Case, Inc. v. United States

37 Cont. Cas. Fed. 76,264, 25 Cl. Ct. 379, 1992 U.S. Claims LEXIS 70, 1992 WL 32703
CourtUnited States Court of Claims
DecidedFebruary 24, 1992
DocketNo. 90-680 C
StatusPublished
Cited by3 cases

This text of 37 Cont. Cas. Fed. 76,264 (Case, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Case, Inc. v. United States, 37 Cont. Cas. Fed. 76,264, 25 Cl. Ct. 379, 1992 U.S. Claims LEXIS 70, 1992 WL 32703 (cc 1992).

Opinion

OPINION

WIESE, Judge.

Plaintiff, a Government contractor, seeks leave to amend its complaint to cure what it sees as a deficient jurisdictional allegation. Defendant opposes the request and seeks dismissal of the suit for lack of jurisdiction in fact. The court, having considered the parties’ written and oral arguments on the issue, concludes that it has jurisdiction over the transaction sued on and that an amendment of the complaint to clarify the factual basis for that jurisdiction is proper. The motion to amend is therefore allowed; the motion to dismiss is denied.

FACTS

In October of 1986, the Defense Personnel Support Center awarded plaintiff a contract for the manufacture of airmen’s coveralls. Difficulties in the performance of the contract led to several extensions of the delivery schedule and eventually to the contracting officer’s issuance of a final decision on July 20, 1989 terminating the contract for default. The termination decision advised the contractor that it would be liable for any excess reprocurement costs and, additionally, that the Government was reserving “all rights and remedies provided by law and/or this contract.”

Two weeks later (August 3, 1989) the contracting officer issued a second final decision letter, this one advising that due to unliquidated progress payments chargeable against contract 0333 (the defaulted contract), Case was indebted to the United States in the amount of $4,064,212.54. The letter requested payment of the stated amount within 15 days and it went on to inform the contractor that, although a proposal for deferred liquidation of the debt could be submitted, interest on that debt would continue to accrue at the statutory rate.

On July 23,1990, the contractor filed this suit. Jurisdiction was premised on the Contract Disputes Act, 41 U.S.C. §§ 601-613 (1988). In its complaint, Case stated that “[tjhis action represents [an] appeal of the Contracting Officer’s Final Decision” (referring to the decision announcing the default termination) and, by way of relief, the contractor requested that the termination for default be converted to a termination for convenience.

Following the filing of the contractor’s suit in this court, the contracting officer issued another final decision letter again relating to the Government’s demand for the return of progress payments. In this letter, the amount of the claimed indebtedness was now shown as $3,432,256.17. The date of the decision was October 25, 1990.

The receipt of this second demand for return of progress payments prompted the contractor’s filing of another complaint here (No. 91-175C). As before, jurisdiction was premised on the Contract Disputes Act and the relief asked for was conversion of the termination for default to a termination for Government convenience. In addition, this second complaint, unlike the first, expressly asked the court to deny defendant recovery on its claim (i.e., the demand for return of unliquidated progress payments).

The Government has moved for dismissal of both suits, the first on the ground that it fails to state a demand for money and therefore is not within our jurisdiction; the second on the ground that the decision appealed from (the contracting officer’s revised repayment demand of October 25, 1990) was a nullity because it was issued more than twelve months after the original repayment demand and thus after the date by which that original decision became “final and conclusive” under section 6 of the Contract Disputes Act.

Following the filing of the Government’s motions, a status conference was convened [381]*381to consider, among other things, the desirability of consolidating the two suits. The Government opposed consolidation on the ground that a joinder of the two suits would not remedy the jurisdictional defects which it saw in each of them and, therefore, would serve no real purpose either for the parties or the court. In lieu thereof, it was decided (over the Government’s objection however) that the contractor would seek leave to amend its first-filed complaint to incorporate a jurisdictionally-valid money claim, i.e., a request for relief from the Government’s initial repayment demand. Additionally, it was decided that, pending disposition of the contractor’s motion to amend, proceedings in the second-filed suit would be suspended.

The Government, as we have indicated, opposes the motion to amend and seeks dismissal of plaintiff's suit for lack of jurisdiction. Consistent with this view of the case, the Government stated (at the status conference) that it had initiated the steps necessary to begin a collection action against plaintiff to recover the unliquidated progress payments. Such an action is, in fact, now pending in the United States District Court for the Eastern District of Kentucky.1

DISCUSSION

Fundamental to the exercise of our jurisdiction under the Contract Disputes Act is a final decision of the contracting officer. 41 U.S.C. § 605(a).2 Where the claim that is put in issue here has not previously been before the contracting officer, we have no authority to hear the matter. Paragon Energy Corp. v. United States, 227 Ct.Cl. 176, 184, 645 F.2d 966, 971 (1981).

It is conceded that the complaint now before us (the first-filed complaint) is jurisdictionally defective in that it asserts a right to relief not previously presented to the contracting officer for decision, i.e., the right to a no-fault contract termination together with appropriate monetary allowances. To overcome this defect, the contractor has moved for leave to amend its complaint to incorporate both the fact of the contracting officer’s August 3, 1989 demand for the return of progress payments and a request for relief from this demand. Save for these proposed changes, the complaint as originally filed would remain unchanged.

In opposing the motion to amend, the Government does not dispute that our basic jurisdictional statute, the Tucker Act, 28 U.S.C. § 1491 (1988), permits a contractor to sue here on a Government claim for money.3 Hence, plaintiff’s amendment, if otherwise allowable, would remedy the jurisdictional defect that attends the complaint as presently drafted. Rather, the Government’s objection to the amendment goes to the fact that it sees the contracting officer’s demand for the return of progress payments as having matured, through the expiration of the twelve month appeal period allowed under the Contract Disputes Act, into an incontestable right to the money claimed due.

The section of the Contract Disputes Act referred to, section 609(a)(3), allows the contractor twelve months from the date of receipt of the contracting officer’s decision on the claim in which to commence suit on the claim in the Claims Court. If suit is not brought within the time allowed, section 605(b) declares the contracting officer’s decision on the claim to be “final and conclusive and not subject to review by any [382]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Renda Marine, Inc. v. United States
65 Fed. Cl. 152 (Federal Claims, 2005)
Case, Incorporated v. United States
88 F.3d 1004 (Federal Circuit, 1996)
Boeing Co. v. United States
38 Cont. Cas. Fed. 76,332 (Court of Claims, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cont. Cas. Fed. 76,264, 25 Cl. Ct. 379, 1992 U.S. Claims LEXIS 70, 1992 WL 32703, Counsel Stack Legal Research, https://law.counselstack.com/opinion/case-inc-v-united-states-cc-1992.