Carson Opera House Ass'n v. Miller

16 Nev. 327
CourtNevada Supreme Court
DecidedOctober 15, 1881
DocketNo. 1,068
StatusPublished
Cited by10 cases

This text of 16 Nev. 327 (Carson Opera House Ass'n v. Miller) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carson Opera House Ass'n v. Miller, 16 Nev. 327 (Neb. 1881).

Opinion

By the Court,

Leonard, C. J.:

Bespondents, Miller and' Cook, entered into a contract with appellant, dated April 27, 1878, whereby the former agreed, within three months from that date, to fully erect, construct, and finish, with first-class material, to be furnished by them, a theater or opera building, in strict accordance with certain plans, details, drawings, and specifications adopted by the parties; also, to secure appellant and keep it harmless from all liens and claims of liens for material or labor upon said building, under the laws of the state; also, to execute and deliver to appellant a bond in the sum of ten thousand dollars, with sufficient sureties, conditioned that said Miller and Cook should perform the terms and conditions of said contract on their part; and appellant agreed to pay said Miller and Cook therefor the sum of ten thousand one hundred and fi'fty-six dollars, as follows: Five hundred dollars each week, after two weeks from the date of said contract, until the said sum should be fully paid. On the same date a bond was executed, as agreed', with Miller and Cook as principals, and respondents, Hatch, Hymers, Marsh, Smith, Clark, and Hoole, as sureties.

It is alleged in the complaint that ‘1 the said plaintiff performed each and every of the covenants and stipulations as in the said contract set out,'and paid to the said J. H. Miller and Frank Cook the several sums and all the money mentioned in said contract, according to the terms and conditions of the said contract, and at the times therein speci[330]*330fied, except as follows: On or about the-day of-, A. D. 187-, and whilst the said Miller and Cook were still engaged in and about the construction of said building, under said contract, the liens hereinafter mentioned ivere filed in the office of the county recorder of said Ormsby county, after which date the said Miller and Cook, nor either of them, made any demand upon plaintiff, or application for the payment of any further sums of money thereafter accruing upon said contract, or then due thereon, but left the money accruing upon said contract, to wit: the sum of one thousand four hundred and seven dollars and seventy-three cents, in the hands of plaintiff, which sum of money so accruing and remaining in the hands of plaintiff, the plaintiff was at all times ready and willing to pay upon the said contract, according to the stipulations thereof, and which said sum of money not being demanded or called for, the plaintiff applied in part satisfaction of said liens in the manner hereinafter particularly set forth.”

It is then alleged that said Cook and Miller did not save and keep plaintiff free or harmless from liens for material and labor upon the said building under the laws of the state, but that, on the contrary, they suffered and permitted two persons named, to acquire, file, and hold liens against said Opera House building for material furnished and used in and about the construction thereof, in the aggregate sum of two thousand eight hundred and seven dollars and seventy-three cents, which said liens were decreed against plaintiff and its said building on the twenty-seventh day of March, 1880, and which said sum, together with necessary costs and attorney’s fees, amounting to four hundred and fourteen dollars and eighty-five cents, plaintiff was after-wards compelled to pay, and did pay, less the sum of one thousand four hundred and seven dollars and seventy-three cents, paid out of moneys in plaintiff’s hands belonging to said Cook and Miller, and due to them upon said contract, as before stated.

This action is to recover one thousand eight hundred and fourteen dollars and eighty-five cents, which plaintiff was [331]*331compelled to pay, and did pay, out of its own separate funds, in order to clear its building of liens,

Bespondents, the sureties, alone appeared. They demurred to the complaint as follows, to wit: “That the same does not state facts sufficient to constitute a cause of action against them, or either of them. That it is ambiguous, unintelligible and uncertain in this. That it appears the contract of these defendants was that of suretyship. That it appears that plaintiff agreed to pay the full sum of ten thousand one hundred and fifty-six dollars, in installments of five hundred dollars each week, after two weeks from April, 1878. That it failed to so pay to the contractors said sum, but retained one thousand four hundred and seven dollars and seyenty-three cents thereof, in violation of said contract, it appearing that there was no obligation on the part of the contractors to demand the same, and it does not appear that plaintiff ever offered to pay the same, or that these defendants, sureties, ever knew or consented to such violation of the contract. It appears that plaintiff had no right to make the application of the moneys as alleged.”

The court sustained the demurrer. Plaintiff refused to amend, and thereupon the court ordered judgment in favor of defendants, the sureties, for their costs. This appeal is from that judgment, and it will be seen that the principal question presented is, whether the application of the fourteen hundred and odd dollars to the satisfaction of the liens, as stated, instead of paying it to the contractors according' to the terms of the contract, released the sureties from their obligations upon the bond.

The only alleged violation of the contract by the contractors is in suffering the liens to be filed and foreclosed. The presumption is, therefore, that, in other respects, it was performed according to its.terms. It follows that the building was fully completed on or before July 27, 1878. It is not stated when the foreclosure suit was commenced. It only appears that the decree was made March 27, 1880, and that the liens were filed before the building was fully completed, that is to say, before July 27, 1878. Under the [332]*332contract all the money was to be paid in five months and one week after about the middle of May, 1878; that is, about the twentieth of October, 1878. After the liens were filed the contractors did not demand, nor did plaintiff pay, or offer to pay, the one thousand four hundred and odd dollars according to the contract, although it was at all times ready and'willing to pay the same according to its stipulations. That sum was never paid to the contractors, but it was applied in part satisfaction of the liens, on or after March 27, 1880, the date of the decree of foreclosure.

it must be borne in mind that this appeal is taken from the judgment in favor of the sureties alone, and what follows applies only to their liability. We have nothing tó do Avith the liability of the contractors. It is necessary to settle some matters of a preliminary character before entering upon.'a discussion of the more important questions presented.

And first, it is claimed that the contract was broken on the part of the contractors by permitting liens to be filed, although appellant suffered no damage by the mere filing; that the contract of defendants Avas to prevent the filing of liens. We do not think so. We think it was purely a contract of indemnity. It was “to secure the plaintiff and keep it harmless from all liens and claims of liens.” In other Avords, they agreed that plaintiff should suffer no harm, injury, or damage from any liens or claims of liens. It is not claimed that the filing Avas in any manner injurious. After the filing it may be said there Avas a liability for damage, but the contract did not cover a mere liability. In Churchill v. Hunt,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Palevac v. Mid Century Non Auto
710 P.2d 1389 (Nevada Supreme Court, 1985)
County of Clark v. Bonanza No. 1
615 P.2d 939 (Nevada Supreme Court, 1980)
County of Glenn v. Jones
80 P. 695 (California Supreme Court, 1905)
Hand Manufacturing Co. v. Marks
52 P. 512 (Oregon Supreme Court, 1900)
Stephens v. Elver
77 N.W. 737 (Wisconsin Supreme Court, 1898)
American Employers' Liability Insurance v. Fordyce
36 S.W. 1051 (Supreme Court of Arkansas, 1896)
Gato v. Warrington
37 Fla. 542 (Supreme Court of Florida, 1896)
Pioneer Savings & Loan Co. v. Freeburg
61 N.W. 25 (Supreme Court of Minnesota, 1894)
Burley v. Hitt
54 Mo. App. 272 (Missouri Court of Appeals, 1893)

Cite This Page — Counsel Stack

Bluebook (online)
16 Nev. 327, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carson-opera-house-assn-v-miller-nev-1881.