Captiva Lake Investments v. Fidelity National Title Ins.

883 F.3d 1038
CourtCourt of Appeals for the Eighth Circuit
DecidedFebruary 28, 2018
Docket16-1854; 16-1923
StatusPublished
Cited by11 cases

This text of 883 F.3d 1038 (Captiva Lake Investments v. Fidelity National Title Ins.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Captiva Lake Investments v. Fidelity National Title Ins., 883 F.3d 1038 (8th Cir. 2018).

Opinion

WOLLMAN, Circuit Judge.

National City Bank of the Midwest (National City) loaned Majestic Pointe Development Company, L.L.C. (Majestic Pointe), $21,280,000 in March 2006. Majestic Pointe planned to build a condominium development on the Lake of the Ozarks in Sunrise Beach, Missouri. To protect its security interest, National City purchased a title insurance policy (the policy) from Fidelity National Title Insurance Company (Fidelity). 2 Midway through construction, Majestic Pointe defaulted on the construction loan agreement and thereafter went bankrupt. National City sold its interest in the condominium development to Captiva Lake Investments, LLC (Captiva), which became the successor-in-interest under the policy.

Captiva filed a claim with Fidelity in August 2009, seeking coverage for mechanics' liens that had been filed against the property. Fidelity agreed to defend *1042 Captiva, subject to a reservation of Fidelity's rights under the policy, and hired attorneys to defend Captiva in the mechanics' lien litigation. Fidelity specifically reserved the right to deny coverage based on Exclusion 3(a), which excludes from coverage loss or damage that arose by reason of liens "created, suffered, assumed or agreed to by the insured claimant." Fidelity did not resolve the liens as quickly as Captiva would have liked, and so in August 2010, Captiva filed an additional claim under the policy's unmarketability-of-title provision, alleging that Fidelity had rendered the title unmarketable by failing to resolve or insure over the pending mechanics' lien claims.

Fidelity filed suit in federal district court in October 2010, seeking a declaration that the title insurance policy did not cover the mechanics' liens. Captiva filed counterclaims, which sought a declaration that the policy covered the mechanics' liens and which asserted claims against Fidelity for failing to diligently defend and resolve the mechanics' liens claims and for tortiously interfering with Captiva's relationship with the attorneys Fidelity had hired to defend Captiva. Before trial, Fidelity decided not to seek reimbursement from Captiva for the liens that it had resolved on Captiva's behalf. The parties thereafter stipulated to the dismissal of Fidelity's complaint and were realigned for trial, with Captiva as the plaintiff and Fidelity as the defendant.

The district court did not allow Fidelity to present its Exclusion 3(a) defense that National City "created, suffered, assumed or agreed to" the mechanics' liens. The court determined that evidence of intentional misconduct or inequitable dealings by National City was required to sustain the defense and that Fidelity had failed to present such evidence. The court dismissed the tortious interference claim. The jury found that Fidelity had breached the title insurance policy and, as is more fully discussed below, awarded more than $6 million in damages to Captiva.

We conclude that the district court did not apply the correct legal standard in deciding that Exclusion 3(a) did not apply to the mechanics' liens at issue in this case. Under the appropriate standard, Fidelity was entitled to present to the jury its defense that National City had "created, suffered, assumed or agreed to" the mechanics' liens. We further conclude that Captiva failed to show that the title was unmarketable on or before the effective date of the policy and thus failed to prove its claim that Fidelity breached the policy's unmarketability-of-title provision.

We affirm the district court's dismissal of the tortious interference claim. We vacate the judgment and remand the case for further proceedings. We also vacate the order awarding attorneys' fees and costs.

I. Background

A construction loan provides funds for the construction of improvements on land. The developer and the lender enter into a construction loan agreement, which sets forth the terms of the loan and "generally incorporates by reference the project's plans and specifications, includes a budget that the developer must follow, and specifies the project completion date." 1 Grant S. Nelson et al., Real Estate Finance Law § 12.1 (6th ed.), Westlaw (database updated Dec. 2014). The developer's obligation to repay is set forth in a promissory note and the loan is secured by a mortgage or deed of trust, meaning that the loan is "secured by the construction project itself-the land and the building in progress." BB Syndication Servs., Inc. v. First Am. Title Ins. Co. , 780 F.3d 825 , 826-27 (7th Cir. 2015).

Construction lending can be risky. "If the construction project fails and puts the *1043 developer into bankruptcy, the lender's loan is protected only by the unfinished project, which is often worth far less than the money put into it." Id. at 827 . Accordingly, construction lending requires careful underwriting and monitoring. Michael F. Jones & Rebecca R. Messall, Mechanic's Lien Title Insurance Coverage for Construction Projects: Lenders & Insurers Beware , 16 Real Est. L.J. 291 , 292-93 (1988). During underwriting, the lender will conduct a detailed analysis of the project to determine its risk. Id. at 292 . Critical to the underwriting analysis is whether the construction loan, together with the developer's investment, provides sufficient funds to complete the project. Id. Many lenders require the developer to invest a substantial amount of its own money in the construction project. Nelson et al., supra , at § 12.1. If there is a shortfall in the loan amount compared with the estimated cost to complete the project, the lender often will require the developer to cover the difference before any loan funds are disbursed. Jones & Messall, supra , at 293. After the lender decides to issue the loan, it disburses loan funds incrementally as work is completed.

Incremental disbursement of loan proceeds allows the lender to monitor the construction project and ensure that the loan remains "in balance"-that is, that sufficient funds exist to complete the project. Id. After the developer requests a disbursement, the lender typically conducts a site inspection to ensure that the work has been completed. See Nelson et al., supra , at § 12.1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
883 F.3d 1038, Counsel Stack Legal Research, https://law.counselstack.com/opinion/captiva-lake-investments-v-fidelity-national-title-ins-ca8-2018.