Mallory Fire Protection Servs. v. McShane Constr. Co.

CourtNebraska Court of Appeals
DecidedOctober 3, 2017
DocketA-16-752
StatusPublished

This text of Mallory Fire Protection Servs. v. McShane Constr. Co. (Mallory Fire Protection Servs. v. McShane Constr. Co.) is published on Counsel Stack Legal Research, covering Nebraska Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mallory Fire Protection Servs. v. McShane Constr. Co., (Neb. Ct. App. 2017).

Opinion

IN THE NEBRASKA COURT OF APPEALS

MEMORANDUM OPINION AND JUDGMENT ON APPEAL (Memorandum Web Opinion)

MALLORY FIRE PROTECTION SERVS. V. MCSHANE CONSTR. CO.

NOTICE: THIS OPINION IS NOT DESIGNATED FOR PERMANENT PUBLICATION AND MAY NOT BE CITED EXCEPT AS PROVIDED BY NEB. CT. R. APP. P. § 2-102(E).

MALLORY FIRE PROTECTION SERVICES, INC., APPELLEE AND CROSS-APPELLANT, V.

MCSHANE CONSTRUCTION COMPANY, LLC, APPELLANT AND CROSS-APPELLEE.

Filed October 3, 2017. No. A-16-752.

Appeal from the District Court for Douglas County: KIMBERLY MILLER PANKONIN, Judge. Affirmed. David J. Koukol and Michael W. Milone, of Koukol & Johnson, L.L.C., for appellant John A. Svoboda, of Gross & Welch, P.C., L.L.O., for appellee.

MOORE, Chief Judge, and BISHOP and ARTERBURN, Judges. ARTERBURN, Judge. I. INTRODUCTION McShane Construction Company, LLC (McShane) appeals and Mallory Fire Protection Services, Inc. (Mallory), cross-appeals from an order entered by the district court after a bench trial which found in favor of McShane for its breach of contract claim, but also found that the contract was divisible and that Mallory had substantially performed under the contract. On appeal, McShane argues the district court erred in its construction and application of the contract, finding that it failed to prove a portion of its damages, dismissing its negligence claims, not admitting proper evidence, and finding that the contract was divisible and that Mallory substantially performed under the contract. On cross-appeal, Mallory argues the district court erred by failing to award damages for work it performed and failing to award prejudgment interest on the work it performed. For the reasons set forth below, we affirm.

-1- II. BACKGROUND McShane was the general contractor for the construction of the Springs at Legacy Commons Apartments (the Project). The Project involved the construction of a seven building apartment complex in Omaha, Nebraska. Mallory was the successful bidder for the fire suppression system subcontract on the Project. On June 8, 2012, McShane and Mallory entered into a subcontract agreement (Agreement) for the design and installation of a fire suppression system in each of the seven buildings. The Agreement provided that Mallory would be paid $345,000.00 for its costs and labor on the Project. A subsequent change order on February 5, 2013, increased the total payment by $28,565.00, for a total subcontract value of $373,565.00. The Agreement provided that Mallory would be paid by submitting a monthly estimate of the work completed pursuant to the General Conditions of Subcontract (General Conditions), which was incorporated into the Agreement. The General Conditions provided that McShane would only make payments to Mallory after McShane had received payments from the owner of the Project. The owner of the Project was not a party in this matter. The Agreement and General Conditions provided the time frame in which the Project needed to be completed and mandatory conditions Mallory must have met. The General Conditions included provisions that allowed McShane to withhold payments from Mallory if Mallory did not meet its contractual obligations. The construction of the Project began in summer 2012 and occurred sequentially, with work beginning on Building 1. Buildings 1-3 were completed by Mallory without issue. Building 1 received its certificate of occupancy, which is received when the building has passed its final inspection, on December 21, 2012. Building 2 received its certificate of occupancy on January 14, 2013, and Building 3 received its certificate of occupancy on March 1, 2013. Buildings 1-3 and 7 were classified under regulations published by the National Fire Protection Agency (NFPA) as NFPA-13R buildings. The NFPA governs the codes for fire sprinkler installation and at the time of this matter the City of Omaha had adopted the 2002 edition of the NFPA code. NFPA-13R buildings are designated as residential buildings. Buildings 4-6 in the Project were designated as NFPA-13 buildings. NFPA-13 buildings are designated as commercial buildings. The key differences between NFPA-13R and NFPA-13 buildings are: (1) NFPA-13 buildings require a sprinkler system in the attic of the building, and (2) NFPA-13 buildings require either a sprinkler system or complete insulation in the interstitial spaces of the building. Interstitial spaces are the areas between the ceiling of the lower level of a building and the framing of the next level of the building. In January 2013, issues with the Project began to arise while Mallory was working on Buildings 4 and 5. The Omaha Fire Department discovered that the interstitial spaces in Buildings 4 and 5 did not have sprinkler systems. The bid submitted by Mallory included the installation of a sprinkler system in the interstitial spaces in Buildings 4-6. However, the design plans for Buildings 4-6 did not include sprinkler systems in the interstitial spaces. Mallory initially disputed whether they were responsible for the installation of the system in the interstitial spaces, but eventually agreed to remedy the problem. Mallory installed sprinklers in the interstitial spaces of Building 4 and had partially installed sprinklers in the spaces of Building 5 when McShane opted to fill the interstitial spaces with insulation in Buildings 4-6.

