Charles River Park, Inc. v. Boston Redevelopment Authority

557 N.E.2d 20, 28 Mass. App. Ct. 795, 1990 Mass. App. LEXIS 358
CourtMassachusetts Appeals Court
DecidedJuly 10, 1990
Docket88-P-1008
StatusPublished
Cited by28 cases

This text of 557 N.E.2d 20 (Charles River Park, Inc. v. Boston Redevelopment Authority) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charles River Park, Inc. v. Boston Redevelopment Authority, 557 N.E.2d 20, 28 Mass. App. Ct. 795, 1990 Mass. App. LEXIS 358 (Mass. Ct. App. 1990).

Opinion

Brown, J.

In this action for specific performance, Charles River Park, Inc. (“CRP”), claims the right to develop the last remaining undeveloped parcel of land in the West End Land Assembly and Redevelopment Project, an urban renewal project. The case is before this court on a report by a judge of the Superior Court of a grant of summary judgment in favor of CRP and against the Boston Redevelopment Authority (“BRA”), the moving party. Upon review of the entire record, we conclude that the judge erred and that summary judgment.should have been granted to the BRA. 1

1. Background. 2 The parcel in question, now referred to as Area E, is a portion of what was originally designated as par *797 cel IE, one of seven parcels of land which CRP was to lease and develop, under a master leasehold agreement (“MLA”), executed March 2, 1960, between CRP and the BRA. 3 *3 The land was to be developed in accordance with the West End Land Assembly and Redevelopment Plan (the “West End Plan”), first drawn up in 1956 and revised in 1959. CRP was designated developer in 1957.

Unlike the usual agreement to lease with an option to purchase, the MLA had as a primary purpose not simply an exchange of property for money but also a public goal: the redevelopment of land in an urban renewal area in accordance with a redevelopment plan drawn up by a public agency, here the BRA.

Under the schedule set out in § 204(b) of the MLA, the final two parcels, Parcels IF and IE, were originally scheduled for conveyance to CRP by March 7, 1964, and March 7, 1965, respectively. Various factors, however, contributed to delay in transferring these last two parcels. Two of those factors were the proposed taking of 40,000 square feet from Parcel IF and the subsequent requests (in November, 1962, and October, 1963) by CRP, pursuant to § 801 of the MLA, to add Parcel 2 4 to Parcels IE and IF to offset the loss of area from Parcel IF. According to letters sent to the BRA by CRP, those changes required a redrawing of the boundary lines of Parcels IE and IF and apparently necessitated revisions of the site plans for the parcels in question. As a result *798 of ongoing uncertainty over the boundaries of the parcels, CRP did not submit revised site plans in 1965.

In March, 1966, a new architect took the place of the original architect, whom CRP had discharged. A May, 1966, BRA status report stated that CRP had been informed that the boundaries of Parcels IE and IF would be revised to include the 40,000 square foot area and Parcel 2 and that CRP had been advised to prepare a new site plan for the parcels as revised. On June 11, 1968, the Boston public facilities commission voted to release Parcel 2 to the BRA for development, and the BRA board then voted, on June 20, 1968, to include Parcel 2 in Parcels IE and IF for development by CRP. 5

CRP submitted revised site plans for Parcels IE, IF, and 2 in 1966, 1967, and 1968. None of the plans submitted, however, complied with the land use restriction (multifamily residential) for Parcels IE and IF set out in the West End Plan: the proposed plans submitted by CRP all included commercial and recreational as well as residential uses. 6 In October, 1967, the BRA executive director wrote Mr. Jerome Rap-paport, counsel for CRP, stating that the board had instructed him to inform CRP “to comply with the land use controls in the . . . Plan with respect to Parcels IE and IF, namely, that these two parcels are restricted to residential use only.”

On June 20, 1968, the BRA voted “to approve the preliminary plans of [CRP] . . ., subject to later review on specific variances that may be required and subject to the review of the final plans by the [d]esign [r]eview [o]ffice.” 7 At the *799 same meeting, the BRA rejected a request by CRP for immediate delivery of Parcels IE and IF. 8 CRP continued to submit plans with nonresidential components. On August 22, 1968, CRP’s architect submitted to the BRA director of urban design two proposals for the project which included, in addition to residential towers, a five-story office building. Further plans were submitted in May, 1969.

