Chadd v. Midwest Franchise Corp.

412 N.W.2d 453, 226 Neb. 502, 1987 Neb. LEXIS 1021
CourtNebraska Supreme Court
DecidedSeptember 18, 1987
Docket85-840
StatusPublished
Cited by84 cases

This text of 412 N.W.2d 453 (Chadd v. Midwest Franchise Corp.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Chadd v. Midwest Franchise Corp., 412 N.W.2d 453, 226 Neb. 502, 1987 Neb. LEXIS 1021 (Neb. 1987).

Opinion

White, J.

Noel L. and Gloria J. Chadd appeal from an order of the Douglas County District Court sustaining Midwest Franchise Corp.’s motion for summary judgment.

This case arises out of a contract dispute between the Chadds and the appellee, Midwest Franchise Corp., a Nebraska corporation. Evidence was received by the district court in support of and in opposition to a motion for summary judgment. Taking a version most favorable to the appellants, the facts appear to be as follows. After some preliminary negotiations the parties executed a document entitled “Lease Agreement” on May 9, 1979. Chadds agreed to lease their land and a building, to be constructed, to Midwest. The building was to be used as a Bonanza restaurant. Chadds were to erect a *504 building, or subcontract the construction, in accordance with plans and specifications provided by Midwest. Chadds were responsible for obtaining bids (including a bid by Chadds themselves) and submitting the same to Midwest for its approval.

The facts are in dispute as to the problems which arose after the lease agreement was executed. Apparently, Chadds were furnished with a standard Bonanza building floor plan, the B-76 plan, which originated from Bonanza International in Dallas, Texas. Midwest made a decision to alter the B-76 plan for the Nebraska area. At least in part, the dispute in this case involves difficulties surrounding the acquisition of final plans for the purpose of an accurate construction bid.

Noel Chadd alleges that he was unable to obtain a complete working set of drawings required for an accurate bid. He notified the principals of Midwest, Larry Miller and Charles Shada, of this problem on several occasions. Both Miller and Shada admit that there had been considerable problems in obtaining final plans from Midwest’s architect. Shada, however, believed that Chadd eventually received a complete, final set of plans from the architect. Chadd alleges that he never received an acceptable set of plans and specifications.

Chadds solicited one bid from Belmont Construction Company based on incomplete plans. They did not advertise generally for the bids, nor submit a bid themselves, because they were waiting for a resolution to the problem with the drawings. The one bid which Chadds received was above the estimated cost of construction set forth in the lease agreement. However, that cost apparently could have been reduced if modifications were allowed, and that would not be known without a final set of plans.

On or about August 22, 1979, Noel Chadd received a letter from Midwest which indicated Midwest’s desire to rescind the lease agreement. In addition, on August 15, 1979, Chadd was informed by another landowner, Bill Lesoing, that Midwest had been negotiating with Lesoing and that it had signed a contract with him. Apparently, Midwest had been negotiating the Bonanza construction project with two other landowners besides Chadds. All three parcels of land were in close *505 proximity.

Chadds concluded the agreement with Midwest was breached as of August 22, 1979. The evidence is ambiguous, at best, as to Midwest’s intention when it sent the attempted rescission letter. Operating under the assumption that the agreement was not going to materialize, Chadds began to explore other options for their land. Eventually, the Chadds conveyed the land to other parties by executing a joint tenancy warranty deed on July 26,1983.

The district court, following the words of Neb. Rev. Stat. § 25-1332 (Reissue 1985), found that there were no genuine issues of material fact and that Midwest was entitled to judgment as a matter of law. The court’s order did not elaborate as to the basis for its decision. This court was compelled to search the record and examine every conceivable issue which might have been the deciding factor for the lower court’s determination.

