CG Schmidt Inc. v. Permasteelisa North America

142 F. Supp. 3d 755, 87 U.C.C. Rep. Serv. 2d (West) 1184, 2015 U.S. Dist. LEXIS 144184, 2015 WL 6442634
CourtDistrict Court, E.D. Wisconsin
DecidedOctober 23, 2015
DocketCase No. 14-CV-1553-JPS
StatusPublished
Cited by2 cases

This text of 142 F. Supp. 3d 755 (CG Schmidt Inc. v. Permasteelisa North America) is published on Counsel Stack Legal Research, covering District Court, E.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CG Schmidt Inc. v. Permasteelisa North America, 142 F. Supp. 3d 755, 87 U.C.C. Rep. Serv. 2d (West) 1184, 2015 U.S. Dist. LEXIS 144184, 2015 WL 6442634 (E.D. Wis. 2015).

Opinion

ORDER

J.P. STADTMUELLER, District Judge.

On December 15, 2015, the plaintiff, CG Schmidt, Inc. (“CGS”), filed a breach of contract claim and promissory estoppel claim against the defendant, Permasteelisa North America (“PNA”). (Docket #1). The allegations in the complaint tell the classic trilogy of a general contractor and subcontractor relationship gone wrong: a bid, ensuing negotiations, and disengagement. PNA moved for summary judgment on both claims asserted against it on August 3, 2015. (Docket # 16).1 As will be discussed more fully below, the Court finds that the undisputed facts entitle PNA to judgment as a matter of law on both the breach of contract and promissory estop-pel claims. Thus, the Court will grant PNA’s motions for summary judgment.

1. BACKGROUND

The facts in this case are largely undisputed.2 CGS is a general contractor managing a portion of the construction of a [759]*759mixed-use, eighteen-story office building located at 833 East Michigan Street, Milwaukee, Wisconsin; a project valued at nearly $52 million. (Docket #18 ¶ 3; Docket # 24 Ex. 3 at 22:20-24, 70:17-18). PNA is part of an international conglomerate of subcontractors that participates in various architectural engineering projects, including the custom design, manufacture, and installation of unitized curtainwalls.3 (Docket # 19 at. 2; Docket # 24 Ex. 10 at 36:22-37:22). The following events took place over the course of approximately fourteen months, from April of 2013 through June of 2014. (Docket # 18 ¶¶ 10, 12, 77-79).

1.1. The Bid

The relationship between CGS and PNA began in April of 2013, when CGS began to solicit subcontractor bids for a custom cur-tainwall on its 833 East Michigan Street Project (the “Project”). (Docket # 18 ¶ 10; Docket # 22 ¶ 3). The curtainwall was slated to be one of the largest subcontracts for the development. (Docket # 18 ¶ 8). To guide the bidding process, CGS provided prospective subcontractors a number of documents, including its Contract Manual (the “Manual”) and a Draft Schedule. (Docket # 15 Ex. 1 at 3, 11; Docket # 18 ¶ 10; Docket # 22 ¶ 3). The Manual contained instructions to bidders on the logistics of bid submission, blank bid forms, work category descriptions, and numerous agreement forms, which included CGS’s blank, standard subcontract and exhibits. (Docket # 15 Ex. 1 at 13-14; Docket # 18 ¶ 10; Docket # 22 ¶ 3). In relevant part, the standard subcontract stated:-

The Contract between CGS and the Subcontractor includes all the terms and conditions of this Subcontract and its Exhibits ... and all the terms and conditions of the Agreement between CGS and the Project Owner (the “Prime Agreement”) ... applicable to the Subcontractor’s Work ... (collectively, the “Subcontract Documents”).4 The Subcontract Documents form the entire’ and integrated agreement between the parties and supersede all prior bidding, proposals, negotiations' and/or agreements, written or oral, between Subcontractor and CGS, except to the extent expressly referenced in these Subcontract Documents.

(Docket # 15 Ex. 1 at 74).

