Anderson Excavating & Wrecking Co. v. Sanitary Improvement District No. 177

654 N.W.2d 376, 265 Neb. 61, 2002 Neb. LEXIS 244
CourtNebraska Supreme Court
DecidedDecember 27, 2002
DocketS-01-1178
StatusPublished
Cited by18 cases

This text of 654 N.W.2d 376 (Anderson Excavating & Wrecking Co. v. Sanitary Improvement District No. 177) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Anderson Excavating & Wrecking Co. v. Sanitary Improvement District No. 177, 654 N.W.2d 376, 265 Neb. 61, 2002 Neb. LEXIS 244 (Neb. 2002).

Opinion

Connolly, J.

Anderson Excavating & Wrecking Company (Anderson) appeals from an order of the district court finding that Anderson had repudiated a contract it entered into with Sanitary Improvement District No. 177 (SID) and determining that Anderson was not entitled to damages. We affirm because the court was not clearly wrong when it found that Anderson had repudiated the contract.

BACKGROUND

In 1992, the SID sought bids for a seawall construction and dredging project at Riverside Lakes, which consists of residential property and adjoining manmade lakes. The project involved erecting seawalls around three islands in a boating lake and dredging the lake to make it more uniform in depth. The plans for the project were designed by an engineering firm, Lamp, Rynearson & Associates, Inc. (Lamp). The plans called for the dredged material to be disposed of on the three islands.

After receiving bids, the SID split the project into two contracts and phases of work. Phase I of the project involved the construction of the seawalls and was awarded to Big River Construction. Anderson was awarded phase II of the project, which involved the dredging of the lake. Anderson was concerned before the contract was signed that the seawalls would not be able to hold the weight of the dredged material. Anderson entered into the contract, however, and obtained a performance bond and insurance. The “Special Conditions” portion of the contract documents between the SID and Anderson provided in part:

The CONTRACTOR shall excavate the existing lake by means of hydraulic dredge and shall dispose of the excavated material on the islands in the lake. . . .
*63 The dredged material shall be distributed on the islands in a manner to provide a generally smooth mounded surface capable of providing a seed bed. Trees do not have to be removed and lower vegetation can be buried in the fill.. . . Placement of dredged materials shall be done in such a manner as to provide a safe ledge at the seawall. Excess material surcharging the seawall shall be promptly removed and all damage to the seawall repaired by dredging contractor.
The CONTRACTOR shall report to the ENGINEER the location and extent of all obstructions to dredging encountered, at which time a change order will be prepared for removal thereof if additional work is determined to be advisable. . . . Obstructions shall be considered materials exceeding five (5) inches in diameter.

The “Agreement” portion of the contract documents provided:

The CONTRACTOR for the Seawall Construction shall commence work on the seawall within thirty (30) days after Notice of Award and shall complete the seawall on one island within twenty (20) working days. All seawall construction shall be completed by April 30, 1993. The CONTRACTOR for the lake dredging shall commence operations immediately upon completion of the seawall on the first island and shall complete all dredging and seeding operations on or before May 28, 1993.

There were delays in the progress of Big River Construction’s work. Thus, on April 16, 1993, Lamp issued a change order which modified the contract to read: “The CONTRACTOR for the lake dredging shall commence operation after September 7, 1993, and shall complete all dredging and seeding operations on or before May 1, 1994.” The “Supplementary Conditions” portion of the contract documents provided that “[t]he Contract Times will commence to run on the day indicated in the Notice to Proceed. In no event will the Notice to Proceed be issued later than six months after the Bid opening.”

The record shows that in the normal course of construction business, a “notice to proceed” is sent to a contractor to formally notify the contractor to commence work. Anderson was never sent *64 a “notice to proceed,” nor was it sent a notice that the contract had been terminated. Anderson also provided evidence that a notice to proceed is different from a change order. The SID, however, presented evidence that the change order fulfilled the notice-to-proceed requirement in the contract because it set a date fixing the date on which work would begin under the contract.

