Castillo v. Toll Bros., Inc.

197 Cal. App. 4th 1172, 130 Cal. Rptr. 3d 150
CourtCalifornia Court of Appeal
DecidedJuly 28, 2011
DocketNo. A128605; No. A128611
StatusPublished
Cited by10 cases

This text of 197 Cal. App. 4th 1172 (Castillo v. Toll Bros., Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Castillo v. Toll Bros., Inc., 197 Cal. App. 4th 1172, 130 Cal. Rptr. 3d 150 (Cal. Ct. App. 2011).

Opinion

Opinion

MARGULIES, J.

Defendant Toll Bros., Inc. (Toll Bros.), a homebuilder, was joined in two wage-and-hour class action lawsuits brought by employees of its subcontractors, Castillo v. Toll Bros., Inc. (Super. Ct. Alameda County, 2010, No. RG06290188) (hereafter Castillo) and Hernandez v. Toll Bros., Inc. (Super. Ct. Alameda County, 2010, No. RG06302769) (hereafter Hernandez). In addition to asserting common law claims, the plaintiffs in each action alleged a claim under Labor Code1 section 2810 seeking, in effect, to hold Toll Bros, liable for the subcontractors’ Labor Code violations. A relatively [1182]*1182new statute, section 2810 authorizes the employees of a services contractor to sue the party hiring the contractor if the hiring party knowingly pays a contract price insufficient to permit the contractor to comply with the law in performing the contract. Toll Bros, moved for summary judgment, arguing, inter alia, that its subcontracts could not be found insufficient under section 2810 because they provided adequate funds to permit the subcontractors to pay their workers the minimum wage, as well as to comply with other applicable laws. Plaintiffs countered the contracts should be found insufficient unless they permitted payment of the locally prevailing wage for comparable work, rather than the legal minimum.

The trial court granted summary judgment for Toll Bros., agreeing the minimum wage was the appropriate measure under section 2810 and finding no triable issue of fact regarding the adequacy of the contracts under this standard. The trial court also found for Toll Bros, as a matter of law on plaintiffs’ common law claims, but it rejected other legal defenses asserted by Toll Bros, under section 2810.

We agree with the trial court’s legal rulings, including its application of the minimum wage as a standard under section 2810, but we conclude plaintiffs raised a triable issue of fact with respect to the sufficiency of two of the contracts challenged in the Castillo matter. Accordingly, we affirm the trial court’s grant of summary judgment in the Hernandez action and its grant of summary adjudication of the common law claims in the Castillo matter, but we reverse summary adjudication and remand for further proceedings on the section 2810 claim asserted in Castillo.

I. BACKGROUND

These two putative class actions were filed in September and December 2006. The named plaintiffs in Castillo are employees of the defendant, Capaz Construction Corp. (Capaz), a subcontractor on several construction projects for which Toll Bros, acted as general contractor. Their third amended complaint alleged a series of wage-and-hour violations by Capaz in connection with its work for Toll Bros., including failure to pay overtime, failure to provide adequate meal breaks and rest periods, failure to provide accurate wage statements and keep accurate payroll records, failure to pay in a timely manner after cessation of work and on a biweekly schedule, and outright refusal to pay wages. The complaint asserted statutory causes of action to recover for these violations, as well as common law claims for unfair business practices, conversion, fraud, and other theories. The claims asserted against Toll Bros., which sought to hold Toll Bros, liable for the Capaz labor law violations, included negligence, unfair competition, and unjust enrichment.

[1183]*1183In addition, Toll Bros, was sued under section 2810. Subdivision (a) of section 2810 (hereafter subdivision (a)) prohibits a party from entering into a contract for certain types of services, including construction services, if the party knows or should know the contract “does not include funds sufficient to allow the contractor to comply with all applicable local, state, and federal laws or regulations governing the labor or services to be provided.”2 Subdivision (g) of the statute establishes a cause of action in favor of employees “aggrieved” by a violation of subdivision (a).