In June, 1969, CRP submitted revised general plans for Parcels IE, IF, and 2. In a cover letter accompanying the June, 1969, submission which referred to the possible adoption by the BRA board of variances and revisions, CRP requested that a proposed third residential tower shown on the plans be made optional. In a letter sent to CRP in response, counsel representing the BRA requested “a clear and unequivocal answer” to the question whether CRP would agree either to construct all three residential towers within a specified time or, if not, to construct the two towers and have excluded from the land conveyed to CRP the portion allocated to the third tower. CRP’s response, which could not be termed unequivocal, stated, e.g., “we obviously hope and expect to be able to build the third tower. ... We are merely requesting the right not to go forward with it.”

*800 On July 31, 1969, the BRA board adopted a resolution to amend the West End Plan to change the land use restrictions for Parcels IE, IF, and 2 to multifamily residential with complementary commercial and recreational uses, conditional upon the execution by CRP by August 15, 1969, of an attached amendment to the MLA which would have (1) set a schedule for submission of plans and commencement of construction, (2) provided that if CRP failed to construct the third residential tower it would reconvey that portion of the land to the BRA, and (3) increased the purchase price for the portion of the parcel to be used for a proposed office building. The resolution accompanying the vote noted that § 204(e) of the MLA directed that the parties make their best efforts to speed the schedule of commencement of the lease terms in order to achieve early completion; that change of circumstance had “operated to decelerate the schedule of commencement of the lease terms for . . . IE and IF,” the change of circumstance being CRP’s October, 1963, request to add Parcel 2 to Parcels IE and IF and the resulting negotiations with other parties; that the BRA had voted on June 20, 1968, to include Parcel 2 with IE and IF; that CRP’s obligation to construct on Parcels IE and IF in accordance with the plans approved in 1960 was not implemented because of the aforementioned change in circumstance; that it was now feasible and desirable to amend the West End Plan; and that the BRA wished to proceed expeditiously based on the “concept of the preliminary plans submitted” by CRP. CRP did not execute the proposed amendment to the MLA.

On August 18, 1969, CRP again submitted proposed site plans calling for three residential towers, an office building, shops, a parking garage, and townhouses.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M.K.C. v. K.G.C.
Massachusetts Appeals Court, 2024
McClain v. Cape Air
D. Massachusetts, 2023
Dalrymple v. Town of Winthrop
Massachusetts Appeals Court, 2020
Limoliner, Inc. v. Dattco, Inc.
809 F.3d 33 (First Circuit, 2015)
B. Thomas Heinzer Associates, Inc. v. Xarras
2010 Mass. App. Div. 218 (Mass. Dist. Ct., App. Div., 2010)
Coviello v. Richardson
924 N.E.2d 761 (Massachusetts Appeals Court, 2010)
Frankston v. Ferme
2007 Mass. App. Div. 203 (Mass. Dist. Ct., App. Div., 2007)
Hoppe v. CMGI, Inc.
20 Mass. L. Rptr. 207 (Massachusetts Superior Court, 2005)
Arno v. Arbella Mutual Insurance
20 Mass. L. Rptr. 108 (Massachusetts Superior Court, 2005)
Town of Franklin v. Wyllie
819 N.E.2d 943 (Massachusetts Supreme Judicial Court, 2005)
Micromuse, Inc. v. MICROMUSE, PLC
304 F. Supp. 2d 202 (D. Massachusetts, 2004)
Bay Colony Systems, Inc. v. Judson
15 Mass. L. Rptr. 579 (Massachusetts Superior Court, 2002)
Cabot v. Cabot
774 N.E.2d 1113 (Massachusetts Appeals Court, 2002)
Hills v. Chambers
12 Mass. L. Rptr. 75 (Massachusetts Superior Court, 2000)
Borges v. Sterling Suffolk Racecourse, Inc.
11 Mass. L. Rptr. 668 (Massachusetts Superior Court, 2000)
Dominic Gentile Painting Co. v. Aulson Co.
2000 Mass. App. Div. 19 (Mass. Dist. Ct., App. Div., 2000)
Newburyport Redevelopment Authority v. Newburyport Inn Ltd. Partnership
9 Mass. L. Rptr. 683 (Massachusetts Superior Court, 1999)
Rizika v. Donovan
695 N.E.2d 1097 (Massachusetts Appeals Court, 1998)
Davis v. Dawson, Inc.
15 F. Supp. 2d 64 (D. Massachusetts, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
557 N.E.2d 20, 28 Mass. App. Ct. 795, 1990 Mass. App. LEXIS 358, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charles-river-park-inc-v-boston-redevelopment-authority-massappct-1990.