Summary judgment is an extreme remedy and should be awarded only when the issue is clear beyond all doubt. Cornhusker Agrl. Assn. v. Equitable Gen. Ins. Co., 223 Neb. 618, 392 N.W.2d 366 (1986). Summary judgment is proper when the pleadings, depositions, admissions, stipulations, and affidavits in the record disclose that there is no genuine issue as to any material fact or as to the ultimate inferences that may be drawn from material facts, and when the moving party is entitled to judgment as a matter of law. In re Estate of Thompson, 225 Neb. 643, 407 N.W.2d 738 (1987). The burden is on the moving party to show that no issues of material fact exist, and unless the party can conclusively do so, the motion must be overruled. Schrodt v. Sullivan Transfer & Storage Co., 222 Neb. 347, 383 N.W.2d 767 (1986). Summary judgment is not appropriate, even where there are no conflicting evidentiary facts, if the ultimate inferences to be drawn from those facts are not clear. Id. In considering a motion for summary judgment, the evidence is to be viewed in the light most favorable to the party against whom the motion is directed, giving to that party the benefit of all reasonable inferences which may be drawn from the evidence. In re Estate of Thompson, supra.

*506 The first issue that must be addressed in this action is whether there was an enforceable contract under which the appellants could recover. A lease is to be construed as any other contract. Omaha Country Club v. Dworak, 186 Neb. 336, 183 N.W.2d 264 (1971). The proper construction of a written contract is generally a question of law to be determined by the courts. Dockendorf v. Orner, 206 Neb. 456, 293 N.W.2d 395 (1980).

Of particular concern in this action is whether, as a matter of law, paragraph 3 of the lease agreement negates the enforceability of the instrument. Paragraph 3 states in part:

3. CONSTRUCTION. Upon execution of this Lease, Owners [Chadds] shall proceed to obtain bids (including a bid by Owners) for the construction of the building in accordance with the attached plans and specifications which have been prepared and approved by Tenant [Midwest]. Upon Owners’ acceptance and approval of a construction bid, the same shall be submitted to Tenant for acceptance and approval. It is estimated that the cost of the building will be between $240,000 and $260,000.

(Emphasis supplied.)

Approval or satisfaction clauses such as that found in the highlighted language above often give rise to arguments that the agreement is too vague or illusory. An agreement which depends on the wish, will, or pleasure of one of the parties is unenforceable. De Los Santos v. Great Western Sugar Co., 217 Neb.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Acklie v. Greater Omaha Packing Co.
306 Neb. 108 (Nebraska Supreme Court, 2020)
TNT Cattle Co. v. Fife
304 Neb. 890 (Nebraska Supreme Court, 2020)
King v. Warner Pac. Coll., an Or. Corp.
437 P.3d 1172 (Court of Appeals of Oregon, 2019)
McKenzie v. Farmers Insurance Exchange
260 F. Supp. 3d 1150 (D. South Dakota, 2017)
GB Auctions, Inc. v. Private Ledger, Inc.
Court of Appeals of Washington, 2014
Weber v. North Loup River Pub. Power
288 Neb. 959 (Nebraska Supreme Court, 2014)
Digital Ally, Inc. v. Z3 Technology, LLC
754 F.3d 802 (Tenth Circuit, 2014)
Digital Ally, Inc. v. Z³ Technology, LLC
864 F. Supp. 2d 1050 (D. Kansas, 2012)
Strategic Staff Management, Inc. v. Roseland
619 N.W.2d 230 (Nebraska Supreme Court, 2000)
Sack Bros. v. Tri-Valley Cooperative, Inc.
616 N.W.2d 786 (Nebraska Supreme Court, 2000)
Radecki v. Mutual of Omaha Insurance
583 N.W.2d 320 (Nebraska Supreme Court, 1998)
ACME Investment, Inc. v. Southwest Tracor, Inc.
911 F. Supp. 1261 (D. Nebraska, 1995)
Pantano v. McGowan
530 N.W.2d 912 (Nebraska Supreme Court, 1995)
Bailey v. Farmers Union Co-operative Insurance
498 N.W.2d 591 (Nebraska Court of Appeals, 1992)
Bailey v. FARMERS UNION CO-OP. INS.
498 N.W.2d 591 (Nebraska Court of Appeals, 1992)
Donaldson v. Farm Bureau Life Insurance
440 N.W.2d 187 (Nebraska Supreme Court, 1989)
Frenzen v. Taylor
439 N.W.2d 473 (Nebraska Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
412 N.W.2d 453, 226 Neb. 502, 1987 Neb. LEXIS 1021, Counsel Stack Legal Research, https://law.counselstack.com/opinion/chadd-v-midwest-franchise-corp-neb-1987.