The Hernandez action is a parallel lawsuit brought by employees of defendant Tim Shannon Construction, Inc. (Shannon), another Toll Bros, subcontractor. The fourth amended complaint in Hernandez asserted similar wage-and-hour violations and common law claims against Shannon and Toll Bros. The Hernandez plaintiffs also asserted a section 2810 claim against Toll Bros.

Toll Bros, moved for summary judgment in both actions in March 2009.3 Although the motions were necessarily directed at all causes of action asserted against Toll Bros., their primary focus was the section 2810 claim. Because the trial court granted a series of postponements to permit additional discovery and the submission of supplemental briefing and evidence, the motions were not heard until nearly a year later. Both motions were ultimately granted in a single, detailed 37-page order issued in March 2010. The appeals have been consolidated.

In moving for summary judgment, Toll Bros, initially argued that plaintiffs could not demonstrate the subcontractors’ alleged violations of law were caused by insufficiency of the contract price and section 2810 was preempted by federal labor law. Toll Bros, also argued it had not violated section 2810 because it did not know, and had no reason to believe, the compensation provided in its contracts with Capaz and Shannon was insufficient to permit the subcontractors to comply with applicable laws.

According to the evidence submitted in support of the motion, Toll Bros, is a developer of large-scale residential projects. Capaz and Shannon are framing contractors, responsible for erecting the structural elements of the [1184]*1184homes in several Toll Bros, projects. Most subcontracts for Toll Bros, projects, including the various contracts of Capaz and Shannon, are “lump-sum” contracts awarded through competitive bidding. Under a lump-sum contract, the subcontractor agrees to accept a set price for the performance of all work required by the contract. When awarding a subcontract through competitive bidding, Toll Bros, typically sends a bid package to five or six potential subcontractors. After the subcontractors submit their bids for the contract, a Toll Bros, employee reviews them, ensures the bid is complete, seeks clarification of any ambiguities from the bidders, confirms each bidder’s licensing and workers’ compensation insurance status, and seeks references to confirm the bidders’ past job performance.

Toll Bros, relies on the competitive bidding process to arrive at an appropriate price for each subcontract. During the competitive bidding process, Toll Bros, is generally given very little information about the basis for the bids. The subcontractors may be asked to break down the cost components of a bid between materials, or subsets of materials, and labor, but there is little or no further detail provided. Even this information may be unreliable. Subcontractors have an incentive to minimize the labor cost allocation of the subcontract in favor of materials costs because the amount of the contract price retained by Toll Bros, to insure against incomplete or inadequate work is based on the labor allocation. Further, it is difficult for Toll Bros, to estimate in advance what any particular subcontractor’s labor costs will be because there are many ways for a subcontractor to perform a particular job, using different mixes of skill and experience in laborers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Stone Construction v. Santa Mix CA4/3
California Court of Appeal, 2026
Mercury Bowl v. Thee Aguila, Inc. CA2/4
California Court of Appeal, 2025
F.G. v. CooperSurgical, Inc.
N.D. California, 2024
Lee v. Amazon.com, Inc.
California Court of Appeal, 2022
Doe v. Google, Inc.
California Court of Appeal, 2020
Roy Allan Slurry Seal, Inc. v. Am. Asphalt S., Inc.
388 P.3d 800 (California Supreme Court, 2017)
Paslay v. State Farm General Insurance Co.
248 Cal. App. 4th 639 (California Court of Appeal, 2016)
Hawkins v. Taca International Airlines, S.A.
223 Cal. App. 4th 466 (California Court of Appeal, 2014)
Calop Business Systems, Inc. v. City of Los Angeles
984 F. Supp. 2d 981 (C.D. California, 2013)
Valley Casework v. Lexington Ins. CA4/1
California Court of Appeal, 2013

Cite This Page — Counsel Stack

Bluebook (online)
197 Cal. App. 4th 1172, 130 Cal. Rptr. 3d 150, Counsel Stack Legal Research, https://law.counselstack.com/opinion/castillo-v-toll-bros-inc-calctapp-2011.