Centric-Jones Co. v. Hufnagel

848 P.2d 942, 17 Brief Times Rptr. 563, 1993 Colo. LEXIS 297, 1993 WL 88131
CourtSupreme Court of Colorado
DecidedMarch 29, 1993
Docket92SA407
StatusPublished
Cited by41 cases

This text of 848 P.2d 942 (Centric-Jones Co. v. Hufnagel) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Centric-Jones Co. v. Hufnagel, 848 P.2d 942, 17 Brief Times Rptr. 563, 1993 Colo. LEXIS 297, 1993 WL 88131 (Colo. 1993).

Opinions

Justice MULLARKEY

delivered the Opinion of the Court.

The petitioners, Centric-Jones Company and its general partners, Nucon Construction Corporation and J.A. Jones Construction Company, have brought an original proceeding before this court pursuant to C.A.R. 21. For purposes of this opinion, we will refer to all three petitioners as Centric. Centric asks us to compel the respondent trial court to order the clerk to • enter judgment for it pursuant to its acceptance of an offer of judgment under section 13-17-202(3), 6A C.R.S. (1992 Supp.). Of concern in this case is whether the trial court was correct in finding that an entry of summary judgment in favor of one of the two defendants participating in a joint offer of judgment voids the offer. We issued a rule to show cause and now make the rule absolute, finding that the trial court erred as a matter of law.

I.

In 1987, the Colorado Department of Highways, since renamed the Department of Transportation (CDOT), undertook a project involving the modification and reconstruction of certain ramps on the I-25/6th Avenue Interchange. CDOT hired a private engineering firm, De Leuw Cather & Co., since renamed Parsons De Leuw, Inc. (De Leuw), to prepare the design, as well as the plans and specifications, and review the shop drawings for this project. Centric was hired by CDOT as the general contractor to implement the plans as set forth by De Leuw.

Errors committed by De Leuw in the design and in reviewing shop drawings caused the project to fall behind schedule. As a result, in 1989, Fought & Company, Inc., Centric’s subcontractor for the manufacture of the steel components needed in the project, brought suit and obtained a judgment against Centric for the damages it incurred due to the delay.

Centric then filed an independent action in 1991 against CDOT on grounds that, because of CDOT’s wrongful conduct, Centric suffered damages in terms of additional costs incurred from the delay and the Fought judgment. The complaint was amended in March 1992 to include De Leuw as a defendant. In June, De Leuw filed a motion for summary judgment on the grounds that Centric’s claims against it were barred by the statute of limitations. An offer of judgment was made jointly by De Leuw and CDOT on September 30, pursuant to section 13-17-202(3), 6A C.R.S. (1992 Supp.) which states in part:

At any time more than ten days before the trial begins, a party defending against a claim may serve upon the adverse party an offer of settlement to the effect specified in his offer, with costs then accrued. If within ten days after the service of the offer, the adverse party serves written notice that the offer is accepted, either party may then file the offer and notice of acceptance, together [945]*945with proof of service thereof, and thereupon the clerk shall enter judgment... ,1

The offer of judgment stated:

1. CDOT and De Leuw hereby make a joint offer of settlement, including any interest and costs to which plaintiff may be entitled as a matter of law, in the total amount of Seven Hundred Fifty Thousand and No/100 Dollars ($750,000) which shall be deemed withdrawn if this offer is not accepted by plaintiffs within ten (10) days from the date hereof.
2. This offer is intended to apply to the total amount of any judgment obtained by plaintiffs against one or both of the defendants, regardless of the claims and theory(ies) asserted by plaintiffs against the defendants, and regardless of the proration of liability between the defendants with respect thereto.

Centric orally gave a counteroffer for $1.4 million, which was rejected.

On October 8, the trial court granted the motion for summary judgment in favor of De Leuw. CDOT and De Leuw immediately attempted to withdraw the offer of judgment by a telephone call on that day and by formal letter on October 9. Knowing of the summary judgment, Centric accepted the offer of judgment despite De Leuw’s and CDOT’s attempted withdrawal. Centric filed the necessary documents with the District Court on October 9. A motion for an order directing entry of judgment was filed by Centric, but was denied by the trial court in an oral ruling. Centric then brought an original proceeding before this court.