PNA submitted its bid to furnish, fabricate, and install a custom curtainwall for the Project on April 19, 2013. (Docket # 18 ¶ 11; Docket #15 Ex, 2). As instructed, PNA used the bid form provided in CGS’s Manual. (Docket # 15 Ex. 2). PNA’s legal team reviewed the bid, and PNA’s Senior Vice President, Michael Kneeland, signed it. (Docket #22 ¶¶9, 17). The bid stated, in relevant part:

The Bidder ... hereby proposes to furnish all labor, materials, tools, equipment ... and to construct all work in the Work Category in accordance with the Contract Drawings and Specifications ... and CG Schmidt Contract [760]*760Manual, dated March 22,2013 for the bid amount stated in this document— The Bidder, if awarded a contract, agrees to commence work and to fully complete this Work Category in accordance with a schedule to be established in collaboration with CG Schmidt....

(Docket # 15 Ex. 1 at 19). The bid added that, “[t]he Bidder agrees that his/her Base Bid shall be good and may not be withdrawn for a period of one hundred twenty (120) calendar days after the bid opening date.” (Docket # 15 Ex. 2 at 2).

CGS’s bid form also required PNA to submit information related to its price estimate, alternative fee proposals, insurance coverage, and resident-and race-based employment practices. (Docket # 15 Ex, 2 at 2-5). Attached to its bid, PNA, on its own letterhead, submitted a more detailed financial breakdown of its initial proposal for the eurtainwall project, which totaled $12,675,421.00. (Docket' # 15 Ex. 2 at 3). PNA likewise, outlined the “scope specifically included” in the eurtainwall, various warranties, site logistics, clarifications, and exclusions. (Docket # 15 Ex. 2 at 8-11). Within a “couple of months” from the submission of PNA’s bid, CGS selected PNA as its subcontractor of choice. (Docket # 18 ¶ 18; Docket # 24 Ex. 3 at 77:22-78:9). ' .

1.2 The Negotiations

Though CGS was “not prepared to write a subcontract” during the spring of 2013, it began “working towards a signed contract” with PNA “based on the award.” (Docket # 18 ¶ 19; Docket # 24 Ex. 3 at 79:18-80:6). The parties waited to sign a subcontract for two primary reasons.

First, CGS had not yet entered into two important agreements with the Project’s owner: the “prime contract” and an important corollary thereto, known as the Guaranteed Maximum- Price Amendment (“GMPA”).5 (Docket # 18 ¶¶ 27-28, 34-41; Docket # 22 ¶ 24). CGS followed industry practice insofar as it maintained a general policy of signing written agreements with all of its subcontractors. (Docket # 18 ¶ 2). But, it could not proceed to sign a contract with PNA until it signed the prime contract and GMPA.6 (Docket # 18 ¶ 34-41; Docket # 22 ¶¶ 1-3, 53; see also Docket # 24 Ex. 3 at 62:25-63:5). By the same token, CGS does not dispute that, as a general matter of good business practice, it does not execute Subcontracts until it first executes a prime contract with a project owner. (Docket # 18 ¶ 40).

Second, immediately after the award of the eurtainwall project to PNA, the parties actively engaged in refining various aspects of their agreement. (Docket #18 ¶¶ 12-15, 21-23, 46-48). CGS was particularly interested in reducing the proposal’s cost and, as a result, PNA issued a series of revised proposals in order to save CGS money. (Docket # 24 Ex. 3 at 31:7-32:12, 71:25-72:16). ‘ The specific requests made by CGS during this “valúe engineering process” primarily centered on cost-saving “alternate” ' materials and the proposed contract scope.7 (Docket # 18 ¶¶ .12-14; Docket # 24 Ex. 2 at 75:16-76:23).

[761]*761Beyond refining the financial aspect of their agreement, as early as May 10, 2013, PNA forwarded various comments (the “May 2013 email”) to CGS from its legal department about CGS’s standard subcontract. (Docket # 18 ¶ 15). Mr. John Stanko (“Stanko”)8 related that, “[b]e-cause we have not yet had an opportunity to review the prime contract, which is referenced in the subcontract,9 we do’ not believe it would be constructive to initiate discussion on the subcontract, but look forward to discussing the documents’ terms in the near future.” (Docket # 18 ¶ 15).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
142 F. Supp. 3d 755, 87 U.C.C. Rep. Serv. 2d (West) 1184, 2015 U.S. Dist. LEXIS 144184, 2015 WL 6442634, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cg-schmidt-inc-v-permasteelisa-north-america-wied-2015.