Cajun Constructors, Inc. v. Velasco Drainage District

Procedural entryThis page is a short order in Cajun Constructors, Inc. v. Velasco Drainage District. Read the opinion of the Court — 2012 Tex. App. LEXIS 6759
Court of Appeals of Texas·Decided July 10, 2012·No. 14-11-00004-CV·Published

Opinion

Motion for En Banc Reconsideration Denied as Moot, Affirmed, and Substitute Opinion filed July 10, 2012.

In The

Fourteenth Court of Appeals

NO. 14-11-00004-CV

CAJUN CONSTRUCTORS, INC., Appellant

V.

VELASCO DRAINAGE DISTRICT, Appellee

On Appeal from the 412th District Court Brazoria County, Texas Trial Court Cause No. 61420

SUBSTITUTE OPINION

We deny Velasco Drainage District’s motion for en banc reconsideration as moot, withdraw our majority and dissenting opinions of May 1, 2012, and issue the following substitute opinion.

In this contract dispute, appellant Cajun Constructors, Inc. (“Cajun”) appeals from the trial court’s summary judgment in favor of appellee Velasco Drainage District (“Velasco”) and a jury’s subsequent award of attorney’s fees to Velasco. Cajun asserts that the trial court erred in granting summary judgment to Velasco because (1) Cajun complied with the notice requirements in the contract at issue or raised a fact issue with regard to the notice issue, (2) the notice provisions in the contract are legally void, and (3) Cajun’s unjust enrichment claim was improperly dismissed. Cajun further contends that the jury should not have been given an attorney’s fee question because Velasco did not recover damages and that Velasco was not entitled to recover attorney’s fees because it failed to segregate the fees. We affirm.

BACKGROUND

In September 2005, Velasco contracted with Cajun to provide labor and materials for the expansion of a pump station located in Brazoria County, Texas (the “project”). The original contract price was $12,974,000. Velasco concurrently contracted with Patterson Pump Company (“Patterson) to provide certain pumps, pump shafts, coupling nuts, and other materials for Cajun to install at the project. Patterson also supplied instructions for Cajun’s installation of the equipment. Cajun subcontracted its installation responsibilities to Louisiana Crane Company, L.L.C. (“Louisiana Crane”).

Velasco’s contract with Cajun (the “contract”) specified an agreed completion date; if Cajun failed to complete the project on time, Cajun agreed to pay liquidated damages of $750 per day. The contract also specified certain dispute resolution procedures under the Standard General Conditions of the Construction Contract (the “general conditions”):

10.05 Claims and Disputes A. Notice: Written notice stating the general nature of each Claim, dispute, or other matter shall be delivered by the claimant to ENGINEER and the other party to the Contract promptly (but in no event later than 30 days) after the start of the event giving rise thereto. Notice of the amount or extent of the Claim, dispute, or other matter with supporting data shall be delivered to the ENGINEER and the other party to the Contract within 60 days after the start of such event (unless ENGINEER allows additional time for claimant to submit additional or more accurate data in support of such Claim, dispute, or other matter). A Claim for an adjustment in Contract price shall be prepared in accordance with the provisions of paragraph 12.01.B. A Claim for an adjustment in Contract Time shall be prepared in accordance with the provisions of paragraph 12.02B. Each claim shall be accompanied by claimant’s written statement that the adjustment claimed is

2 the entire adjustment to which the claimant believes it is entitled as a result of said event. The opposing party shall submit any response to ENGINEER and the claimant within 30 days after receipt of the claimant’s last submittal (unless ENGINEER allows additional time). B. ENGINEER’S Decision: ENGINEER will render a formal decision in writing within 30 days after receipt of the last submittal of the claimant or the last submittal of the opposing party, if any. ENGINEER’s written decision on such Claim, dispute, or other matter will be final and binding upon OWNER and CONTRACTOR unless: 1. An appeal from ENGINEER’s decision is taken within the time and in accordance with the dispute resolution procedures set forth in Article 16; or 2. If no such dispute resolution procedures have been set forth in Article 16,[ 1] a written notice of intention to appeal from ENGINEER’s written decision is delivered by OWNER or CONTRACTOR to the other and to ENGINEER within 30 days after the date of such decision, and a formal proceeding is instituted by the appealing party in a forum of competent jurisdiction within 60 days after the date of such decision or within 60 days after Substantial Completion, whichever is later (unless otherwise agreed in writing by OWNER and CONTRACTOR), to exercise such rights or remedies as the appealing party may have with respect to such Claim, dispute, or other matter in accordance with applicable Laws and Regulations. C. If ENGINEER does not render a formal decision in writing within the time stated in paragraph 10.05.B, a decision denying the Claim in its entirety shall be deemed to have been issued 31 days after receipt of the last submittal of the claimant or the last submittal of the opposing party, if any. D. No claim for an adjustment in Contract Price or Contract Times (or Milestones) will be valid if not submitted in accordance with this paragraph 10.05. On May 16, 2008, Cajun filed Claim #1 – 96” Pump Sole Plate Grout Removal and Replacement, a claim for an adjustment in contract price of $139,157.00. On