The facts of this case raise two interrelated issues. First is the general question whether a defendant which has made an offer of judgment pursuant to the statute may withdraw that offer within ten days of making the offer. Second is the specific question whether an offer of judgment automatically is revoked if, within the ten-day period, the trial court enters summary judgment in favor of one of the two defendants which made a joint offer of judgment pursuant to the statute. In this case, the trial court held that the defendants could not revoke the offer within the ten-day period but that entry of summary judgment for one defendant made the offer “ineffectual for all purposes.” We agree that the offer was irrevocable during the ten-day period but reject the trial court’s conclusion that its entry of summary judgment voided the offer.

II.

We first address a preliminary matter of jurisdiction. The respondent trial court contends that the exercise of our jurisdiction under C.A.R. 21 is inappropriate since Centric could appeal the summary judgment order subsequent to trial. Both CDOT and Centric argue in favor of this court exercising its original jurisdiction and making the rule absolute. CDOT now wants the offer of judgment enforced and contends that it cannot settle unless De Leuw is bound by the joint offer of judgment. Both CDOT and Centric argue that it would be a waste of judicial resources to force them to go to trial.

Whether to take jurisdiction over an original proceeding is entirely within this court’s discretionary authority. See Halaby, McCrea & Cross v. Hoffman, 831 P.2d 902, 905 (Colo.1992) {citing White v. District Ct., 695 P.2d 1133, 1135 (Colo.1984)). An original proceeding is not a substitute for an appeal and in this case there are important reasons for exercising our original jurisdiction. Judicial economy favors the resolution of this matter on an original proceeding because, if the rule is made absolute, no trial is necessary. Further, the trial court’s ruling raises substantial doubt as to the proper implementation of the statute authorizing offers of judgment. Since public policy favors the early resolution of disputes in the most expeditious and inexpensive method possible, it is appropriate to review this case promptly and to provide suitable guidance to the trial [946]*946courts and the bar. Accordingly, we decline to dismiss our order to show cause.

III.

A.

Having found the exercise of our jurisdiction to be appropriate under C.A.R. 21, we now turn to the question of the revoca-bility of an offer of judgment made pursuant to the statute. The parties to this action are in agreement that, generally, such an offer of judgment is not revocable within the ten-day period. We look for guidance to jurisdictions having similar statutes or rules in order to assess the correctness of the parties’ position.

The general weight of precedents, as the parties have recognized, is in consensus that offers of judgment are irrevocable.2 See 12 Charles A. Wright & Arthur R. Miller, Federal Practice and Procedure

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jesus Lazaro Collar v. Abalux, Inc.
895 F.3d 1278 (Eleventh Circuit, 2018)
White v. Estate of Soto-Lerma
2018 COA 34 (Colorado Court of Appeals, 2018)
Miller v. Hancock
410 P.3d 819 (Colorado Court of Appeals, 2017)
Pahoua Xiong v. Knight Transportation, Inc.
658 F. App'x 884 (Tenth Circuit, 2016)
McGinnis v. Cox
465 S.W.3d 157 (Court of Appeals of Tennessee, 2014)
Rost ex rel. Rost v. Atkinson
2012 COA 74 (Colorado Court of Appeals, 2012)
Kroener v. Florida Insurance Guaranty Ass'n
63 So. 3d 914 (District Court of Appeal of Florida, 2011)
Strunk v. Goldberg
258 P.3d 334 (Colorado Court of Appeals, 2011)
Ferrellgas, Inc. v. Yeiser
247 P.3d 1022 (Supreme Court of Colorado, 2011)
Novak v. Craven
195 P.3d 1115 (Colorado Court of Appeals, 2008)
Montoya v. Connolly's Towing, Inc.
216 P.3d 98 (Colorado Court of Appeals, 2008)
Dillen v. Healthone, L.L.C.
108 P.3d 297 (Colorado Court of Appeals, 2005)
Morgan v. Genesee Co., LLC
86 P.3d 388 (Supreme Court of Colorado, 2004)
Rubio v. Farris
51 P.3d 992 (Colorado Court of Appeals, 2002)
Chartier v. Weinland Homes, Inc.
25 P.3d 1279 (Colorado Court of Appeals, 2001)
Hale v. Erickson
23 P.3d 1255 (Colorado Court of Appeals, 2001)
Garcia v. Wal-Mart Stores, Inc.
209 F.3d 1170 (Tenth Circuit, 2000)
Tucker v. Benevolent & Protective Order of Elks Lodge 417
2000 OK CIV APP 51 (Court of Civil Appeals of Oklahoma, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
848 P.2d 942, 17 Brief Times Rptr. 563, 1993 Colo. LEXIS 297, 1993 WL 88131, Counsel Stack Legal Research, https://law.counselstack.com/opinion/centric-jones-co-v-hufnagel-colo-1993.