Capitol Cement Company, Inc. v. City of Harvey

2026 IL App (1st) 241045-U
Appellate Court of Illinois·Decided March 31, 2026·No. 1-24-1045·Unpublished

Opinion

2026 IL App (1st) 241045-U

SECOND DIVISION

March 31, 2026

Nos. 1-24-1045, 1-25-0235 (cons.)

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1).

IN THE

APPELLATE COURT OF ILLINOIS FIRST JUDICIAL DISTRICT

CAPITOL CEMENT COMPANY, INC., an ) Illinois Corporation, ) Appeal from the Circuit Court of ) Cook County.

Plaintiff-Appellant, )

)

v. ) No. 2019 CH 07434 )

CITY OF HARVEY, H&H ELECTRIC CO., and ) ILLINOIS DEPARTMENT OF ) Honorable TRANSPORTATION, ) Neil H. Cohen, ) Judge, presiding.

Defendants-Appellees. )

JUSTICE D.B. WALKER delivered the judgment of the court.

Justice Ellis concurred in the judgment.

Presiding Justice Van Tine specially concurred.

ORDER

¶1 Held: The circuit court’s dismissal of plaintiff’s unjust enrichment claim was premature, but its grant of summary judgment on the breach of contract claim was appropriate. We affirm in part and reverse in part.

¶2 In 2010, the City of Harvey, Illinois (defendant) passed the first of several resolutions authorizing a project to improve a stretch of 167th Street in Harvey. Capitol Cement Company, Inc. (plaintiff) won the contract to perform the project work. The project was

funded by a combination of defendant’s own funds and grant funds provided by the State of Illinois and Cook County. Within months of plaintiff starting work, when the project was approximately 75% complete, defendant instructed plaintiff to stop work because it no longer had funds to pay plaintiff for its work because one of the necessary grants was withdrawn by the State. Plaintiff sued on a number of grounds, including breach of contract and, in the alternative, unjust enrichment. Plaintiff stated in its complaint that the Illinois Department of Transportation (IDOT) and H&H Electric Company were named as defendants only as necessary parties, and seeks no relief against them. The circuit court dismissed the unjust enrichment claim and awarded defendant summary judgment on the breach of contract claim. Plaintiff appeals.

¶3 I. BACKGROUND

¶4 On October 25, 2010, defendant passed Resolution 2564, which authorized Robinson Engineering (Robinson) to perform a study and produce a design for what it called “the 167th Street expansion project.” Defendant subsequently passed Resolution 2622 in 2012, committing $250,000 in “general obligation funds or motor fuel tax funds” to be spent on the project in conjunction with anticipated funds from a “CDBG-IKE Disaster Recovery Program grant.” Defendant passed Resolution 2702 in 2013, allowing defendant to borrow $105,173.97 from “the appropriate TIF” 1 for the project, to be reimbursed from Illinois Disaster Recovery Grant funds. Resolution 2702 also noted that defendant had received Illinois Disaster Recovery Grant funds amounting to $2,650,000.00, though no language in the resolution commits those grant funds to the 167th Street project.

1 Although the resolution does not specify the meaning of “TIF,” we understand it to refer to tax increment financing funds, the details of which are not germane to this appeal.

¶5 On October 9, 2014, Robinson sent a letter to defendant’s mayor describing the physical details of the project and the anticipated funding sources. The project was to be paid for “utilizing a DCEO and EDP funding,” 2 and was to reconstruct and improve “167th Street from Center Street to Lowe Avenue with an omission at Halsted Street.” In the letter, Robinson noted plaintiff’s bid of $4,969,883.46 as the lowest bid received for the project and recommended that defendant award the contract to plaintiff. On October 13, 2014, defendant took Robinson’s advice and signed a contract with plaintiff accepting its bid in exchange for the roadwork. The contract did not detail the breakdown of funding sources and instead only referred to the total sum to be paid to plaintiff: $4,969,883.46. The Contract dictated that 10% of its value would be withheld by defendant until final payment on the project.

¶6 On January 21, 2015, a document labeled “Intergovernmental Agreement” (IGA) was signed by representatives of Cook County, the State of Illinois, and defendant. That agreement describes defendant as making “efforts to apply for and procure state funding for [the 167th Street project]” and notes that “without said funding the Project could not be completed.” Section 3 of the IGA detailed the funding sources for the project, and attached to the agreement as an exhibit was the following “Funding Breakdown” table:

2 These acronyms are again undefined. DCEO undoubtedly refers to the Illinois Department of Commerce & Economic Opportunity, which is responsible for dispersing funds from the 2008 Community Development Block Grand Disaster Recovery Program, also known as the CDBG-IKE. 2008 Community Development Block Grant Disaster Recovery (CDBG-DR) Program (DR-1800 IKE), Illinois Department of Commerce & Economic Opportunity, https://dceo.illinois.gov/communityservices/disasterrecovery/ikedisasterrecovery.html (last visited March 12, 2026). EDP refers to the Economic Development Program grant offered by the Illinois Department of Transportation for expanding access to “new or expanding industrial, manufacturing or distribution type companies.” Economic Development Program, Illinois Department of Transportation, https://idot.illinois.gov/programs-and-projects/grants/economic-development-program.html (last visited March 12, 2026).

