Campagna v. Smallwood
This text of 428 So. 2d 1343 (Campagna v. Smallwood) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Warren CAMPAGNA, Joseph Campagna, Mary Robin, d/b/a Madeline Enterprises and Campagna Fiberglass Skiff Corporation
v.
William E. SMALLWOOD, d/b/a W.E. Smallwood, Builder, and Home Indemnity Insurance Company.
Court of Appeal of Louisiana, Fourth Circuit.
*1344 Manuel A. Fernandez, Chalmette, for plaintiffs-appellees.
Owen A. Neff, Peter S. Title, Sessions, Fishman, Rosenson, Boisfontaine & Nathan, New Orleans, for defendants-appellants.
Before SCHOTT, GARRISON and BARRY, JJ.
BARRY, Judge.
This dispute arose out of a contract for the construction of a pre-engineered metal building to be used in plaintiff Warren Campagna's skiff manufacturing business. The contract between plaintiff and defendant-contractor, William Smallwood, was executed on 10/22/75 and provided the work was to commence within 90 days and be completed within 110 days. The contract price was $38,500 payable in five "progress payments" at various stages of the construction with the final payment due upon occupancy or acceptance, whichever was sooner. The contract contained the usual contractor's warranty of good workmanship, "free from defects," and provided payments could be withheld on account of "defective work not remedied" or "unsatisfactory *1345 prosecution of the work by the contractor." The contract provided that "all claims or disputes arising out of this contract or the breach thereof shall be decided in accordance with the Construction Industry Rules of the American Arbitration Association."
The construction was to be completed in two stages so that the owner could occupy the north half of the building when completed while the contractor worked on the south half. Toward the end of construction plaintiff became dissatisfied with defendant's work and presented defendant's project manager with two "punch lists" of items for correction or additional work. The items were not completed to plaintiffs' satisfaction and on February 16, 1976, plaintiff presented defendant with a consolidated punch list of 19 items. Two days later Smallwood submitted a list of proposed solutions to the problems. While defendant's men were working on those items, plaintiff moved into the second half of the building and began using the entire building.
Although many of the problems were corrected, several major defects, including misalignment of roof panels, two misdrilled roof panels, misalignment of an end wall, inadequate support for a one ton capacity monorail, and torn ceiling insulation, were not corrected to plaintiff's satisfaction. Plaintiff and defendant met on May 26, 1976 to resolve the remaining problems, and the next day plaintiff's attorney sent defendant a letter asserting the building was incomplete and did not meet the standards of good workmanship. The letter referred to the 19 punch list items and other deficiencies, and stated, "Please accept this letter as notice that if those conditions are not corrected within the next five days, you will be placed in default on this contract ...." That letter apparently crossed in the mail with a letter from defendant's attorney expressing defendant's willingness to supervise additional corrections or to employ a metal building erection specialist to effect necessary repairs. Defendant received plaintiff's letter on 5/31/76 and went to the job site the next day with a crew, but plaintiff refused to allow defendant to perform any work. Defendant's attorney wrote plaintiff's attorney on July 21 and again on August 31 attempting to resolve the matter amicably, but plaintiff refused to allow defendant to attempt further repairs.
On January 24, 1977 plaintiff sued for $35,000.00 to correct the roof and other deficiencies, and for $10,000.00 in consequential damages. On February 9, 1977, defendant advised plaintiff of his desire to settle the dispute by arbitration in accordance with the contract's arbitration clause. Defendant filed an exception of prematurity or, alternatively, moved to stay the proceedings pending arbitration. The trial court overruled defendant's exception and denied the stay.
Defendant then filed an answer and reconventional demand seeking $8,700.00 for the unpaid balance on the contract, plus $2,016.76 for extra work and alleged losses. Judgment was rendered for plaintiff for $28,600.00, consisting of $18,600.00 for a new roof, $6,500.00 for corrections to the monorail, and $3,500.00 for reworking walls and installing new louvers. The trial court did not render a judgment on defendant's reconventional demand.
On appeal defendant assigns as error the lower court's failure to dismiss this suit and require arbitration, the implied rejection of his reconventional demand, the excessive amount of damages, and the failure to find plaintiff refused to mitigate his damages.
ARBITRATION
Louisiana has a strong public policy in favor of arbitration[1] which our courts have recognized in numerous cases dealing *1346 with the timeliness of a party's demand for arbitration. In Matthews-McCracken Rutland Corp. v. The City of Plaquemine, 414 So.2d 756, 757 (La.1982), the Louisiana Supreme Court reaffirmed the legislative mandate to the courts to order arbitration when suit has been filed despite an arbitration agreement. The Court further declared,
... Because of the strong policy favoring the right to demand arbitration, a party's otherwise explainable conduct should be construed against waiver of the right.
and noted that only in extreme cases have courts found waiver of the right to demand arbitration.
However, during oral argument defendant's counsel acknowledged that the record is complete and stated that a remand would only cause additional delays. The purpose of arbitration is to avoid costly and lengthy litigation and for speedy resolution of contractual disputes. Spencer v. Hoffman, 392 So.2d 190, 191 (La.App. 4th Cir. 1980). That purpose has long since been rendered moot in this case. We agree that no purpose would be served by setting aside the judgment and remanding for arbitration.
PROOF OF DEFECTS AND COST OF REPAIRS
In his Reasons the Trial Judge found the building was:
"1. Out of square.
2. That this resulted in roof misalignment or that the misalignment in the roof resulted in this unsquareness of the structure.
3. That multiple leaks resulted therefrom.
4. That there is a sag or deflection in the mono-rail [sic] system which does somewhat hinder production."
The trial court stated it "was impressed with the testimony ... of Mr. John F. McCaskell ... and bases its awards upon his testimony" and cited his testimony that two-thirds of the roof was misaligned and "the only correct remedy was a new roof." The court also awarded sums for "necessary corrections to the monorail" and for reworking the walls and installing new louvers.
We find the evidence conflicting as to the extent of the defects and the necessary corrections. Defendant's witnesses agreed that a substantial number (one-half to two-thirds) of the metal roof panels were misaligned, that there was at least a 1½ inch deflection in the roof area supporting each of two exhaust fans, that 18 roof sheets were originally misdrilled and two have still not been replaced, and that there were numerous water leaks into the building. Defendant-contractor and his expert, Mr. Puckett (a local contractor) testified that despite misalignment the roof could be made watertight at a cost of $1300-$1500.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
428 So. 2d 1343, Counsel Stack Legal Research, https://law.counselstack.com/opinion/campagna-v-smallwood-lactapp-1983.