1 Article 16, entitled “Dispute Resolution,” states: Dispute resolution methods and procedures, if any, shall be as set forth in the Supplementary Conditions. If no method and procedure has been set forth, and subject to the provisions of paragraphs 9.09 and 10.05, OWNER and CONTRACTOR may exercise such rights or remedies as either may otherwise have under the Contract Documents or by Laws or Regulations in respect of any dispute. The Supplementary Conditions of the Contract do not set forth any dispute methods and procedures.

3 September 5, 2008, Baker Lockwood JV, the Engineer referenced in the contract, denied this claim. On July 2, 2008, Cajun filed Claim #2 – Coupling Nut Removal and Installation, another claim for an adjustment in contract price of $163,540.00. Baker Lockwood denied this claim also on September 5, 2008. On August 5, 2008, Cajun submitted a revised Claim #3 – Fabrication Problems with the Patterson Pump Equipment, a claim for an adjustment in contract price of $68,164.00. 2 On September 10, 2008, Baker Lockwood rejected part of this claim, but recommended that Velasco approve an adjustment in contract price of $5,387.00 for this claim. On July 2, 2008, Cajun submitted Claim #4 – Time Impact Analysis, a claim for an adjustment in contract time of an additional 373 calendar days. Also on September 10, 2008, Baker Lockwood rejected the bulk of this claim, but recommended that Velasco approve an adjustment in contract time of an additional 30 days.

The project was substantially completed on May 23, 2008, which was 275 days later than the extended completion date. 3 After final completion of the project, Velasco withheld $206,250.00 (275 days x $750/day) from the final contract payment as liquidated damages.

This dispute arose in February 2008 when Cajun sued Louisiana Crane for breach of contract and negligence and later added claims against Patterson for negligence. Subsequently, the trial court dismissed Louisiana Crane due to a forum selection clause in the contract between Cajun and Louisiana Crane. On October 10, 2008, Cajun amended its petition to add Velasco as a defendant, seeking the money Velasco had withheld from Cajun’s final contract payment under theories of breach of contract and quantum meruit.

Free access — add to your briefcase to read the full text and ask questions with AI

Cajun Constructors, Inc. v. Velasco Drainage District, (Tex. Ct. App. 2012).

Cajun Constructors, Inc. v. Velasco Drainage District (Cajun Constructors, Inc. v. Velasco Drainage District) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
FM Properties Operating Co. v. City of Austin
22 S.W.3d 868 (Texas Supreme Court, 2000)
Criswell v. European Crossroads Shopping Center, Ltd.
792 S.W.2d 945 (Texas Supreme Court, 1990)
7979 Airport Garage, L.L.C. v. Dollar Rent a Car Systems, Inc.
245 S.W.3d 488 (Court of Appeals of Texas, 2007)
Guillot v. Hix
838 S.W.2d 230 (Texas Supreme Court, 1992)
M.D. Anderson Hospital & Tumor Institute v. Willrich
28 S.W.3d 22 (Texas Supreme Court, 2000)
Hohenberg Bros. Co. v. George E. Gibbons & Co.
537 S.W.2d 1 (Texas Supreme Court, 1976)
Nixon v. Mr. Property Management Co.
690 S.W.2d 546 (Texas Supreme Court, 1985)
Lundy v. Masson
260 S.W.3d 482 (Court of Appeals of Texas, 2008)
CDI Engineering Group, Inc. v. Administrative Exchange, Inc.
222 S.W.3d 544 (Court of Appeals of Texas, 2007)
T.F.W. Management, Inc. v. Westwood Shores Property Owners Ass'n
162 S.W.3d 564 (Court of Appeals of Texas, 2005)
Associated Indemnity Corp. v. CAT Contracting, Inc.
964 S.W.2d 276 (Texas Supreme Court, 1998)
AU Pharmaceutical, Inc. v. Boston
986 S.W.2d 331 (Court of Appeals of Texas, 1999)
MCI Telecommunications Corp. v. Texas Utilities Electric Co.
995 S.W.2d 647 (Texas Supreme Court, 1999)
Taylor v. Louis
349 S.W.3d 729 (Court of Appeals of Texas, 2011)
Tony Gullo Motors I, L.P. and Brien Garcia v. Nury Chapa
212 S.W.3d 299 (Texas Supreme Court, 2006)