*Requested

TOTAL DCEO Budget ITEM ESTIMATED Amount IDOT EDP COUNTY CITY COST Funds Funding SHARE SHARE

PhaseII $380,000.00 $30,000.00 $100,000.00 $0 $250,000.00 Design Engineering Right-of-Way $200,000.00 $200,000.00 $0 $0 ($200,000.00 Paid by City)

Construction $300,000.00 $0 $300,000 $0 $0 Engineering Construction $4,770,000.00 $2,270,000.00 $1,600,000.00 $900,000.00 $0 TOTAL $5,650,000.00 $2,500,000.00 $2,000,000.00 $900,000.00 $250,000.00

*Requested DCEO Grant Budget Amount $2,500,000.00 shall reimburse the COUNTY.

¶7 Per the IGA, whatever monies were used from the DCEO Budget Amount Funds, to a maximum budget of $2,500,000.00 would be used to reimburse Cook County. The County’s estimated cost beyond the $2,500,000.00, to be reimbursed by DCEO funds was $900,000.00. Defendant’s costs beyond DCEO and EDP funds were anticipated to be $250,000.00.

¶8 At his deposition, plaintiff’s president, Massoud “Mike” Farshchi (Farshchi), testified that plaintiff began work on the project sometime during the spring of 2015. Plaintiff was able to complete an estimated 75% of the project before Robinson instructed it to stop work because funds were not available to continue paying plaintiff. Farshchi averred separately that the damages to plaintiff amounted to $904,618.40, of which $248,494.17 was the retention withheld by defendant, $552,000.000 was various costs incurred by the project (including attorney fees), and $104,124.23 was the cost of traffic signal maintenance, usage, and repairs.

¶9 On June 22, 2015, the DCEO director sent a letter to Cook County to inform it that the appropriation that provided for the $2,500,000.00 DCEO grant had not been reappropriated

in any current capital bill, therefore the grant was being suspended effective June 30, 2015, and Cook County was obligated to cease any spending of grant funds on or before that date. The letter stated that “to the extent Cook County already has obligated grant funds, the terms of the Agreement require Cook County to use all efforts to cancel those obligations.” Cook County was required to submit “a financial expense report *** detailing all grantee expenditures and any other obligations which cannot be canceled after June 30, 2015.” Robinson provided the letter to plaintiff on June 30, 2015, with a brief letter stating that defendant had received the letter from Cook County the preceding day, and that the project was suspended until further notice. Farshchi testified that $625,478.84 of DCEO grant funds had been provided before the grant was suspended.

Free access — add to your briefcase to read the full text and ask questions with AI

Capitol Cement Company, Inc. v. City of Harvey, 2026 IL App (1st) 241045-U (Ill. Ct. App. 2026).

2026 IL App (1st) 241045-U (Capitol Cement Company, Inc. v. City of Harvey) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Addison v. Distinctive Homes, Ltd.
836 N.E.2d 88 (Appellate Court of Illinois, 2005)
People v. Janas
906 N.E.2d 686 (Appellate Court of Illinois, 2009)
Beling v. City of East Moline
144 N.E.2d 865 (Appellate Court of Illinois, 1957)
Nielsen-Massey Vanillas, Inc. v. City of Waukegan
657 N.E.2d 1201 (Appellate Court of Illinois, 1995)
HPI Health Care Services, Inc. v. Mt. Vernon Hospital, Inc.
545 N.E.2d 672 (Illinois Supreme Court, 1989)
Adames v. Sheahan
909 N.E.2d 742 (Illinois Supreme Court, 2009)
Senese v. Climatemp, Inc.
582 N.E.2d 1180 (Appellate Court of Illinois, 1991)
Ligenza v. Village of Round Lake Beach
478 N.E.2d 1187 (Appellate Court of Illinois, 1985)
People v. Phyllis B.
899 N.E.2d 218 (Illinois Supreme Court, 2008)
Reynolds v. Jimmy John's Enterprises, LLC
2013 IL App (4th) 120139 (Appellate Court of Illinois, 2013)
Gagnon v. Schickel
2012 IL App (1st) 120645 (Appellate Court of Illinois, 2012)
Norabuena v. Medtronic, Inc.
2017 IL App (1st) 162928 (Appellate Court of Illinois, 2017)
Lewis v. Lead Industries Ass'n
2020 IL 124107 (Illinois Supreme Court, 2020)
Vogt v. Round Robin Enterprises, Inc.
2020 IL App (4th) 190294 (Appellate Court of Illinois, 2021)
Dawkins v. Fitness International, LLC
2022 IL 127561 (Illinois Supreme Court, 2022)
Johnson v. Armstrong
2022 IL 127942 (Illinois Supreme Court, 2022)
Walworth Investments-LG, LLC v. Mu Sigma, Inc.
2022 IL 127177 (Illinois Supreme Court, 2022)
Ivey v. Transunion Rental Screening Solutions Inc.
2022 IL 127903 (Illinois Supreme Court, 2022)
Finn v. Project Resource Solutions, LLC
2024 IL App (1st) 221016 (Appellate Court of Illinois, 2024)