Carlo Bianchi & Co. v. United States

157 Ct. Cl. 432, 1962 U.S. Ct. Cl. LEXIS 107, 1962 WL 9278
CourtUnited States Court of Claims
DecidedMay 9, 1962
DocketNo. 466-54
StatusPublished
Cited by4 cases

This text of 157 Ct. Cl. 432 (Carlo Bianchi & Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carlo Bianchi & Co. v. United States, 157 Ct. Cl. 432, 1962 U.S. Ct. Cl. LEXIS 107, 1962 WL 9278 (cc 1962).

Opinion

Per Curiam :

In the court’s opinion of January 14, 1959 (144 Ct. Cl. 500), it was decided that the plaintiff was entitled to an equitable adjustment for the cost of installing permanent supports in the tunnel, and the case was remanded to the Trial Commissioner pursuant to Rule 38(c) to determine the amount.

The Trial Commissioner has now reported that Items 2 through 7, both inclusive, and Item 16 were reasonably related to the cost of installing the tunnel supports and the damages for the delay incident thereto and as a result of the disruption to the balance of the contract work. The court agrees with the Trial Commissioner that the plaintiff is entitled to recover for such items, but the court is of the opinion that the plaintiff is also entitled to recover its profit on the cost of installing the permanent tunnel supports and the work incident thereto, which are Items 3, 4, 5 and 16 listed in finding 5 of the Commissioner’s report.

In the plaintiff’s original bid, which was accepted by defendant, there was included 15 percent profit before overhead, taxes and insurance. Plaintiff is entitled to the same profit on these items. With the addition of this profit, so computed, Items 3, 4, 5 and 16 amount to the following:

Item 3 (Finding 28)_$35,418.81
Item 4 (Finding 32)__ 33,432.39
Item 5 (Finding 34)- 16,115.25
Item 16 (Finding 39) __ 3,243.54

[434]*434The amount of recovery for Items 2, 6 and 7, as found by the Trial Commissioner and approved by the court, is as follows:

Item 2 (Finding 26)_$8,442.08
Item 6 (Finding 36)_ 37,189.29
Item 7 (Finding 38)_ 15,776.00

Items 2 to 7, both inclusive, and Item 16, as thus amended, amount to $149,617.36, which sum plaintiff is entitled to recover.

Plaintiff is not entitled to recover the additional items claimed in its amended petition filed March 9, 1959, for the reason that the additional items claimed therein have no relation to the cost of the installation of the permanent tunnel supports; nor is the plaintiff foreclosed from recovering on the items allowed above by reason of the execution of the release, this matter having been heretofore determined by the court in its opinion filed on January 14, 1959.

Judgment will be entered for plaintiff and against the defendant in the sum of $149,617.36.

It is so ordered.

FINDINGS OF FACT

The court, having considered the evidence, the report of Trial Commissioner William E. Day, and the briefs and argument of counsel, makes findings of fact as follows:

1. The plaintiff constructed an earthen dam and related works near Hornell, New York, pursuant to contract entered into between it and the United States, through the Army Engineer Corps as a flood control project. The plaintiff was paid about three and one-half million dollars for the work, sustaining a net loss of $327,000.

2. This action was brought to recover “compensation for additional work done and reimbursement for the increased costs occasioned by Government delays and other increased costs * * *” due to the failure on the part of the defendant to authorize permanent tunnel supports and liner plates in the tunnel which had been blasted through rock for a distance of 710 feet.

3. The original petition claimed damages totaling $259,-721.87. This total was made up of the following items claimed:

[435]*435Schedule oí Plaintiffs Increased Costs
1. Cost of Bemoving Extra Overbreak During Original Tunnel Driving_ $1, 092.75
2. Cost of Bemoving Fallen Bock and Extra Bock to Invert Subsequent to Completion of Tunnel Driving (March 25, 1947)_ 9, 018. 00
3. Permanent Tunnel Supports Installed After March 25, 1947 _ 29,354.51
4. Backpacking Installation_ 24, 979.15
5. Additional Concrete Placed_ 11,200.00
6. Heating Costs — Winter Concrete_ 45, 853.08
7. Loss of Efficiency — Winter Concrete_ 18, 560.00
8. Excess Supervisory, Engineering and Administrative Labor — period 1-16-49 through 6-30-49_ 35,250.01
9. Cost of principal Items of Plant and Equipment used and Maintained on Contract after 1-16-49_ 58,118.25
$233,425. 75
(15% allowance for profit on items 1-8, incl.)_ 26,296.12
$259,721. 87

4. The case proceeded to trial on the issue of liability. On January 14,1959, the court decided that the plaintiff was entitled to recover, with the amount of recovery to be determined pursuant to Rule 38(c). Finding 49 of the court reads as follows:

From all the evidence of record, it is found that the failure and refusal of the resident engineer to recommend and of the contracting officer to direct the installation of steel arch ribs and liner plates caused a disruption of the sequences of operations, as well as delay in the performance of the work by the plaintiff. It required that concreting operations, which the plaintiff could, and would have performed in warm weather, be accomplished in winter weather with resulting loss of efficiency.

5. On March 9, 1959, after leave granted by the court, the plaintiff filed its second amended petition which increased the damages claimed to $680,066.01. This total was made up of the following items:

Schedule of Plaintiff’s Increased Costs
1. _
2. Cost of Bemoving Fallen Bock and Extra Bock in Invert Subsequent to Completion of Tunnel Driving (March 25, 1947)_ $8,442.08
[436]*4363. Permanent Tunnel Supports Installed After Mareli 25, 1947_ 31,248.69
4. Backpacking Installation- 29,392.12
5. Additional Concrete Placed- 13,697.96
6. Heating Costs — Winter Concrete_ 37,189.29
7. Loss of Efficiency — Winter Concrete_ 15, 776. 00
8. Excess Supervisory, Engineering and Administrative Labor — period 1-16-49 through 6-30-49- 32,367. 87
9. Cost of Principal Items of Plant and Equipment used and Maintained on Contract after 1-16-49- 49,400. 51
10. Stockpiling of Impervious Material From Spillway Excavation, and Later Re-excavating and Placing same in the Closure Section of the Dam Embankment _ 59,261. 80
11. Excess Costs of Maintaining and Operating Earth Handling Equipment in Construction of Dam Embankment _ 249,619.14
12. Excess Costs of Supervisory and Engineering Personnel Employed in Construction of Dam Embankment _ 21,186.13
13.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

L. L. Hall Construction Company v. The United States
379 F.2d 559 (Court of Claims, 1966)
Utah Construction & Mining Co. v. United States
339 F.2d 606 (Court of Claims, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
157 Ct. Cl. 432, 1962 U.S. Ct. Cl. LEXIS 107, 1962 WL 9278, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carlo-bianchi-co-v-united-states-cc-1962.