-2- The parties’ relationship further deteriorated between February and March 2013. Mallory submitted invoices to McShane for work performed, but McShane ceased paying the requested amounts. According to Mallory, they left the jobsite on March 8, 2013, because of non-payment. McShane signed a contract with another fire suppression company, Continental Fire Sprinkler Company (Continental), the day before Mallory left the jobsite. McShane contracted with Continental to examine, evaluate, repair, and complete the design and installation of the fire sprinkler systems in Buildings 4-7. Continental worked on the Project for approximately three weeks. Continental encountered issues with the use of Mallory’s designs, as well as deficiencies in the work completed by Mallory and submitted a new proposal to McShane to perform remedial measures and complete the Project. After receiving the new proposal, McShane determined that it would be best for both McShane and Mallory if Mallory could return to the jobsite to finish the Project. The issues encountered by Continental were substantial. Continental discovered that some of the pipes installed were not the size called for in the design plan. This had occurred within the walls of the buildings and in the attic spaces. Additionally, Continental discovered that the main risers in the buildings were not the correct size. The parties exchanged emails about Mallory returning to the Project in late March 2013. McShane requested that Mallory perform the necessary remedial work and to complete Buildings 4-6. McShane agreed that upon final inspection of the buildings, it would pay Mallory $130,604.54 for the completed work. Mallory agreed to provide the revised engineering plans to McShane before receiving payment, perform the remedial work, and complete the buildings. Mallory hired a new engineer, Craig Taschner, to redesign the installation plans for the buildings. Taschner’s new plans called for a major overhaul because he discovered the previous design plans were not NFPA compliant. Some of the installed pipe needed to be replaced, some locations required different sprinkler heads, and some units required an additional wall to hide the pipe feeding into the attic system. A few units with two-car garages needed to be converted into one-car garages with a fire door replacing the installed door. Additionally, the RPZ backflow prevention valve in the buildings needed to be removed and another prevention valve needed to be installed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Selig v. Wunderlich Contracting Company
69 N.W.2d 861 (Nebraska Supreme Court, 1955)
BSB CONST., INC. v. Pinnacle Bank
776 N.W.2d 188 (Nebraska Supreme Court, 2009)
Gaspar v. Flott
307 N.W.2d 500 (Nebraska Supreme Court, 1981)
Shipler v. General Motors Corp.
710 N.W.2d 807 (Nebraska Court of Appeals, 2006)
HOUSTEIN TRUCKING v. Sandhills Beef, Inc.
308 N.W.2d 331 (Nebraska Supreme Court, 1981)
Dutton-Lainson Co. v. Continental Ins. Co.
778 N.W.2d 433 (Nebraska Supreme Court, 2010)
Archbold v. Reifenrath
744 N.W.2d 701 (Nebraska Supreme Court, 2008)
Aon Consulting v. Midlands Financial
748 N.W.2d 626 (Nebraska Supreme Court, 2008)
Weber v. North Loup River Pub. Power
288 Neb. 959 (Nebraska Supreme Court, 2014)
Gibbons Ranches v. Bailey
289 Neb. 949 (Nebraska Supreme Court, 2015)
Marcuzzo v. Bank of the West
290 Neb. 809 (Nebraska Supreme Court, 2015)
Labenz v. Labenz
291 Neb. 455 (Nebraska Supreme Court, 2015)
Arens v. NEBCO, Inc.
291 Neb. 834 (Nebraska Supreme Court, 2015)
Roskop Dairy v. GEA Farm Tech.
292 Neb. 148 (Nebraska Supreme Court, 2015)
RM Campbell Indus. v. Midwest Renewable Energy
886 N.W.2d 240 (Nebraska Supreme Court, 2016)
Donut Holdings v. Risberg
885 N.W.2d 670 (Nebraska Supreme Court, 2016)
ACI Worldwide Corp. v. Baldwin Hackett & Meeks
296 Neb. 818 (Nebraska Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Mallory Fire Protection Servs. v. McShane Constr. Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/mallory-fire-protection-servs-v-mcshane-constr-co-nebctapp-2017.