Cantor v. Detroit Edison Co.

428 U.S. 579, 96 S. Ct. 3110, 49 L. Ed. 2d 1141, 1976 U.S. LEXIS 4, 15 P.U.R.4th 401
Supreme Court of the United States·Decided July 6, 1976·No. 75-122·Published·Cited by 383 cases

Opinions

[581] Mr. Justice Stevens

delivered the opinion of the Court.

In Parker v. Brown, 317 U. S. 341, the Court held that the Sherman Act was not violated by state action displacing competition in the marketing of raisins. In this case we must decide whether the Parker rationale immunizes private action which has been approved by a State and which must be continued while the state approval remains effective.

The Michigan Public Service Commission pervasively regulates the distribution of electricity within the State and also has given its approval to a marketing practice which has a substantial impact on the otherwise unregulated business of distributing electric light bulbs. Assuming, arguendo, that the approved practice has unreasonably restrained trade in the light-bulb market, the District Court1 and the Court of Appeals2 held, on the authority of Parker, that the Commission’s approval exempted the practice from the federal antitrust laws. Because we questioned the applicability of Parker to this situation, we granted certiorari, 423 U. S. 821. We now reverse.

Petitioner, a retail druggist selling light bulbs, claims that respondent is using its monopoly power in the distribution of electricity to restrain competition in the sale of bulbs in violation of the Sherman Act.3 Discovery [582] and argument in connection with defendant’s motion for summary judgment were limited by stipulation to the issue raised by the Commission’s approval of respondent’s light-bulb-exchange program. We state only the facts pertinent to that issue and assume, without opining, that without such approval an antitrust violation would exist. To the extent that the facts are disputed, we must resolve doubts in favor of the petitioner since summary judgment was entered against him. We first describe respondent’s “lamp exchange program,” we next discuss the holding in Parker v. Brown, and then we consider whether that holding should be extended to cover this case. Finally, we comment briefly on additional authorities on which respondent relies.

I

Respondent, the Detroit Edison Co., distributes electricity and electric light bulbs to about five million people in southeastern Michigan. In this marketing area, respondent is the sole supplier of electricity, and supplies consumers with almost 50% of the standard-size light bulbs they use most frequently.4 Customers are billed for the electricity they consume, but pay no separate charge for light bulbs. Respondent’s rates, including the omission of any separate charge for bulbs, have been approved by the Michigan Public Service Commission, and may not be changed without the Commission’s approval. Respondent must, therefore, con[583] tinue its lamp-exchange program until it files a new tariff and that new tariff is approved by the Commission.

Respondent, or a predecessor, has been following the practice of providing limited amounts of light bulbs to its customers without additional charge since 1886.5 In 1909 the State of Michigan began regulation of electric utilities.6 In 1916 the Michigan Public Service Commission first approved a tariff filed by respondent setting forth the lamp-supply program. Thereafter, the Commission’s approval of respondent’s tariffs has included implicit approval of the lamp-exchange program. In 1964 the Commission also approved respondent’s decision to eliminate the program for large commercial customers.7 The elimination of the service for such customers became effective as part of a general rate reduction for those customers.

In 1972 respondent provided its residential customers with 18,564,381 bulbs at a cost of $2,835,000.8 In its accounting to the Michigan Public Service Commission, respondent included this amount as a portion of its cost of providing service to its customers. Respondent’s accounting records reflect no direct profit as a result of the [584] distribution of bulbs. The purpose of the program, according to respondent’s executives, is to increase the consumption of electricity. The effect of the program, according to petitioner, is to foreclose competition in a substantial segment of the light-bulb market.9

The distribution of electricity in Michigan is pervasively regulated by the Michigan Public Service Commission. A Michigan statute10 vests the Commission with “complete power and jurisdiction to regulate all public utilities in the state . . . .” The statute confers express power on the Commission “to regulate all rates, fares, fees, charges, services, rules, conditions of service, and all other matters pertaining to the formation, operation, or direction of such public utilities.” Respondent advises us that the heart of the Commission’s function is to regulate the “ 'furnishing ... [of] electricity for the production of light, heat or power ....’”11

The distribution of electric light bulbs in Michigan is unregulated. The statute creating the Commission contains no direct reference to light bulbs. Nor, as far as we have been advised, does any other Michigan statute authorize the regulation of that business. Neither the Michigan Legislature, nor the Commission, has ever made any specific investigation of the desirability of a lamp-exchange program or of its possible effect on competition in the light-bulb market. Other utilities regulated by the Michigan Public Service Commission do not follow the practice of providing bulbs to their customers at no [585] additional charge. The Commission’s approval of respondent’s decision to maintain such a program does not, therefore, implement any statewide policy relating to light bulbs. We infer that the State’s policy is neutral on the question whether a utility should, or should not, have such a program.

Although there is no statute, Commission rule, or policy which would prevent respondent from abandoning the program merely by filing a new tariff providing for a proper adjustment in its rates, it is nevertheless apparent that while the existing tariff remains in effect, respondent may not abandon the program without violating a Commission order, and therefore without violating state law. It has, therefore, been permitted by the Commission to carry out the program, and also is required to continue to do so until an appropriate filing has been made and has received the approval of the Commission.

Free access — add to your briefcase to read the full text and ask questions with AI

Cantor v. Detroit Edison Co., 428 U.S. 579, 96 S. Ct. 3110, 49 L. Ed. 2d 1141, 1976 U.S. LEXIS 4, 15 P.U.R.4th 401 (1976).

428 U.S. 579 (Cantor v. Detroit Edison Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Sanders v. Brown
504 F.3d 903 (Ninth Circuit, 2007)
Borough of Lansdale v. PP & L, INC.
503 F. Supp. 2d 730 (E.D. Pennsylvania, 2007)
Summit Water Distribution Co. v. Summit County
2005 UT 73 (Utah Supreme Court, 2005)
California Ex Rel. Lockyer v. Mirant Corp.
266 F. Supp. 2d 1046 (N.D. California, 2003)
Miranda v. Michigan
141 F. Supp. 2d 747 (E.D. Michigan, 2001)
General Motors Corp. v. Tracy
519 U.S. 278 (Supreme Court, 1997)
Tanner Electric Cooperative v. Puget Sound Power & Light
911 P.2d 1301 (Washington Supreme Court, 1996)
Mummelthie v. City of Mason City, Iowa
873 F. Supp. 1293 (N.D. Iowa, 1995)
Federal Trade Commission v. Ticor Title Insurance
504 U.S. 621 (Supreme Court, 1992)
Davis v. Southern Bell Telephone & Telegraph Co.
755 F. Supp. 1532 (S.D. Florida, 1991)
Town of Concord, Mass. v. Boston Edison Co.
721 F. Supp. 1456 (D. Massachusetts, 1989)
Sonitrol of Fresno, Inc. v. American Telephone & Telegraph Co.
629 F. Supp. 1089 (District of Columbia, 1986)
Capital Telephone Co. v. New York Telephone Co.
750 F.2d 1154 (Second Circuit, 1984)
Campbell v. City of Chicago
577 F. Supp. 1166 (N.D. Illinois, 1983)
City of Chanute v. Kansas Gas & Electric Co.
564 F. Supp. 1416 (D. Kansas, 1983)