Ceco Concrete Construction v. J.T. Schrimsher Construction Co.

792 F. Supp. 109, 1992 U.S. Dist. LEXIS 7941
CourtDistrict Court, N.D. Georgia
DecidedJune 2, 1992
Docket1:92-cr-00140
StatusPublished
Cited by2 cases

This text of 792 F. Supp. 109 (Ceco Concrete Construction v. J.T. Schrimsher Construction Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ceco Concrete Construction v. J.T. Schrimsher Construction Co., 792 F. Supp. 109, 1992 U.S. Dist. LEXIS 7941 (N.D. Ga. 1992).

Opinion

ORDER

MOYE, District Judge.

In these consolidated cases Ceco Concrete Construction Company seeks to have an arbitration award confirmed; Schrimsher Construction Company seeks to have it vacated.

It is conceded that the arbitration under the construction contract rules of the American Arbitration Society involved a *110 dispute relating to a construction contract involving interstate commerce within the meaning of the Federal Arbitration Act, 9 U.S.C. section 1 et seq (Brief of J.T. Schrimsher Construction Company, Inc., in support of its motion to dismiss plaintiffs complaint and application for confirmation of award of arbitrators, filed February 24, 1992, pp. 4-5). Thus “federal law applies to all questions of interpretation, construction, validity, revocability and enforceability” (underscoring added), Coenen v. R.W. Pressprich & Co., 453 F.2d 1209, 1211 (C.A.2, 1972), cert. den. 406 U.S. 949, 92 S.Ct. 2045, 32 L.Ed.2d 337. “In deciding the question of arbitrability, the federal policy [is] to construe liberally arbitration clauses to find that they cover disputes reasonably contemplated by their language, and to resolve doubts in favor of arbitration,” Coenen, supra, 453 F.2d at 1212, citing Metro Industrial Painting Corp. v. Terminal Construction Co., 287 F.2d 382, 385 (2d Cir., 1961).

Schrimsher argues first in support of its motion to dismiss and application to vacate, that it was entitled to a postponement of the arbitration proceeding because otherwise it would likely be exposed to the possibility of conflicting results with the owner on the one hand and Ceco on the other (Schrimsher’s application to vacate arbitration award, par. 19). The thrust of this argument is that, at the time of the arbitration proceeding, cleanup “costs to correct Ceco’s defective work were still being incurred and the issue of delay damages as between Schrimsher and Ceco could not reasonably be determined until that same issue had been resolved between Schrimsher and the owner, Auburn University” (application to vacate, par. 17).

9 U.S.C. section 10(a) provides that an arbitration award may be vacated.

“ * * * (3) Where the arbitrators were guilty of misconduct in refusing to postpone the hearing upon sufficient cause shown ...”

The Court does not believe such a situation has been shown here. By its motion to vacate Schrimsher effectively was seeking a stay of proceedings pending determination of a related proceeding. Such right to a stay does not exist under the Federal Arbitration Act. Volt Info. Sciences v. Leland Stanford Jr. University, 489 U.S. 468, 470, 109 S.Ct. 1248, 1250-1251, 103 L.Ed.2d 488 (1988). 1

The granting or denying of an adjournment or postponement falls within the broad discretion of appointed arbitrators. Nyall Storey v. Searle Blatt Ltd., 685 F.Supp. 80, 82 (S.D.N.Y., 1988) citing Fairchild and Co. v. City of Richmond et al., 516 F.Supp. 1305, 1313 (D.D.C., 1981), and Dan River Inc. v. Cal-togs, Inc., 451 F.Supp. 497, 503-504 (S.D.N.Y.1978). Thus, assuming a reasonable basis for the arbitrators’ considered decision not to grant a postponement, the Court will be reluctant to interfere with the award on these grounds. Fairchild and Co., supra, at 1313-1314. Although the arbitrators here did not articulate the basis upon which they denied the requested postponement, the Court believes that decision was not unreasonable, and certainly not the product of misconduct. The Court believes that the postponement to permit completion of related administrative proceedings involving only Schrimsher and the owner, if proper at all, was unnecessary. The Court believes all the questions presented under the agreement to arbitrate all disputes with respect to the underlying construction contract, could be decided in the proceeding involving only Schrimsher and Ceco. Schrimsher says it believes some of the delay damages may had been the responsibility of the owner, and if Ceco was damaged thereby that the construction agreement provided that Schrimsher would act as Ceco’s conduit to present such claims to the owner. But Ceco claimed only that such damages as it sought were Schrimsher’s fault. Had Schrimsher proven in the arbitration proceeding (in which it fully participated, albeit under protest), that the *111 delays where the owner’s fault, not Schrimsher’s, presumably the arbitrators would have so found, and presumably their award is of damages solely attributable to Schrimsher. Thus, having in mind the purpose of Congress to afford participants to arbitration agreements a prompt, economical and adequate solution of their problems through arbitration if the parties are willing, as here, to accept less certainty of legally correct adjustment, the arbitrators were entirely correct in their decision to refuse postponement pending determination of the related administrative proceedings.

As to Schrimsher’s claim that it was continuing to incur costs related to the matters being arbitrated, the Court notes that when the arbitrators were asked to reconsider their refusal to postpone, they informed the parties that, “Should the panel find in favor of Schrimsher in all or in part, the hearings will remain open for a reasonable time for Schrimsher to conclude its case.” Letter from American Arbitration Association to the attorneys for the parties dated October 18, 1991.

Schrimsher’s other objection to the award is that it included an amount for attorneys fees, which Schrimsher asserts was beyond the competence of the arbitrators. This position is based upon two opinions by the Court of Appeals of the State of Georgia, Hughes and Peden, Inc. v. Budd Contracting Company, Inc., 193 Ga.App. 656, 388 S.E.2d 753 (1989) and Walton Acoustics, Inc. v. Currahee Construction Co. Inc., 197 Ga.App. 659, 399 S.E.2d 265 (1990).

The subcontract between the parties provided:

“(42) In any action or proceeding brought to enforce any of the provisions of this contract, prevailing party shall recover the cost thereof, including reasonable attorneys fees from the other party.”

In the arbitration submission, both parties (Schrimsher as well as Ceco) claimed for attorneys fees.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lomax v. Woodmen of the World Life Insurance Society
228 F. Supp. 2d 1360 (N.D. Georgia, 2002)
Ebasco Constructors, Inc. v. Ahtna, Inc.
932 P.2d 1312 (Alaska Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
792 F. Supp. 109, 1992 U.S. Dist. LEXIS 7941, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ceco-concrete-construction-v-jt-schrimsher-construction-co-gand-1992.