in December 2008, but the meeting was subsequently canceled.

15 Nothing else of significance happened in this case until November 2009, when, at the instance of Cheek's counsel, the attorneys for the parties met and inspected the property. They discussed a plan for proceeding and agreed to communicate again in a few weeks. In light of these developments, Cheek's counsel was surprised when, in December 2009, Bulloch's counsel informed him during a phone call of his intention to move for dismissal for failure to prosecute. Bul-loch's counsel followed up his phone call with a letter repeating this intention. On January 7, 2010, Cheek filed a motion for a scheduling conference. Bulloch filed its motion to dismiss eight days later. The court granted the dismissal motion, and Cheek appeals the ruling.

16 Cheek argues for a standard of review that would essentially allow this court to review the trial court's decision de novo. However, "[iJn reviewing a trial court's decision to dismiss for failure to prosecute, we accord the trial court broad discretion and do not disturb its decision absent an abuse of discretion and a likelihood that an injustice has occurred." Hartford Leasing Corp. v. State, 888 P.2d 694, 697 (Utah Ct.App.1994), cert. denied, 899 P.2d 1231 (Utah 1995). See also Charlie Brown Constr. Co. v. Leisure [967]*967Sports, Inc., 740 P.2d 1368, 1370 (Utah Ct.App.), cert. denied, 765 P.2d 1277 (Utah 1987). Further, "(iln determining whether the court abused its discretion, we 'balance the need to expedite litigation and efficiently utilize judicial resources with the need to allow parties to have their day in court.'" Hartford Leasing, 888 P.2d at 697 (quoting Meadow Fresh Farms, Inc. v. Utah State Univ., 813 P.2d 1216, 1219 (Utah Ct.App.1991)). Thus, we review for abuse of discretion the trial court's decision to dismiss for failure to prosecute. See id.

T7 In analyzing whether a trial court has abused its discretion in dismissing a case for failure to prosecute, we use the five Westinghouse factors, which are

(1) the conduct of both parties; (2) the opportunity each party has had to move the case forward; (3) what each party has done to move the case forward; (4) the amount of difficulty or prejudice that may have been caused to the other side; and (5) "most important, whether injustice may result from the dismissal."

Meadow Fresh Farms, 813 P2d at 1219 (quoting Westinghouse Elec. Supply Co. v. Paul W. Larsen Contractor, Inc., 544 P.2d 876, 879 (Utah 1975)). Cheek contends that the trial court improperly applied these five factors to the facts of this case. We do not agree with all of Cheek's analysis, but we do agree that, taking the five Westinghouse factors together, the trial court exceeded its discretion in dismissing the case.

18 First, we consider the extent to which Westinghouse requires a court to take into account the actions of both parties. Cheek is correct that in considering a motion to dismiss for failure to prosecute, Westinghouse suggests that the conduct of both parties is germane. However, we have held that the plaintiff bears the primary responsibility for advancing the case and that the defendant's responsibility in this area "is limited." Hartford Leasing, 888 P.2d at 699. Further, "(allthough inaction on the part of a defendant may contribute to the justifiability of a plaintiff's excuse for delay, the duty to prosecute is a duty of due diligence imposed on a plaintiff, not on a defendant." Country Meadows Convalescent Ctr. v. Utah Dep't of Health, 851 P.2d 1212, 1216 (Utah Ct.App.1993). We previously referred to this concept as "the obvious" in explaining:

What each party has done to move the case forward can only be evaluated in light of each party's responsibility concerning the case. Of course, the plaintiff, as the party initiating the lawsuit, has the primary responsibility to move the case forward. The defendant's responsibility is limited to responding timely to the action, expeditiously attending to discovery, and moving any counterclaim along. The defendant has no general responsibility to move plaintiff's action to judgment.

Hartford Leasing, 888 P.2d at 698 n. 2 (emphasis in original). Ultimately what this means is that inaction by the defendant to move the plaintiff's claim along is irrelevant unless that inaction constitutes some actual hindrance, i.e., where the plaintiff can show that the defendant's inaction "contributed to [the plaintiff's] own delays." PDC Consulting, Inc. v. Porter, 2008 UT App 372, ¶ 10, 196 P.3d 626.

19 Certainly the analysis is a bit different where the defendant has filed a significant counterclaim and therefore bears plaintiff-like responsibility for prosecuting its counterclaim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Plantations at Haywood 1 v. Cottonwood Residential
2023 UT App 7 (Court of Appeals of Utah, 2023)
CBS Enterprises v. Sorenson
2018 UT App 2 (Court of Appeals of Utah, 2018)
Cheek v. Clay Bulloch Construction Inc.
2016 UT App 227 (Court of Appeals of Utah, 2016)
Bryner v. Custodian of Records
2016 UT App 40 (Court of Appeals of Utah, 2016)
Finlayson v. State
2015 UT App 31 (Court of Appeals of Utah, 2015)
R.O.A. General, Inc. v. Chung Ji Dai
2014 UT App 124 (Court of Appeals of Utah, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2011 UT App 418, 269 P.3d 964, 697 Utah Adv. Rep. 30, 2011 Utah App. LEXIS 420, 2011 WL 6091676, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cheek-v-clay-bulloch-construction-inc-utahctapp-2011.