A dispute arose between Anderson and the SID about Anderson’s ability to place the dredged material on the islands. According to Steven Braithwaite, Anderson’s project manager, the islands were rounded on top and any material placed there would run off into the lake. Because the contract would hold Anderson liable for excess material surcharging the seawalls and for damage to the seawalls, Braithwaite was concerned about exposing Anderson to liability. According to Otto Ludewig, an engineer at Lamp, his firm’s opinion was that the islands needed a “little bit of work” to flatten them out and that the addition of silt fences would allow the dredged material to be placed on the islands.

Anderson presented evidence that residents of the lake had complained about the possibility of depositing the dredged material on the islands and that the SID was looking for other sites for the material. Braithwaite testified that unless the island issue was resolved, there was nothing Anderson could do.

On August 16, 1993, Braithwaite sent a letter to Joel Bard, an engineer from Lamp, stating that Anderson had been assured in a meeting which had occurred during the past winter that the islands would be “bowled out in the middle” before Anderson commenced phase II and that this work had not been done. Braithwaite wrote that “it is not the responsibility of the dredger to prepare the islands for dredging materials. It is only the responsibility of the dredger to place the materials on the islands.” The letter indicated that Anderson considered the problem to be an obstruction to dredging under the contract.

On August 17, 1993, Bard responded that the problem was not an obstruction under the contract. He further wrote that he agreed that bowling out the islands was one way to prepare the islands for disposal of the dredged material but also wrote that “[wjhile we and the [SID] were agreeing that you and Big River could make some agreement as to how to prepare the islands for *65 your convenience, neither Big River [n]or the [SID] was obligated to perform such work.”

A meeting was held on August 19,1993, between Braithwaite, Bard, Ludewig, and a consultant of Anderson to discuss the problem. Three options were discussed at the meeting: (1) issuance of a change order to allow additional payment to Anderson, (2) termination of the contract without financial liability to either party, and (3) execution of the work by Anderson according to Anderson’s interpretation of the contract.

On August 24, 1993, Braithwaite wrote to Bard, stating:

To prepare the islands for placement of dredged materials will cost approximately $27,000.00. If the S.I.D. is prepared to issue a Change Order to that effect Anderson will begin as agreed. However, if the S.I.D. is unwilling to issue the Change Order, then there appears to be only two other alternatives.
First, they could rebid the dredging portion of the contract, and include the areas left unaddressed such as the island preparation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JDS So Cal, Ltd. v. Dept. of Natural Resources
2018 Ohio 1159 (Ohio Court of Appeals, 2018)
Darnall v. Parrish Project
Nebraska Court of Appeals, 2017
Beinstein v. Navani
131 A.D.3d 401 (Appellate Division of the Supreme Court of New York, 2015)
Weber v. North Loup River Pub. Power
288 Neb. 959 (Nebraska Supreme Court, 2014)
Stauffer v. Benson
288 Neb. 683 (Nebraska Supreme Court, 2014)
Digital Ally, Inc. v. Z³ Technology, LLC
864 F. Supp. 2d 1050 (D. Kansas, 2012)
Davenport Ltd. v. 75th & Dodge I
780 N.W.2d 416 (Nebraska Supreme Court, 2010)
Jackson v. BROTH. RELIEF & COMPEN. FUND
779 N.W.2d 589 (Nebraska Supreme Court, 2010)
Schiefelbein v. SCHOOL DIST. NO. 0013
758 N.W.2d 645 (Nebraska Court of Appeals, 2008)
MBH, INC. v. John Otte Oil & Propane, Inc.
727 N.W.2d 238 (Nebraska Court of Appeals, 2007)
Triple 7, Inc. v. Intervet, Inc.
338 F. Supp. 2d 1082 (D. Nebraska, 2004)
Par 3, Inc. v. Livingston
686 N.W.2d 369 (Nebraska Supreme Court, 2004)
Professional Business Services Co. v. Rosno
680 N.W.2d 176 (Nebraska Supreme Court, 2004)
Asbury Square, LLC v. Amoco Oil Co.
221 F.R.D. 497 (S.D. Iowa, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
654 N.W.2d 376, 265 Neb. 61, 2002 Neb. LEXIS 244, Counsel Stack Legal Research, https://law.counselstack.com/opinion/anderson-excavating-wrecking-co-v-sanitary-improvement-district-no-177-neb-2002.